SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Online)(Ker) 18888

IN THE HIGH COURT OF KERALA AT ERNAKULAM
MR. SOUMEN SEN, CJ, MR. SYAM KUMAR V.M., J
PERUMPADANNA JANAKIYA VIKASANA SAMRAKSHANA SAMITHI – Appellant
Versus
UNION OF INDIA – Respondent
WP(PIL) NO. 107 OF 2025



Advocates:
For the Appellants/Petitioners: SRI.S.GOPAKUMAR, SMT.T.M.BINITHA, SMT.SREELAKSHMI S.J.
For the Respondents: SHRI.K.R.RAJKUMAR, SHRI.ANOOP V.NAIR, SHRI.N.MANOJ KUMAR

The court upheld that satisfactory progress in public infrastructure projects can resolve grievances, reflecting the importance of cooperation among authorities.

Headnote:The judgment involved an analysis of the laws relevant to highway construction and public interest litigations. The case addressed the construction of an underpass and discussions with local authorities. The court found that the grievances raised by the writ petitioner had been adequately addressed. The main issues included the compliance with safety standards in the construction process. The court emphasized the progress made under the existing recommendations and endorsed the collaborative approach with the local authorities. The WP(PIL) stands disposed of. There will be no order as to costs.

In view of the decisions/recommendations recorded in the minutes of the meeting held on 09.01.2026 under the Chairmanship of the District Collector, which inter alia includes a decision/recommendation with regard to construction of the Underpass at Chakkarakadavu, and the affidavit filed by the NHAI affirmed on 26.02.2026 stating that the modifications can be carried out on the basis of the sketch to be received from the Municipality concerned indicating the existing entry, exit and ‘0’ points and in view of the assurance of the District Collector with regard to the use of the service road by the light motor vehicles and also, having regard to the fact that the Project Director acknowledged that the issue with regard to the construction of ramps and certain locations would be examined and appropriate feasible solution will be explored in accordance with the technical standards and safety requirements and the NHAI would also consider any proposal along with the estimate submitted by the Municipality with regard to the drainage along with the service road, we are satisfied with the progress made in this regard and we are of the view that the grievance of the writ petitioner has been adequately addressed.

The WP(PIL) stands disposed of. There will be no order as to costs.

Sd/-

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top