2023 Supreme(Online)(MAD) 30166
MADRAS HIGH COURT
T.Sabitha – Appellant
Versus
The Member secretary – Respondent
WP/31545/2022
Local authorities have a duty to take action against unauthorized construction and encroachment.
Headnote:
UNAUTHORIZED CONSTRUCTION - ENCROACHMENT - MANDAMUS - [Tamil Nadu Urban Local Bodies Act, 1998 and Rules 2000]
Fact of the Case:
The petitioner, the owner of a plot of land, alleged that the 3rd respondent had constructed flats on an adjacent plot without leaving any side setback and had also encroached upon a portion of the petitioner's land. The petitioner had complained to the respondents, but no action had been taken.
Finding of the Court:
The court directed the 2nd respondent to inspect the property within 15 days and take necessary action in accordance with the law within 8 weeks if any unauthorized construction was found.
Issues: Whether the 3rd respondent had put up unauthorized construction and encroached upon the petitioner's land.
Ratio Decidendi: The court relied on the letter issued by the 1st respondent to the 2nd respondent directing the latter to take necessary action against the unauthorized construction.
Final Decision: The court directed the 2nd respondent to inspect the property and take necessary action in accordance with the law within 8 weeks if any unauthorized construction was found.
W.P.No.31545 of 2022
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED: 04.01.2023
CORAM:
THE HONOURABLE MS.JUSTICE V.M.VELUMANI
and
THE HONOURABLE
MRS.JUSTICE R.HEMALATHA
W.P.No.31545 of 2022
T.Sabitha
.. Petitioner
Vs.
1.The Member Secretary,
Chennai Metropolitan Development Authority,
Thalamuthu Natarajan Building,
No.1, Gandhi Irwin Road,
Egmore, Chennai-600 008.
2.The Executive Officer,
Mangadu Town Panchayat,
Mangadu Chennai-600 122.
3.Ramadoss
.. Respondents
Prayer: Writ Petition is filed under Article 226 of the Constitution of
India, praying for issuance of a Writ of Mandamus, directing the 1st and
2nd Respondents to take necessary and immediate enforcement action
against the 3rd Respondent deviated and unauthorised construction at Plot
No.5A and 5B, A.R. Nagar, Mangadu Village, Chennai-600 122, as per
the provision of Tamil Nadu Urban Local Bodies Act, 1998 and Rules
2000.
1/6
https://www.mhc.tn.gov.in/judis
W.P.No.31545 of 2022
For Petitioner
: Mr.M.Devaraj
For R1
: Mr.C.N.Vinobha
Standing Counsel (CMDA)
For R2
: Mr.P.Srinivas
Standing Counsel
For R3
: Mr.S.Sathish Rajan
O R D E R
(Order of the Court was delivered by V.M.VELUMANI, J.)
The present writ petition is filed for a direction to the respondents
1 and 2 to take necessary and immediate enforcement action against the
3rd respondent deviated and unauthorised construction at Plot No.5A and
5B, A.R. Nagar, Mangadu Village, Chennai-600 122, as per the provision
of Tamil Nadu Urban Local Bodies Act, 1998 and Rules 2000.
2. Heard Mr.M.Devaraj, learned counsel appearing for the
petitioner, Mr.C.N.Vinobha, learned Standing Counsel appearing for the
1st respondent, Mr.P.Srinivas, learned Standing Counsel appearing for the
2nd respondent as well as Mr.S.Sathish Rajan, learned counsel appearing
for the 3rd respondent and perused the entire materials on record.
3. The petitioner is a Power of Attorney of one T.Sabitha, who is
2/6
https://www.mhc.tn.gov.in/judis
W.P.No.31545 of 2022
the owner of Plot No.6 measuring to an extent of 3042 sq.ft., comprised
in Survey Nos.357/9, 10 and 11 situated at A.R.Nagar, approved by
MMDa PPD/LO.12/1998 in Mangadu Village, Sriperumbudur Taluk,
Kancheepuram District. The 3rd respondent is the owner of adjacent plot
of the petitioner bearing No.5, A.R.Nagar, Mangadu Village,
Sriperumbudur Taluk, Kancheepuram District. The 3rd respondent sub
divided the said plot into Survey Nos.5A and 5B measuring to an extent
of 885 sq.ft., and 1876 sq.ft., respectively and put up construction
contrary to the approved plan and also encroached 116 sq.ft of the
petitioner's property. The petitioner has given various complaints to the
respondents 1 and 2. Thereafter, the 1st respondent by its Letter No.EC/C-
1/2420/2020, dated 30.05.2020 directed the 2nd respondent to take
necessary action against the unauthorised construction put up by the 3rd
respondent. The 3rd respondent informed that he is ready to co-operate
and willing for the survey of the property in question. Inspite of that, the
2nd respondent has not inspected the property and has not taken any
action. Hence, the petitioner has come out with the present writ petition.
4. Mr.S.Sathish Rajan, learned counsel appearing for the 3rd
3/6
https://www.mhc.tn.gov.in/judis
W.P.No.31545 of 2022
respondent submitted that the 3rd respondent sub divided the property as
Survey Nos.5A and 5B and constructed flats and sold the same to various
third parties and there is no unauthorised construction put up by the 3rd
respondent.
5. Mr.P.Srinivas, learned Standing Counsel appearing for the 2nd
respondent submitted that the 2nd respondent/the Executive Officer,
Mangadu Town Panchayat has now been upgraded as Mangadu
Municipality and new Commissioner will inspect the property in
question and if there is any unauthorised construction put up by the 3rd
respondent, necessary action wil