MADRAS HIGH COURT
Needle Industries (India ) – Appellant
Versus
The Superintending Engineer – Respondent
WP 21007/2019
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED: 08.03.2022
CORAM
THE HONOURABLE DR. JUSTICE ANITA SUMANTH
W.P.No.21007 of 2019
and
WMP.Nos.20184 & 20186 of 2019
Needle Industries (India) Private Limited,
Ketti, The Nilgiris
Tamil Nadu 643 243
HTSC Nos.31 & 39
Represented by its Managing Director
T.A.Devagnanam
...Petitioner
Vs
1. The Superintending Engineer,
Nilgiris Electricity Distribution Circle,
Tamil Nadu Generation & Distribution
Corporation Limited (TANGEDCO),
Udhagamandalam.
2. Tamil Nadu Generation &
Distribution Corporation Limited,
(TANGEDCO) rep. by its Chairman,
10th Floor, 144, Anna Salai,
Chennai 600 002.
3. The Deputy Financial Controller,
Tamil Nadu Generation &
Distribution Corporation Limited,
(TANGEDCO),
Nilgiris Electricity Distribution Circle,
Udhagamandalam.
... Respondents
Prayer: Writ Petition filed under Article 226 of the
Constitution of India, to issue a Writ of Certiorarified
Mandamus, calling for the records of the 3rd Respondent with
respect to the High Tension Bill dated 04.07.2019 for the month
of June 2019 pertaining to HTSC No.31 (Service No.039094820031)
belonging to the Petitioner and quash the same as illegal in so
far as it relates to the amount of Rs.20,38,976/- levied in
Page.No.3 under the caption “Affecting Adjustments” and forbear
the Respondents, their men, agents and representatives from
levying or enforcing any charges on the Petitioner except in
accordance with Section 56(2) of the Electricity Act, 2003.
https://hcservices.ecourts.gov.in/hcservices/
For Petitioner :
Mr.Krishna Srinivasan
for Mr.S.Ramasubramaniam
For Respondents
:
Mr.Abul Kalam
Standing Counsel
O R D E R
Heard Mr.Krishna Srinivasan, learned counsel for
Mr.S.Ramasubramaniam, learned counsel appearing for the
petitioner and Mr.Abul Kalam, learned Standing Counsel appearing
for the respondents.
2.The petitioner has challenged a High Tension invoice dated
04.07.2019 pertaining to HTSC.No.31 relating to the period
August 2015. The impugned invoice seeks to raise a demand after
a period of four years when the time of consumption. The primary
argument that is raised relates to the bar of limitation.
3.Admittedly, there is a difference of 3,68,939 units
generated by the WTG as recorded by the authorities and as
logged by the petitioner. The aforesaid difference had escaped
the attention of TANGEDCO and no due was raised in this regard.
4.The error was brought to the notice of the authorities on
24.10.2015 by the petitioner under communication dated
24.10.2015 received on 26.10.2015 by the respondents. The
communication states that with respect to the subject matter,
which is the WTG 'generation units difference', as per records,
the WTG generated units for the month of August was 3,34,483. In
the monthly HT current consumption bill, the WTG unit taken into
account was a sum of a Rs.7,03,422/-. There was thus a
difference of 3,68,939 units, difference called for verification
and reconciliation.
5. Thus, the fact that the petitioner had been granted
excess credit in regard to 3,68,939 units has been noticed by
the petitioner and duly brought to the notice of the respondents
as early as on 26.10.2015. Despite this, no action was initiated
by the respondents to reverse the credit. The subsequent current
consumption bill (CC bill) did not make an adjustment, as
specifically sought for by the petitioner on 24.10.2015.
6. For the first time, on 02.04.2019, the authorities write
to the petitioner proposing to demand a sum of Rs.23,79,973/- as
a supplemental claim on account of short collection of energy
charges, putting it to notice that the demand in this regard
https://hcservices.ecourts.gov.in/hcservices/
would be included in the current consumption bill for the
ensuing month and should be remitted by the petitioner, i
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.