2022 Supreme(Online)(Mad) 84437
MADRAS HIGH COURT
G.Uttam Kumar – Appellant
Versus
The State – Respondent
WP/15397/2017
WP.Nos. 15397 to 15400 of 2022
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED : 27.06.2022
CORAM
THE HONOURABLE MR. JUSTICE M.DHANDAPANI
WP. Nos. 15397 to 15400 of 2017
and
WMP. Nos. 16707 to 16710 of 2017
G.Uttam Kumar
... Petitioner in W.P.No.15397 of 2017
G.Uttam Kumar
... Petitioner in W.P.No.15398 of 2017
Ashok Kumar Bagri
... Petitioner in W.P.No.15399 of 2017
G.Uttam Kumar
... Petitioner in W.P.No.15400 of 2017
Versus
1 The Secretary to Government,
Industries Department,
Secretariat, Chennai 9.
2 The District collector,
Thiruvallur District.
3 The Special Tahsildar,
(Land Acquisition),
Chennai Petroleum Corporation Limited,
No.62/1, East Jones Road, Saidapet, Chennai-15.
1/8
https://www.mhc.tn.gov.in/judis
WP.Nos. 15397 to 15400 of 2022
4. The Tahsildar,
Madhavaram Taluk,
Chennai-60.
5. The Superintending Engineer,
Transmission,
Tamil Nadu Electricity Board,
800, Anna Salai, Electricity Avenue,
Chennai-2.
... Respondents in all the petitions
Common Prayer:- Writ Petitions are filed under Article 226 of the
Constitution of India praying to issue a Writ of declaration declaring that
acquisition of lands in respect of the petitioners herein pursuant to the land
acquisition proceedings in G.O.Ms. No.264 Industries (MID-1) Department
dated 16.07.1992 and section 6 declaration published in Tamil Nadu
Government Gazatte No.30C Supplement Dated 29.07.1992 Part-II Section
2 at Page No.11 to 14 Award dated 05.08.1994 in Award No.04/ 1994 and
consequential amendment in Letter No.25554/ MID 1/ 2003-2 dated
11.03.2004 has been lapsed in view of section 24 Clause 2 of the Right Fair
Compensation and Transparency in Land Acquisition Rehabilitation and
Re-settlement Act 2013.
For Petitioners
: Mr. S.Ramesh Kumar (in all the petitions)
For Respondents
: Mr. P.Sathish, AGP For RR1 to 4
Mr.L.Jai Venkatesh For R5
(in all the petitions)
2/8
https://www.mhc.tn.gov.in/judis
WP.Nos. 15397 to 15400 of 2022
COMMON ORDER
Since the issue involved in all the matters and the facts are one
and the same. Therefore, all the petitions are disposed of by way of common
order.
2. All the writ petition have been filed for declaration declaring
that acquisition of lands in respect of the petitioners herein pursuant to the
land acquisition proceedings in G.O.Ms. No.264, Industries (MID-1)
Department, dated 16.07.1992 and section 6 declaration published in Tamil
Nadu Government Gazatte No.30C Supplement Dated 29.07.1992 Part-II
Section 2 at Page No.11 to 14, Award dated 05.08.1994 in Award No.04/
1994 and consequential amendment in Letter No.25554/ MID 1/ 2003-2
dated 11.03.2004 has been lapsed in view of section 24 Clause 2 of the
Right Fair Compensation and Transparency in Land Acquisition
Rehabilitation and Re-settlement Act 2013.
3/8
https://www.mhc.tn.gov.in/judis
WP.Nos. 15397 to 15400 of 2022
3. The case of the petitioners is that they are land looser.
Challenging the acquisition proceedings, the petitioners came up before this
Court. For the purpose of setting up of National Aromatics Complex in
Saidapet Taluk, the respondents acquired the lands including the petitioners
property. The third respondent issued notification under G.O.Ms.No.264
Industries (MID-1) Department, Dated 16.07.1992. Subsequent to that, a
declaration under Section 6 was published in Tamil Nadu Government
Gazatte No.30C, Supplement Dated 29.07.1992, Part-II, Section 2 at Page
No.11 to 14 and later an award was also made on 05.08.1984 in Award
No.04/1994. Challenging the same, these writ petitions have been filed for
re-convey the land.
4. The learned counsel for the petitioners submitted that an award
was passed and the compensation amount has not been paid to the
petitioners and th