SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Online)(Ker) 28604

IN THE HIGH COURT OF KERALA AT ERNAKULAM
Ziyad Rahman A.A., J
Vijay Construction – Appellant
Versus
State of Kerala – Respondent
WP(C) NO. 34063 OF 2025 | WP(C) NO. 19728 OF 2024



Advocates:
For the Appellants/Petitioners: SHRI.BLAZE K.JOSE, SMT.GAYATHRI A.L., SMT.AFRUS SHAHANA, SHRI.NIKHIL SANJAY, SMT.TREESA ROSE, SMT.AIRINE JOBY
For the Respondents: SHRI.HARIKRISHNAN R., SMT.DIVYA C BALAN, SHRI.P.D.SUBRAMANIAN NAMPOOTHIRI, SHRI.K.N.SUGATHAN, SHRI.SIDHARTH BIMAL, SMT.GOWRI V. NAIR, SRI. BINOY DAVIS, GOVT. PLEADER

Contract termination invalid due to delayed, uncommunicated extension order despite genuine delay reasons; extension granted to original contractor.

Headnote:(A) PWD Manual and contract terms - Termination of contract at risk and cost - Extension of time - Communication of extension order - Where field officers found reasons for delay genuine and recommended extension on 5.11.2022, but order issued only on 24.1.2023 extending time to 25.1.2023 without communication to contractor until after expiry, effective extension was only one day, rendering termination unjustifiable. (Paras 15, 16)

(B) Principles of natural justice and administrative fairness - Contractor's repeated willingness to complete work at original rates ignored - Re-tender at 47.91% above PAC against State interest - Termination without justifiable grounds, especially leading to penalty and potential blacklisting, not bona fide. (Paras 16, 17)

Facts of the case:
Petitioner, an A Class PWD contractor, awarded road work contract on 21.01.2021 for Rs.1,72,04,015.06/- below PAC. Delays due to COVID-19, material scarcity, monsoon; extensions granted up to 26.10.2022. Further extension to 25.01.2023 recommended by field officers but issued late without proper communication, leading to termination, penalty, and re-tendering.

Findings of Court:
Impugned orders quashed; extension of minimum two months directed to complete work at original rates.

Issues: Validity of contract termination despite genuine delay reasons accepted by field officers; propriety of delayed and uncommunicated extension order; impact of contractor's willingness versus higher re-tender costs.

Ratio Decidendi: Termination at risk and cost unsustainable if extension order delayed without explanation and not communicated timely, frustrating effective use of extended period; State interest demands allowing original contractor to complete at lower rates when willing.

Result: Writ petition allowed.

Table of Content
1. contract delays due to covid and material scarcity; field officers recommended extension. (Para 2 , 3 , 4)
2. non-communication of extension led to termination; prior writs set aside orders. (Para 5 , 6 , 7 , 8)
3. penalty imposed; re-tender at high cost; counter averments on extensions. (Para 9 , 10 , 11 , 12)
4. petitioner's challenge to termination based on delayed extension. (Para 13 , 14)
5. delayed uncommunicated extension invalidates termination; direct further extension. (Para 15 , 16 , 17)

JUDGMENT

[WP(C) Nos.34063/2025 & 19728/2024]...

Both these writ petitions are filed by the very same petitioner and the issues involved in these writ petitions are touching upon the termination of contract entered into between the petitioner and the 3rd respondent herein. W.P(C)No.19728 of 2024 is petitioner challenging Ext.P17 order dated 16.04.2024 passed by the 3rd respondent, by which, the termination of the contract entered into between the petitioner and the 3rd respondent was ordered. W.P(C)No.34063 of 2025 is filed by the petitioner challenging Exts.P25 and P26. Ext.P25 order passed by the Government and Ext.P26 consequential order was passed by the Chief Engineer. (W.P(C)No.34063 of 2023 is treated as the leading case and hereinafter exhibits and parties are referred to as prescribed in the said writ petition).

2. The facts that led to the filing of this writ petition are as follows:

The petitioner is an ‘A Class’ contractor under the PWD and the petitioner was entrusted with the work of Chithrapuzha-Ponjassery road from CH 3/380 to 8/000 for an amount of Rs.1,72,04,015.06/-, which was below the PAC. An agreement was executed on 21.01.2021 and the site was handed over to the petitioner on 30.01.2021. As per the terms and conditions of the agreement, the petitioner ought to have completed the work, within six months and the said period was expired on 29.07.2021. According to the petitioner, because of various reasons including, COVID-19, scarcity of materials on account of shut down of quarries due to the ban imposed during the COVID-19 period, monsoon etc, the petitioner could not complete the work and therefore the extensions of time were sought. The same was granted from time to time up to 26.10.2022.

3. The petitioner had submitted the application for further extension of the period beyond 26.10.2022 as per Ext.P1 application dated 25.10.2022. The reasons cited by the petitioner included, non availability of the materials from Cochin Refinery and other stone crushing units owing to the reasons attributable to the Covid-19 pandemic. After considering Ext.P1 application, the 5th respondent, the Assistant Engineer, recommended extension of time, after finding that, the request of the petitioner is genuine. Thus, the extension was recommended upto 25.1.2023. The 4th respondent also recommended the extension of time upto 25.1.2023 without the risk and cost of the petitioner, by observing that, the reasons cited by the petitioner are genuine. Ext.P2 is the recommendation made by the 5th respondent and Ext.P3 is the recommendation made by the 4th respondent, which are dated 5.11.2022.

4. According to the petitioner, despite the above recommendations, the 3rd respondent did not act upon the same immediately thereafter, which prompted the petitioner to submit several representations. Ultimately, the petitioner was served with Ext.P8 E-mail dated 25.2.2023, issued by the 2nd respondent intimating the petitioner that, even though a hearing notice was issued to the petitioner directing the petitioner to attend the office of the 2nd respondent, the petitioner failed to appear before the said officer and therefore the petitioner was again directed to appear for hearing before the 2nd respondent on 28.2.2023. The said communication was forwarded to the petitioner in the official e-mail Id of the petitioner viz., vijayconstructions85@gmail.com. However, according to the petitioner, the hearing notice referred to in Ext.P8, was n

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top