2026 Supreme(Online)(Ker) 13687

IN THE HIGH COURT OF KERALA AT ERNAKULAM
ZIYAD RAHMAN A.A., J
M/S. ANCHOR STRUCTURALS ENGINEERS & CONTRACTORS – Appellant
Versus
KERALA STATE ELECTRICITY BOARD LIMITED – Respondent
WP(C) NO. 4486 OF 2026



Advocates:
For the Appellants/Petitioners: SRI.THOMAS T.VARGHESE, SRI.PHILIP T.VARGHESE, SMT.ACHU SUBHA ABRAHAM, SMT.V.T.LITHA, SMT.K.R.MONISHA, SMT. NITYA R., SMT.JINCY C.J.
For the Respondents: SRI.AJIT JOY, SC

The decision affirms the need for timely action by public authorities in finalizing claims of contractors under contractual agreements.

Headnote:The petitioner, M/S. ANCHOR STRUCTURALS ENGINEERS & CONTRACTORS was awarded a contract for the Balance Civil Works of Tunnel, Surge Shaft, Pressure Shaft, Penstock, Power House and allied works. The completion of work is noted, but disputes regarding final settlement are delayed. The Court determined to require the competent officer of the first respondent to address Ext.P10 representation within one month, allowing the petitioner a hearing opportunity. The key issues revolved around the delay in finalization and the requisite compliance with procedural safeguards. The Court stated, 'Such an order shall be passed within a period of one month from the receipt of copy of this judgment.'

Table of Content
1. overview of contract award and completion status. (Para 1)
2. court's directive to expedite claim finalization. (Para 2)

JUDGMENT

The petitioner was awarded with a contract work for completing the ‘Balance Civil Works of Tunnel, Surge Shaft, Pressure Shaft, Penstock, Power House and allied works’ of Pallivasal Extension Scheme. According to the petitioner, the work was completed within the extended period of time. However, certain claims of the petitioner relating to the final settlement of the amount, were considered by the competent officers in Exts.P2, P4, P7 and P8 minutes and a favourable decision is taken which is in the process of final consideration.

2. According to the petitioner, Ext.P6 Board Order also supports the claim of the petitioner in respect of certain heads. The grievance of the petitioner is with regard to the delay in finalizing the said claims. Now, the petitioner has already submitted Ext.P10 representation highlighting its grievances, which is now pending before the 2nd respondent. The limited relief sought by the petitioner is to direct the competent officer under the 1st respondent to consider the same and pass appropriate orders.

After hearing the learned counsel for the petitioner and the learned Standing Counsel for the respondents, I am inclined to dispose of this writ petition. Accordingly, it is ordered that the 1st respondent shall ensure that the competent officer of the 1st respondent takes up Ext.P10 and appropriate orders are passed there on, after giving the petitioner an opportunity for being heard. Such an order shall be passed within a period of one month from the receipt of copy of this judgment.

Sd/-

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top