SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Ker) 543

IN THE HIGH COURT OF KERALA AT ERNAKULAM
C. JAYACHANDRAN, J.
Puthiyaparampil Enterprises  - Appellant
Versus 
The District Geologist, The Mining And Geology Department – Respondent
WP(C) NO. 43736 OF 2025
Decided on : 22-01-2026

Advocates Appeared:
For the Appellant : SHRI.PHILIP J.VETTICKATTU SMT.NEENU BERNATH SHRI.SAJU S. DOMINIC
SHRI.MANU SANTHOSH
For the Respondent: ADV. SRI.AJITH VISWANATHAN, GOVERNMENT PLEADER

A governmental order lacks retrospective effect unless explicitly stated, impacting procedural compliance in administrative decisions.

Headnote:This judgment pertains to WP

(C) NO. 43736 OF 2025, where the petitioner challenges the insistence of a fresh survey under a Government Order issued post the submission of its final quarry closure plan. The court finds merit in the petitioner’s arguments that the government order cannot be applied retroactively to affect the previously submitted documents. The court emphasizes that a governmental regulation is generally prospective unless expressly stated otherwise. The requirement for a new survey was deemed inapplicable to the closure plan submitted before the issuance of the new governmental directive. Ultimately, the request for reevaluation under the prior legislation was directed, and the impugned communication was set aside.

Table of Content
1. petitioner's quarrying operations and legal challenges. (Para 1)
2. governmental orders' prospective application. (Para 3)
3. order to reconsider based on previous regulations. (Para 4)

JUDGMENT :

C. JAYACHANDRAN, J.

1. The petitioner has been conducting quarrying operations since 2008 on the basis of valid quarrying permits issued. The quarrying operations got exhausted by 30.05.2022, namely, the date of expiry of the Environmental Clearance. Ext.P2 demand notice was issued to the petitioner alleging excess excavation within the permitted area. The same was challenged and ultimately got settled in the Adalat Scheme of the Government, vide Ext.P3. A revised notice was issued vide Ext.P4 and the petitioner remitted the entire dues, as could be seen from Exts.P5 and P6. A final quarry closure plan was submitted vide Ext.P7 on 27.11.2024 in respect of the area covered by Ext.P1 permit. Much later, the 1st respondent issued the impugned Ext.P8 communication insisting for a fresh survey based on the Drone LiDAR method, introduced vide Ext.P9 Government Order (S.R.O. No.161/2025) issued on 14.02.2025. The short point canvassed by the learned counsel for the petitioner is that the G.O issued on 14.02.2025 cannot govern Ext.P7 final quarry closure plan submitted on 27.11.2024. The final quarry closure plan/Ext.P7 has to be acted upon based on the law as it existed at the time of submission of such closure plan. Even in Ext.P9, the survey is contemplated only at the time of submission of the final quarry closure plan; and inasmuch as the final quarry closure plan precedes the date of Ext.P9, the methodology contemplated in Ext.P9 cannot be pressed into service, is the point moved.

2. Learned Government Pleader would submit that a statement has been filed opposing the relief sought for in this Writ Petition.

3. Having heard the learned counsel for the petitioner and the learned Government Pleader, this Court finds substantial merit in the submissions made by the learned counsel for the petitioner. It goes without saying that a Government Order can only be treated as prospective, unless specifically made retrospective. There is no quarrel that Ext.P9 G.O was issued only on 14.02.2024. There is also no quarrel with respect to the date of application of final quarry closure plan vide Ext.P7, that is to say, 27.11.2024. Therefore, the requirements of Ext.P9 cannot be insisted upon for accepting Ext.P7 final quarry closure plan, which was filed as early as on 27.11.2024. A, more or less, similar issue has been considered by this Court in W.P.(C) No.23811/2025. As per judgment dated 05.08.2025, the legal question has been clarified as regards the operation of the Government Order, which has been produced in the instant Writ Petition as Ext.P9.

4. In the circumstances, Ext.P8 will stand set aside. There will be a direction to the 1st respondent/Geologist to consider Ext.P7 application in the light of the law and the state of affairs prevailing as on the date of Ext.P7 application, expeditiously, at any rate, within a period of two months from the date of receipt of a copy of this judgment. The petitioner will produce a copy of this judgment before the 1st respondent, for compliance.

This Writ Petition will stand disposed of, as above.

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top