2025 Supreme(Online)(Ker) 74014
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT THE HONOURABLE MR.JUSTICE MURALI PURUSHOTHAMAN
TUESDAY, THE 26TH DAY OF AUGUST 2025 / 4TH BHADRA, 1947
CRP(LR) NO. 336 OF 2013
AGAINST THE ORDER OF TALUK LAND BOARD, PARAVUR IN NO.SM-1/92/PRR DATED 25.04.2013
PETITIONER:
ALWAYE SETTLEMENT, ALWAYE
REPRESENTED BY ITS MANAGER
O.V.MATHAI, OFFICE OF THE ALWAYE SETTLEMENT,
ALWAYE.
BY ADV SRI.S.SUJIN
SRI. N.N SUGUNAPALAN
RESPONDENTS:
1 TALUK LAND BOARD, PARAVUR,
REPRESENTED BY ITS CHAIRMAN
OFFICE OF THE TALUK LAND BOARD,
PARAVUR.
2 THASILDAR, PARAVUR
ERNAKULAM DISTRICT – 682 513.
3 TAHSILDAR, MUKUNDAPURAM
ERNAKULAM DISTRICT – 683 141.
4 STATE OF KERALA
REPRESENTED BY CHIEF SECRETARY
SECRETARIAT,
THIRUVANANTHAPURAM - 695 001.
*ADDL. R5 BISHOP B.N. FENN
AGED 60 YEARS
S/O. LATE FENN, BISHOP IN NORTH KERALA,
C.S.I SHORNUR P.O,
PALAKKAD DISTRICT – 628 001.
(ADDL. R5 IS IMPLEADED VIDE ORDER DATED 29/06/2015 IN IA.NO.1382/2014.)
*ADDL. R6 SUNRISE KOCHI
PROJECT OFFICE, DIT BUILDING, THURUTHY,
FORT KOCHI, PIN – 682 001,
REPRESENTED BY ITS PROJECT COORDINATOR
MOHAMMED BASHEER.
*IMPLEADED AS ADDL.R6 AS PER ORDER DATED 28.07.2025 IN I.A. 1564/2018.
*ADDL. R7 KARUMALOOR GRAMA PANCHAYATH
KARUMALOOR P.O, ERNAKULAM - 683 511,
REPRESENTED BY ITS SECRETARY
*IMPLEADED AS ADDL.R7 AS PER ORDER DATED 28.07.2025 IN I.A.1/2019.
*ADDL. R8 MALANKARA MARTHOMA SYRIAN CHURCH
REPRESENTED BY REV. ABEY T. MAMMEN,
SABHA SECRETARY, MARTHOMA SABHA OFFICE,
THIRUVALLA P.O., PATHANAMTHITTA DISTRICT.
*IMPLEADED AS ADDL.R8 AS PER ORDER DATED 26.08.2025 IN I.A.2/2025.
BY ADVS.
SRI. T.R.RAJAN
SRI. C.ANIL KUMAR
SRI. M.K.DILEEPAN
SRI. P.K.SAJEEV
SRI. JACOB GEORGE
SRI. S.KARTHIK MENON
SMT. A.K.PREETHA
SRI. ASWIN SETHUMADHAVAN – SPL. GP
THIS CRP (LAND REFORMS ACT) HAVING COME UP FOR ADMISSION ON 26.08.2025, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
ORDER
The revision petition is disposed of.
Sd/-
MURALI PURUSHOTHAMAN
JUDGE
SPR
This revision petition is filed against the order of the Taluk Land Board, Paravur in SM-1/92/PRR dated 25.04.2013.
2. The petitioner is a Non-trading Company incorporated under the Travancore Companies Act and is having 200 odd acres of land in Kodassery Village in Mukundapuram Taluk which was originally granted by the Government, for cultivation. In 1993, the petitioner received a notice from the Taluk Land Board enclosing a draft statement. The petitioner filed objection to the draft statement contending that the petitioner is a charitable and educational institution of public nature coming under Section 81(1)(t)(ii) of the Kerala Land Reforms Act, 1963 (for short, ‘the Act’) and therefore the property held by the petitioner is exempted from the provisions of the Act and no proceedings can be initiated by the Taluk Land Board against the property.
3. The petitioner also filed an application dated 28.09.1994 seeking exemption of the land as provided under Section 81(3) of the Act before the Government. Later, the petitioner filed O.P No.15396 of 1999 before this Court and by judgment dated 28.06.1999, this Court directed the Government to consider the said application. The proceedings before the Taluk Land Board was ordered to be kept in abeyance till the disposal of the application.
4. The Government rejected the application for exemption by order dated 25.02.2000. Pursuant thereto, the Taluk Land Board re-commenced the proceedings before it on 20.05.2000. The petitioner took up the matter before this Court in O.P No.16861 of 2000 contending, inter alia, that the order dated 25.02.2000 was passed by the Government without issuing notice to the petitioner. This Court disposed of the original petition by judgment dated 29.01.2009 and the relevant portion thereof reads as follows:-
“3. I am of opinion that those are contentions which the petitioner has to take up with the Taluk Land Board in the ceiling case at the time of hearing. Ext.P5 is only a notice issued by the Taluk Land Board directing the petitioner to appear for a hearing of the ceiling case. It is open to the petitioner to raise all their contentions before the Taluk Land Board in the hearing pursuant to Ext.P5. In the above circumstances, without prejudice to such right of the petitioner, this original petition is dismissed.”
5. Pursuant to the judgment of this Court, the Taluk Land Board issued notice to the petitioner proposing to continue the ceiling proceedings under Section 81(3) of the Act. The Taluk Land Board, by the order impugned, rejected the claim of the petitioner for exemption under Section 81(1)(t)(ii) of the Act finding that the Government have already rejected the application of the petitioner under Section 81(3) of the Act. The relevant portion of the order reads as follows:-
“1) It is submitted in the statements, that the declarants are a non-trading charitable institutions established in the year 1927 as per Section 26 of Travancore companies Regulation 1 of 1092 and is now being governed by Section 25B of the Indian Companies Act and hence entitled to be exempted from the provisions of KLR Act U/s 81(1)(t)(ii) as it is a religious, charitable and educational institutions of public nature. Since the Government have already rejected the application of the declarants to declare the institution as a charitable educational institution of a public nature, as required under Section 81(3), the claim cannot be admitted.”
The petitioner was directed to surrender 201.29.163 acres of land in various survey numbers of Karumalloor Village in Paravur Taluk and Kodassery Village in Mukundapuram Taluk.
6. In the meantime, W.A.No.2091 of 2009 was filed by the petitioner against the judgment in OP No.16861 of 2000 and the appeal was disposed of by judgment dated 24.10.2014 setting aside the order dated 25.02.2000 passed by the Government under Section 81(3) of the Act. The Division Bench directed the Government to reconsider the application of the petitioner da