2017 Supreme(Online)(KER) 37328
HIGH COURT OF KERALA
P.D.RAJAN, J
METRO TRADING COMPANY – Appellant
Versus
ZILLA SAINIK WELFARE OFFICER PALAKKAD – Respondent
AS 526 1996
Important Points
Subject
Civil Law - Property Law
Act Referred
Headnote
Rent - Recovery of Arrears - Act Section List - The court evaluated the oral lease agreement against the statutory provisions, determining that the government guidelines for rent fixation rendered the informal agreement unenforceable and influenced the dismissal of the appeal.
Fact of the Case:
The appellant entered into an oral lease agreement with the respondent for a building, but disputes arose over rental payments due to delayed fixation by the government, leading to a suit for recovery of arrears after non-payment.
Issues: Whether an oral lease agreement can be enforced for recoveries when the fixing of rent is subject to governmental regulations.
Ratio Decidendi: The court held that the informal agreement violated statutory provisions and could not be enforced, especially since the authority to fix rent lay with the government, aligning with the findings in the lower court.
Final Decision: The appeal was dismissed with no merits found.
SRI.K.MOHANA KANNAN, SRI.B.R. MURALEEDHARAN
J U D G M E N T
This appeal is preferred by the plaintiff against the judgment in O.S. No.14 of 1992 of the Subordinate Judge, Palakkad for recovery of arrears of rent. The appellant's case is that on 10.7.1987, the 1st respondent took on lease, door No.24/905 of Koppam amsom to Jilla Sainik Board, Palakkad by an oral lease and the monthly rent was agreed as Rs.800/-. The lease period was for three years and for continuing the lease period, the rent was agreed to be increased by 16%. The first respondent informed that he is competent to represent the Government and he paid rent for six months. There was no payment of rent and no response from the side of respondents. In the circumstance, he filed RCP No.66 of 1991 before Rent Control Court, Palakkad for eviction on the ground of arrears of rent. He also filed the present suit for recovery of Rs.41,400/- with 6% interest from the date of the suit.
2. In the trial court, defendants resisted the suit by filing a written statement and contended that rent could be paid only at the rate fixed by the Government according to PWD rules and Government orders. The delay in non payment of rent was due to non fixation of rent by PWD which was informed to the plaintiff. Subsequently, first defendant shifted from the office building on 6.12.1991 and PWD has fixed the rent of the building at the rate of Rs.244/- per month and the actual amount of rent is Rs.12,932/-. Out of that, he paid Rs.4800/- and the balance is only Rs.8132/-.
3. Both parties adduced both oral and documentary evidence. The plaintiff was examined as PW1 and his documents were marked as Ext.A1 to A8. The defendant's evidence consists of the oral testimony of DW1 and Ext.B1 to B4. The learned Subordinate Judge decreed the suit for a sum of Rs.8,132/- with interest at the rate of 6% per annum from the date of suit till realisation with cost of the suit. Being aggrieved by that, plaintiff preferred this appeal.
4. The possession of the building for a period of three years on the basis of an oral lease was admitted by both parties. PW1, in his evidence, admitted that he received Rs.852.78/- per month as rent for six months in the year 1988-1989. As per Ext.A4, respondent admitted that arrears could be paid only after rent is approved by Government. It is clear from Ext.B1 that rent could be fixed only on the basis of the guidelines issued by the Government. A private building can be taken on rent for departmental use if the owner of the building accepts the rent fixed by PWD. Lower court observed that no agreement was entered into between the appellant and respondents agreeing the claimed rate, therefore, A2 agreement has no legal validity. It is also clear that the 1st respondent has no authority to execute a lease agreement fixing rent with the appellant without the concurrence of the Government. There is no difficulty for the appellant for getting the enhanced rent provided that the enhanced rate has to be approved by the government, which was communicated to the appellant as per Ext.B3 letter. As per Ext.B3, there is no difficulty in sanctioning special rate, provided the reason has also to be stated by the Government while fixing the enhanced rate. In Ext.B4 rent certificate the monthly rent fixed by the Assistant Executive Engineer, PWD, Palakkad was Rs.244/- per month. Appellant contended that the fixed rate is a meagre amount, which is not as per the rate agreed with the respondent. Even though such a contention was made by the appellant, the respondent cannot go beyond Exts.B1 to B4 documents.
5. In this context, the learned counsel appearing for the appellant submitted that the doctrine of promissory estoppal is applicable since the appellant and respondent agreed the rate of Rs.800/- per month and the arrears was Rs.41,400/- with 6% interest. Normally the doctrine of promissory estoppal cannot be invoked for enforcement of a promise which is made contrary to law. The respondent is not the competent authority to make an