2024 Supreme(Online)(Mad) 78966
IN THE HIGH COURT OF JUDICATURE AT MADRAS
Dated : 08.01.2025
The Hon'ble Mr.Justice N.Sathish Kumar
G.Rajasekaran ... Revision Petitioner Vs. 1. M/s. Galamour Leather, rep. By its Partners, Office No.91/14, First Floor, Narayana Chetty Street, Periamet, Chennai – 600 003, Tannery No.615, Konamedu, Vaniyambadi Taluk, Vellore District. 2. Kathawal Aness UR Rahman 3. Mr.O.A.Mohamed Sayeed. ..Respondents
Civil Revision Petition filed under Article 227 of the Constitution of India against the order passed in E.P.No.Nil of 2024 in O.S.No.7 of 2018, on the file of the District Court, Tirupattur, dated 30.04.2024, and to direct the learned Judge, Tirupathur, to number the said Execution Petition No.Nil of 2024 in O.S.No.7 of 2018.
For Revision Petitioner : Mr.B.Sathish Sundar
For Respondent-1 : Court notice returned
For Respondents 2 & 3 : Mr.K.N.Nataraj
O R D E R
08.01.2025
sd
Index : yes/no
To
The District Court, Tirupattur,
N.Sathish Kumar,J.,
sd
08.01.2025
This Civil Revision Petition is filed challenging the order passed in E.P.No.Nil of 2024 in O.S.No.7 of 2018, on the file of the District Court, Tirupattur, dated 30.04.2024.
The facts relevant for disposal of the Revision Petition are as follows:-
i) The revision petitioner/plaintiff filed a suit in O.S.No.7 of 2018 for recovery of a sum of Rs.29,29,797/-. The suit was decreed in favour of the revision petitioner/decree holder and based on the said decree, the revision petitioner/decree holder also filed an Execution Petition to realize the decree amount with subsequent interest. In the said Execution Petition, orders have been passed attaching the movable properties on 22.04.2022. In the meanwhile, at the request of the parties, the matter has been referred to Lok Adalath and on 20.02.2023 both the parties had agreed for settlement for a sum of Rs.29,29,797/- and it is also recorded that the entire amount has been received by the revision petitioner herein on 20.02.2023 and an award has been passed to the effect that the matter has been settled. Execution Petition terminated and Attachment to be raised.
ii) Thereafter, application has been taken out by the revision petitioner for attachment of the property and also filed another Execution Petition by contending that the Lok Adalat amount has not been settled. The said Execution Petition has been dismissed. Challenging the same, the present Revision Petition is filed.
The learned counsel appearing for the revision petitioner would submit that the revision petitioner has been forced to sign the documents and accept the award, and since he has not received the award amount, he has filed application seeking for attachment of the property and filed another Execution Petition, however, the Executing Court dismissed the Execution Petition as not maintainable. Therefore, the learned counsel prays for setting aside the impugned order.
The learned counsel for the respondents 2 and 3 would submit that the revision petitioner had participated in the lok adalat proceeding and agreed for a compromise, it was only thereafter, award has been passed by recording the said compromise memo, therefore, it is not open to the revision petitioner to raise fallacious contentions that he has been forced to sign the award due to force or coercion exerted by a middleman.
Heard the learned counsel for the revision petitioner and respondents 2 and 3 and perused the materials placed on record.
Though several grounds have been raised in this Revision Petition, as if, the revision petitioner was pressurized by the middleman and was forced to sign the documents and accept the award, the fact remains that the revision petitioner has signed the award, admitting the receipt of the entire decree amount. Based on his admission alone, award has been passed by the Lok Adalat by clearly recording the fact that the entire amount was received by the revision petitioner, and thereby, the E.P. was terminated and attachment was raised. However, it appears that after a period of 10 months of the award dated 20.02.2023 passed by the Lok Adalat, the revision petitioner, somehow, manoeuvred to get the Court orders served to the concerned Sub Registrar to indicate, as if, immovable properties have been attached, which has been done in connivance with the Court staff and Advocate, who appeared for the revision petitioner. When the Executing Court realised this mistake and raised the attachment, application has been taken out by the revision petitioner for attachment of the property and also filed another Execution Petition by contending that the Lok Adalat amount has not been settled. The Executing Court considering the entire circumstances of the case, rejected the second Execution Petition as not maintainable on the ground that amount has been settled as per the award, therefore, E.P. got terminated, and attachment was raised, therefore, the question of second Execution Petition for attachment of the properties would not