2022 Supreme(Online)(Mad) 73438
MADRAS HIGH COURT
Honourable Mr Justice C. SARAVANAN
February Two Thousand Twenty Two PRESENT THE HON`BLE MR.JUSTICE C.SARAVANAN WMP.NOS.29029 AND 29030 OF 2021 IN WP.NO.27502 OF 2021 L.R.RAJA [PETITIONER IN BOTH THE PETITIONS] – Appellant
Versus
1 THE COMMISSIONER [ – Respondent
HIGH COURT OF JUDICATURE AT MADRAS ( Special Original Jurisdiction ) Friday, the Twenty Fifth day
IN THE HIGH COURT OF JUDICATURE AT MADRAS
( Special Original Jurisdiction )
Friday, the Twenty Fifth day of February Two Thousand Twenty Two
PRESENT
THE HON`BLE MR.JUSTICE C.SARAVANAN
WMP.NOS.29029 AND 29030 OF 2021
IN WP.NO.27502 OF 2021
L.R.RAJA [PETITIONER IN BOTH THE PETITIONS]
Vs
1 THE COMMISSIONER [RESPONDENTS IN BOTH THE PETITIONS]
GREATER CHENNAI CORPORATION,
RIPPON BUILDING, CHENNAI-600 003
2 THE EXECUTIVE ENGINEER
GREATER CHENNAI CORPORATION ZONE-XIV,
PERUNGUDI, NO.6/64,PUZHUTHIVAKKAM MAIN ROAD,
CHENNAI-600 091
3 THE ASSISTANT ENGINEER
GREATER CHENNAI CORPORATION ZONE-XIV
PERUNGUDI, NO.6/64,PUZHUTHIVAKKAM MAIN ROAD,
CHENNAI-600 091
4 THE ASSISTANT REVENUE OFFICER
GREATER CHENNAI CORPORATION ZONE-XIV,
PERUNGUDI, NO.6/64,PUZHUTHIVAKKAM MAIN ROAD,
CHENNAI-600 091
Petition praying that in the circumstances stated therein and
in the affidavit filed therewith the High Court will be pleased to
stay all further proceedings pursuant to assessment and demand made
in online notice and notice affixed on wall dated 03.09.2021 in a
sum of INR 15,28,380/- (WMP.NO.29029/2021) pending disposal of the
WP.NO.27502/2021 and;
ii) To direct the respondents 2 to 4 to return the sum of INR
2,16,680/- paid by the petitioner on account of property tax for
II-2013-2014 and I-2014-2015 vide receipt Nos.18313 dated
11.11.2013
and
102449
dated
30.09.2014
respectively,
(WMP.NO.29030/2021) pending disposal of the WP.NO.27502/2021.
Order : This Miscellaneous petitions coming on this day for
hearing upon perusing the petition and the affidavit filed in
support thereof and upon hearing the arguments of MR.C.JOHNSON,
Advocate for the petitioner in both the petitions, the court made
the following order:-
The petitioner had applied for constructing a commercial
complex with the erstwhile Ulnagaram Puzhuthivakkam Municipality on
16.06.2011. The petitioner was also given a planning permission by
the Puzhuthivakkam Panchayat. Subsequently,Puzhuthivakkam Panchayat
came within the purview of Chennai Corporation in the year 2013 and
therefore the construction put up by the petitioner came within the
purview of the CMDA. On inspection, the CMDA found that the
petitioner had deviated and made additional construction of 600
Sq.ft in the 3rd floor, though the permission granted on 16.06.2011
was stilt plus two floors.
2.The learned counsel for the petitioner submits that on
19.09.2013 the property was put on lock and seal and demolition
notice was issued by the CMDA. It is submitted that the petitioner
had also approached this Court in W.P.No.33418 of 2013 which came
to be disposed, pursuant to which the petitioner preferred an
Appeal before the Government and further the appeal is stated to be
pending before the appropriate Authority.
3.The learned counsel for the petitioner submits that though
the petitioner opted to get property assessed and paid property tax
for the 2nd half of 2013-14 and 1st half of 2014-15, it is submitted
that the property has been under lock and seal since 19.09.2013 and
therefore, the property cannot be subjected to tax after the
property was put under lock and seal with effect from 18.11.2013
pursuant to lock and seal notice dated 19.09.2013 of CMDA.
4.The learned counsel for the petitioner submits that the
property is not fetching any rent, though it was intended to lease
to ICICI Bank for a sum of Rs.1,00,00,000/- during 2013. It is
submitted that as per Section 100 of the Chennai City Municipal
Corporation Act, 1919 tax is to be paid on the Gross Annual rent at
which at the time of assessment and since the property is under
lock and seal since 2013 there is no justification in taking
property tax from the petitioner.
5.The learned counsel for the petitioner has drawn attention
to Regulation 20 of the Tamil Nadu Combined Development Building
Rules 2019.