SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Online)(Ker) 18449

IN THE HIGH COURT OF KERALA AT ERNAKULAM
ZIYAD RAHMAN A.A., J
K.P.ABRAHAM – Appellant
Versus
HINDUSTAN PREFAB LTD – Respondent
WP(C) NO. 43536 OF 2024



Advocates:
For the Appellants/Petitioners: SRI.C.S.GOPALAKRISHNAN NAIR, SMT.CHANDINI G.NAIR
For the Respondents: SMT.MOLLY JACOB, SRI.SANTHOSH PETER (MAMALAYIL), SRI. BINOY DAVIS, G.P

The Court determined that contractual disputes involving factual questions requiring evidence must be resolved outside the writ jurisdiction under Article 226 of the Constitution.

Headnote:(A) Constitution of India - Article 226 - Writ jurisdiction - Contractual disputes involving questions of fact - Petitioner, a Government contractor, sought relief for alleged non-payment of dues and delay in project completion. Court held that matter involves disputed facts needing evidence, thus outside writ jurisdiction. (Paras 16 and 17)

(B) Writ of Mandamus - Scope - A writ cannot be issued in cases where disputes of fact arise which require factual adjudication beyond the court's jurisdiction under Article 226. (Paras 8 and 15)

Facts of the case:
The petitioner, a Government contractor, was contracted to construct a mall by the 1st respondent. Delays occurred due to changes in work requirements, floods, and the pandemic, with disputes over payment still outstanding.

Findings of Court:
The 1st respondent's detailed rebuttal to the petitioner's claims indicates unresolved disputed questions of fact making writ relief inappropriate.

Issues: Whether the delays in project completion were justifiable and if the amounts claimed by the petitioner were due.

Ratio Decidendi: The court emphasized that matters raising disputed facts must be resolved by appropriate forums other than a writ court under Article 226, noting the need for evidentiary adjudication.

Result: Writ petition dismissed.

Table of Content
1. details of the construction contract and delays. (Para 1 , 2 , 3)
2. petitioner's claims for reliefs stated. (Para 4)
3. respondent's counter and opposition to claims. (Para 5 , 8)
4. court's consideration of arguments and context. (Para 6 , 7 , 9)
5. details of allegations and evidence regarding claims. (Para 10 , 12 , 13)
6. court's reasoning on jurisdiction and disputed facts. (Para 15 , 16 , 17)

JUDGMENT

The petitioner is an approved Government Contractor, who used to undertake Civil Contracts awarded by the Central Public Works Department and other Government Departments. As part of the same, the petitioner undertook the work awarded by the 1st respondent, for the construction of a mall named “Suburban Mall” at Piravom in Ernakulam District. The said Mall was being constructed by the 1st respondent for the purpose of the 3rd respondent, the Kerala State Civil Supplies Corporation and the 1st respondent was the implementing agency. Based on the same, an agreement was executed on 25.02.2015, between the petitioner and the 1st respondent. The 2nd respondent is the Regional in charge of the 1st petitioner and as per the terms and the conditions of the same, the work ought to have been completed within a period of 15 months from the date of letter of Award. Thus, the period within which the work ought to have been completed was 19.03.2016.

2. According to the petitioner, after commencement of the work, a necessity arose, for altering the manner in which the piling work was to be done, as it was found that, instead of ordinary piling method, raft foundation will have to be made. There occurred some delay in completing the work on account of the same and thus, the work could be completed only in the year 2020. It is also the case of the petitioner that, in the meantime, despite the fact that the 1st respondent was under an obligation to make the payment towards the part bills within a specified time, the same was also not affected and this has also contributed to the delay. The other reasons the petitioner highlighted for causing the delay are, the flood that occurred in the year 2018 and also the Covid-19 pandemic.

3. The petitioner also places reliance upon Ext.P2-Government Order issued, where the question of delay in completing the project was considered by the Government and found that the 1st respondent was responsible for the lapses, including that of additional cost for providing raft foundation, which was due to the unprofessional management, and in the said order, appropriate action and penalty was suggested to be imposed against the 1st respondent. Thus, according to the petitioner, the change in the nature of the piling work was due to the reasons attributable to the 1st respondent. Ext.P2 Government Order would go to show that the responsibility has been imposed upon the 1st respondent. However, the 1st respondent had passed on the said liability upon the petitioner. Ultimately, the work was completed on 09.09.2020 and Ext.P6 is the completion certificate evidencing the same. The grievance of the petitioner is that, despite the fact that, the work was completed, even though belatedly, the amounts payable to the petitioner towards the bills have not been released so far. Apart from the payments covered by the bills, the petitioner also submits that the amount towards the GST component in the contract, the amount deducted from the petitioner towards GST, amount payable towards service tax for the period prior to 01.07.2017, the security deposit furnished by the petitioner, etc., are also yet to be released.

4. In such circumstances, the petitioner had earlier approached this Court by filing a writ petition which was numbered as W.P.(C)No.25111/2023, and it culminated in Ext.P17 judgment. As per the said judgment, this Court directed the 1st respondent herein, to take a each of his claims, adverting to every documents and orders to be produced by him during the afore exercise. Later, the petitioner submitted C

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top