SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2021 Supreme(Online)(MAD) 1774

IN THE HIGH COURT OF JUDICATURE AT MADRAS Reserved on : 03.11.2020 Delivered on : 19.01.2021 CORAM THE HONOURABLE Ms. JUSTICE P.T. ASHA O.P.No.34 of 2020 Tamilnadu Road Sector Project II, Highways Department Represented by Project Director, No.171, South Kesava Perumal Puram, Chennai – 600 028, India. ...Petitioner Vs

1.M/s.IRCON International Ltd. And Sumber Mitra Jaya (J.V.)

Palika Bhavan, Sector-XII R.K.Puram, New Delhi – 110 066

2.M/s.Sheladia Associates Inc.

“Amsri Shamira” 2nd floor flat no.206 & 207 Door No.9-1-113 to 118, SD Road Old Lancer lanes Secundrabad – 500003, Telangana ... Respondents Prayer: Petition filed under Section 11 (6) of the Arbitration and Conciliation Act, 1996, to appoint a suitable person as nominee Arbitrator of the respondent as per the Arbitration clauses in the Agreements dated 04.02.2005 and 10.09.2004 to decide the disputes which have arisen between the petitioner and the respondents.

For Petitioner : Mr.M.Sricharan Rangarajan Additional Advocate General For Respondent 1 : Mr.S.V.S. Chowdry For Respondent 2 : Mr.P.J.Rishikesh

ORDER

The petition has been filed invoking the provisions of section 11 (6) of the Arbitration and Conciliation Act, 1996, herein after called the Act. The petitioner who is the Tamilnadu Road Sector Project II, Highways Department had entrusted to the 1st respondent herein the Civil constructions work relating to the upgradation of the road from Nagapatinam to Kattumavadi and the new bypass roads at, Nagapattinam, Thiruthuraipundi and Muttupet, which was being financially assisted by a loan from the International Bank for Reconstruction and Development in the year 2005.

st

2. The 1 respondent was entrusted with the civil construction work and an agreement to this effect was entered into on 04.02.2005. Prior to this agreement, the petitioner had engaged the services of the nd

2 respondent as the Supervision Consultant, to supervise and administer the contract for which an agreement was entered into on nd

10.09.2004 between the petitioner and the 2 respondent.

3. The petitioner would submit that the 1st respondent who had commenced the contract in the year 2005 had concluded the same in the year 2011 and the defects liability period also came to an end in the year 2012.

4. The petitioner would contend that on 03.04.2017 when the inspection was conducted by the Director, Highways Research Station, several defects were found in the work undertaken and a letter dated 01.07.2017 was addressed to the respondents directing them to inspect the defects and give the actual cost estimate for the repair and st rehabilitation of the ROB. The 1 respondent did not submit any nd response. However, the 2 respondent had issued a reply dated

21.07.2017.

5. Thereafter, since the repair works were not effected the same was undertaken by the petitioner through the Chief Engineer, Construction and Maintenance Department by reason of which the petitioner had incurred huge costs. Thereafter, on 29.08.2019, the petitioner had issued seperate legal notices to the respondents to make good the loss. The petitioner had called upon the respondents to treat the said notice as an invocation of the arbitration clause under Section 21 of the Act. They had nominated one Mr.V.Thamilselvam, Chief Engineer (Retd) as their arbitrator. The petitioner had invoked clause 67.3 of the General Conditions of contract of the agreement dated 04.02.2005 entered into with the 1st respondent, for ease of understanding hereinafter referred to as the 2nd Contract, and clause 8.2 of the Special Conditions of Contract dated 10.09.2004 entered into with the 2nd respondent, for ease of understanding hereinafter referred to as the 1st Contract.

st

6. To this notice, the 1 respondent had sent a reply dated nd

01.10.2019 and the 2 respondent had sent a reply dated 07.10.2019. Both the respondents had denied the liability and they had contended that the 2nd contract contemplated an arbitral tribunal consisting of three members, and clause 8.2 of the Special Conditions of the 1st Contract contemplated an arbitral tribunal consisting of a sole arbitrator. They would also contend that the agreement having come to an end in the year 2012 the invocation of the arbitral clause was not maintainable. The petitioner contended that since the contracts related to the same work they were filing a single petition under Section 11 (6) of the Act for appointing an arbitrator.

nd

7. The 2 respondent has filed a counter in and by which they would contend that there is no arbitral dispute between the parties nd since the 2 respondent has completed its services under the nd supervision consultancy contract. Further, the 2 respondent would contend that the grounds on which the reliefs are sought is not amenable to the provisions of Section 11 of the Act.

8. The 2nd respondent would submit that though their work had been completed, the petitioner had extended the mandate till May nd

2013 and the 2 respondent as the Supervision Consultant had handed over all the documents and records to the petitioner as contemplated unde

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top