SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Online)(Ker) 59027

IN THE HIGH COURT OF KERALA AT ERNAKULAM
C. JAYACHANDRAN, J
SUDHEESH A.T. – Appellant
Versus
THE DIRECTOR OF MINING AND GEOLOGY DEPARTMENT, GOVERNMENT OF KERALA – Respondent
WP(C) NO. 9795 OF 2023|WP(C) NO. 13492 OF 2023|WP(C) NO. 19300 OF 2023|WP(C) NO. 27035 OF 2023|WP(C) NO. 4510 OF 2024|WP(C) NO. 10121 OF 2024|WP(C) NO. 18741 OF 2024|WP(C) NO. 19999 OF 2024|WP(C) NO. 20487 OF 2024|WP(C) NO. 26197 OF 2024|WP(C) NO. 27291 OF 2024|WP(C) NO. 28314 OF 2024|WP(C) NO. 29919 OF 2024|WP(C) NO. 31355 OF 2024|WP(C) NO. 31398 OF 2024|WP(C) NO. 35059 OF 2024|WP(C) NO. 15219 OF 2025|WP(C) NO. 19599 OF 2025|WP(C) NO. 21958 OF 2025|WP(C) NO. 21964 OF 2025



Advocates:
For the Appellants/Petitioners: SRI.PHILIP J.VETTICKATTU, SMT.SAJITHA GEORGE, SMT.NEENU BERNATH, SRI.ENOCH DAVID SIMON JOEL, SRI.S.SREEDEV, SRI.RONY JOSE, SHRI.LEO LUKOSE, SRI.KAROL MATHEWS SEBASTIAN ALENCHERRY, SRI.DERICK MATHAI SAJI, SRI.V.GIRISHKUMAR, M.P.SREEKRISHNAN, SC, T.P.SAJAN, SPECIAL GOVERNMENT PLEADER (FOREST), SRI.M.JAYAKRISHNAN, CGC, SMT.O.M.SHALINA, DEPUTY SOLICITOR GENERAL OF INDIA, SRI.T.C.KRISHNA, SENIOR PANEL COUNSEL
For the Respondents: SRI.V.GIRISHKUMAR, M.P.SREEKRISHNAN, SC, T.P.SAJAN, SPECIAL GOVERNMENT PLEADER (FOREST), SRI.ACHUTH KRISHNAN R., CGC, SMT.O.M.SHALINA, DEPUTY SOLICITOR GENERAL OF INDIA

The Supreme Court ruling allows quarry operations near a wildlife sanctuary, invalidating SEIAA's requirement for wildlife clearance based on its prior orders, asserting precedence over regulatory conditions.

Headnote:(A) Environment (Protection) Act, 1986 - Conditions imposed by State Environmental Impact Assessment Authority (SEIAA) for environmental clearances - The Supreme Court allowed quarry operations located within 7.5 km of wildlife sanctuary based on its prior order that stipulated conditions concerning mining. The petitioners challenged the requirement for additional wildlife clearance. Court reasons that the previous order of the Supreme Court invalidates the condition requiring wildlife clearance under OM dated 17/05/2022. (Paras 1-10)

(B) Interpretation of Supreme Court Orders - The court highlighted that the Supreme Court's analysis and decisions on buffer zones applicable in previous analogous cases are binding and applicable here, allowing similar relief to petitioners. (Paras 2-8)

(C) Jurisdiction of the Court - The court reaffirmed that conditions imposed by SEIAA cannot supersede the authority of the Supreme Court's orders. (Paras 6-10)

Table of Content
1. introduction of the case and factual background. (Para 1 , 2)
2. understanding petitioners' reliance on supreme court's previous order. (Para 3)
3. discussions on legal arguments by the parties. (Para 4 , 5)
4. court's analysis of the supreme court's orders. (Para 6 , 7 , 8)
5. final judgment and directive by the court. (Para 10)

COMMON JUDGMENT

In this batch of 21 cases, all the writ petitioners essentially seek the same relief, which pertains to a condition incorporated in the Environmental Clearance issued by the State Environmental Impact Assessment Authority ('SEIAA' for short). One such condition, incorporated in the case of petitioner in W.P.(C) No.28314/2024, is extracted here below:

“Condition No.5: Since, the project is located within 10km of Peechi Vazhani Wild Life Sanctuary and Chimmony Wild Life Sanctuary, the project proponent has to obtain Wild Life Clearance from the SCNBWL as per the OM dated 17/05/20225 of MoEF & CC as per the directions in the Hon’ble Supreme Court judgment dated 26/04/2023 in I.A.13177 of 2022 before the commencement of mining”.

In respect of a similar condition imposed in the Environmental Clearance issued by SEIAA, the Hon’ble Supreme Court passed a recent Order dated 29.05.2025 in I.A.Nos.132289/2025, 132290/2025 and 138819/2025 in W.P.(C) No.202/1995. As per the said Order, the operations in the Petitioner’s quarry, which is located 7.5 km away from the Peechi-Vazhani Wildlife Sanctuary, were permitted, repelling the objections of the Ministry of Environment, Forest and Climate Change ('MoEF & CC', for short) in this regard. The petitioners herein seek similar treatment in accord with the said Order of the Supreme Court.

2. Heard the learned counsels for the petitioners; learned Standing Counsel for SEIAA,; learned Central Government Counsel for MoEF & CC; learned Special Government Pleader (Forest) and the learned Government Pleader. Perused the records.

3. As regards the interpretation of the said Order, considerable arguments were advanced by the respective parties. While the petitioners contend that similar condition, imposed by the SEIAA in the Environmental Clearance is the subject matter of these Writ Petitions, wherefore, the above Order dated 29.05.2025 of the Hon'ble Supreme Court would squarely govern the situation, learned Standing Counsel for SEIAA would submit that the above Order cannot substitute the requirements of O.M. dated 17.05.2022 of the MoEF & CC, as also, the directions contained in the earlier Orders passed by the Hon'ble Supreme Court in the same Writ Petition.

4. This Court will straight away refer to the objections raised by the learned Standing Counsel for SEIAA. Learned Standing Counsel would submit that three Orders have been passed by the Hon'ble Supreme Court in In Re: T.N.Godavarman Thirumulpad v. Union of India and Others. The first is one dated 3rd June, 2022 (hereinafter referred to as ‘G.V-I’). Reference to various paragraphs of G.V-I is required and it is clarified that the paragraph numbers being referred hereunder are as contained in the Order (G.V-I) downloaded from the Supreme Court portal. Learned Standing Counsel invited the attention of this Court to paragraph no.44 of G.V-I Order, which contains several directions. As per paragraph no.44(a), a minimum distance of 1 km is prescribed as Eco-Sensitive Zone (ESZ) measured from the demarcated boundary of a Protected Forest (National Park or Wildlife Sanctuary) for conducting the activities prescribed in the Guidelines dated 09.02.2011. Paragraph no.44(b) deals with the situations, where ESZ has already been prescribed by law, which goes beyond 1 km buffer zone. In such cases, the wider buffer zone prescribed under the statutory instrument for the particular National Park or Wildlife Sanctuary has to be maintained. Paragraph no.44(d) is a complete prohibition for mining within the National Parks and Wildlife Sanctuaries. Paragraph no.44(e) deals with activities already undertaken within

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top