2026 Supreme(Online)(Ker) 67271
IN THE HIGH COURT OF KERALA AT ERNAKULAM
JAIN BUILDERS – Appellant
Versus
CHIEF ENGINEER (NW) – Respondent
WP(C) 31654/2025
##PAGE1##
IN THE HIGH COURT OF KERALA AT ERNAKULAM PRESENT THE HONOURABLE MR.JUSTICE ZIYAD RAHMAN A.A.
RD WEDNESDAY, THE 23 DAY OF SEPTEMBER 2026 / 1ST ASWINA, 1948 WP(C) NO. 31654 OF 2025 PETITIONER/S: JAIN BUILDERS
216(C), SHIVA COLONY, MAYO LINK ROAD, AJMER-, REPRESENTED BY ITS POWER OF ATTORNEY HOLDER MR.
PRAFUL JAIN, S/O. SHRI SUBODH JAIN, PIN - 305007 BY ADVS.
SHRI.DEEPU THANKAN SMT.UMMUL FIDA SMT.LAKSHMI SREEDHAR SMT.CINDIA S.
SMT.POOJA CHANDRAN SMT.GAYATHRI G.
RESPONDENT/S:
1 CHIEF ENGINEER (NW)
MILITARY ENGINEER SERVICE, SOUTHERN NAVAL COMMAND, NAVAL BASE PO, KOCHI, PIN - 682004
2 GARRISON ENGINEER (P)
MILITARY ENGINEER SERVICE, SOUTHERN NAVAL COMMAND, NAVAL BASE PO, KOCHI, PIN - 682004 BY ADV O.M.SHALINA, DEPUTY SOLICITOR GENERAL OF INDIA THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD ON
23.09.2026, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
##PAGE2##JUDGMENT
The petitioner is an 'S' Class contractor of Military Engineer Services and the dispute highlighted in this writ petition relates to the denial of claim made by the petitioner for price escalation.
2. The facts that led to the filing of this writ petition are as follows: Ext.P1 is the notice inviting tender dated 29.04.2017, which was published for inviting tenders in relation to the work of addition/alteration of special repairs to Tarangini Apartments, Kochi. The work was to be completed in two phases, the first phase included addition/alteration and special repairs to Block B, C, and D and the second phase included the work of addition/alteration and special repairs to Block A. The time specified for phase I was 450 days, whereas, the time fixed for phase II was 365 days. The petitioner turned out to be the lowest bidder and accordingly he was issued with Ext.P2, the Letter of Acceptance, on 04.07.2017, followed by Ext.P3 Work order dated 14.07.2017. According to the petitioner, the total period specified for completing the work was 815 days (27 months) and therefore the petitioner is entitled to escalation of price, in view of the fact that, the total tenure of the contract exceeds two years.
##PAGE3##3. Thus, the said claim is made by the petitioner on the basis of Ext.P6, which is copy of Appendix 8.1 of the Manual on Contracts published by the respondents. As per Clause XIII thereof, the reimbursement/refund on variation in prices labour wages is applicable for all tenders, where the period of completion as per administrative approval is two years or more. According to the petitioner, during the course of contract, the Kerala State Government published Ext.P8 notification making amendments to the Minimum Wages Act, thereby increasing the wages applicable to the employees. Thus, there occurred escalation in wages and the petitioner had to incur additional expenditure under the said Act. Therefore, according to the petitioner, by virtue of such escalation of wages, the petitioner is entitled to invoke, the stipulations in Clause XIII of Appendix
##PAGE4##8.1 of the Manual on Contracts, a copy of which is produced as Ext.P6.
4. The petitioner had completed the work on
05.02.2021 and all the bills have been settled. Subsequently, seeking additional amounts owing to the price escalation by relying upon Ext.P6, P14 was submitted. Since the claim put forward by the petitioner in this regard was not considered, the petitioner approached this Court by filing W.P.(C) No. 1905/2021, which culminated in Ext.P15. As per Ext.P15, this Court disposed of the writ petition directing the 2nd respondent to consider Ext.P14, which is produced as Ext.P13 therein, and take a decision based on Ext.P6 herein (which is produced as Ext.P5 therein). On the basis of the said direction, Ext.P16 order has been issued by the 2nd respondent, wherein, the claim put forward by the petitioner was rejected, after entering into a finding that, the total tenure of the contract is less than two years and therefore, Ext.P6 herein and the price escalation contained therein is not applicable.