2026 Supreme(Online)(Ker) 31552

IN THE HIGH COURT OF KERALA AT ERNAKULAM
M.A.Abdul Hakhim, J
Nazar T – Appellant
Versus
HDFC Bank Limited – Respondent
WP(C) NO. 25002 OF 2025



Advocates:
For the Appellants/Petitioners: T.Sanjay, Sanil Kumar G, Satheesh Kumar K, Afnan Dawood
For the Respondents: P. Sathisan, Tony Augustine

A bank is entitled to exercise a general lien under Section 171 of the Indian Contract Act and rely on contractual cross-collateralization clauses to retain security documents until all outstanding debts of the borrower are fully settled.

Headnote:The case involves a dispute regarding the refusal of a financial institution to release security documents post-repayment of a specific loan, invoking contractual clauses and statutory lien rights. The petitioners contended that since the dues under the primary loan were satisfied, the refusal to issue a No Objection Certificate was unjustified. The court examined the terms of the loan agreement, which expressly permitted the retention of security for other outstanding liabilities of the borrower. The core issue was whether the bank could exercise a general lien over securities despite the closure of a specific loan account. The court observed that the contractual agreement explicitly provided for cross-collateralization, allowing the bank to retain security until all outstanding loans granted to the borrower were settled. This principle of contractual freedom and the application of statutory lien provisions were central to the court's reasoning. Ultimately, the court held that in light of the explicit contractual clause allowing retention of security for other loans, no relief could be granted to the petitioners, and the writ petition was dismissed.

Table of Content
1. contractual clauses allowing for the retention of security across multiple loans are binding on the borrower. (Para 1 , 2 , 3 , 4)

JUDGMENT

1. The Petitioners have filed this Writ Petition seeking direction to the Respondent No.2 to issue No Objection Certificate and other related documents held by the Bank with respect to Ext.P1 Loan Agreement by which the Petitioners availed a commercial vehicle loan from the Respondent Bank. The contention of the Petitioners is that the dues under the said loan are fully paid. In spite of that, the Respondent Bank is refusing to issue No Objection Certificate and release the related documents to the Petitioners.

2. Respondent Bank has filed a counter affidavit opposing the prayers in the Writ Petition. It is contended that there is a specific clause in Ext.P1 Loan Agreement that allows the Bank to retain the security provided by the borrower for any other loan granted by the Bank to the borrower. The learned Counsel for the Respondent Bank further relies on the general lien under Section 171 of the Indian Contract Act, 1872, in order to retain the security.

3. Though the Respondent Bank has filed a counter affidavit stating that another loan is outstanding, the Petitioners have not disputed the same. The parties are governed by contractual obligations arising out of the Ext.P1 Loan Agreement. When the Ext.P1 Agreement specifically contains a clause that the security can be retained for other loans also to be granted to the Borrower, the Petitioner cannot claim NOC for the loan granted as per the Ext.P1 Agreement. No relief can be granted in this Writ Petition.

4. Accordingly, this Writ Petition fails and the same is dismissed.

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top