MADRAS HIGH COURT
S.RAVICHANDRAN – Appellant
Versus
M/S.HIMAYAM ENGINEERS AND – Respondent
OSA 89 2018
IN THE HIGH COURT OF JUDICATURE AT MADRAS
Judgment Reserved on : 30.09.2019
Judgment Delivered on : 12.11.2019
CORAM:
THE HONOURABLE MR.JUSTICE R.SUBBIAH
and
THE HONOURABLE MRS. JUSTICE T.KRISHNAVALLI
O.S.A.No.89 of 2018
and
C.M.P.Nos.5542, 12366 and 12367 of 2018
1. S.Ravichandran
2. S.Veeraraghavan
3. R.Jagadeesan
.. Appellants
Vs.
Himayam Engineers & Builders,
Represented by its Proprietor,
P.Ramana Reddy,
having office at
New No.150, Old No.60, Ramanaicker Street,
Nungambakkam,
Chennai-600034.
.. Respondent
Original Side Appeal (OSA) filed under Clause 15 of the
Letters Patent read with Order XXXVI Rule 1 of the Madras High
Court Original Side Rules, against the judgment dated 07.09.2017
and decree dated 12.12.2017 in C.S.No.460 of 2005 on the file of
this Court.
Prayer in CS.No.460 of 2005:
a) granting specific performance of the "development agreement"
dated 10.09.2003 entered into between the plaintiff and
defendants 1 and 2 represented by their power of Attorney Agent
3rd defendant
b) for permanent injunction restraining the defendants from in
any manner preventing or interferring with the plaintiff from
proceeding with construction in the suit schedule property in
accordance with the approved plan hereafter to be obtained from
the CMDA and
Page No.1/28
https://hcservices.ecourts.gov.in/hcservices/
c) to direct defendants 1 & 2 to pay plaintiff jointly and
severally a sum of Rs.71,00,000/-(Seventy One Lakhs) towards
damages for breach of suit agreement and Rs.20,00,000/-(Twenty
Lakhs being the return of advance amount in all a total sum of
Rs.91,00,000/-(Ninety One Lakhs)
d) for costs of the suit.
For appellants : Mr.E.J.Ayyappan
For respondent : Mr.R.Thiyagarajan
JUDGMENT
R.SUBBIAH, J
This Original Side Appeal is filed against the judgment and
decree dated 07.09.2017 passed by the learned Single Judge of
this Court in C.S.No.460 of 2005, granting the relief of
specific performance to the respondent/plaintiff in respect of
the Development Agreement entered into between the
respondent/plaintiff and the appellants 1 and 2/defendants 1 and
2 being the owners of the suit properties, represented by their
Power of Attorney Agent, the third defendant (third appellant).
2. The appellants herein are the defendants and the
respondent herein is the plaintiff in the suit. For the purpose
of convenience, the parties herein are referred to as they are
ranked in the suit as plaintiff and defendants.
3. The case of the plaintiff before the learned Single Judge
in C.S.No.460 of 2005 is as follows:
(a) The plaintiff - P. Ramana Reddy is carrying on business
in the name and style of M/s.Himayam Engineers and Builders. The
defendants 1 and 2 are the owners of four plots of land in
Survey No.415 in Mogappair Village, then Saidapet Taluk in then
Chengalpet District. The two plots in item Nos.1(a) and 1(b) in
the schedule to the plaint, belong to the first defendant and
the remaining two plots in Item Nos.2(a) and 2(b) in the
schedule to the plaint, belong to the second defendant. The
third defendant is the Power of Attorney of the defendants 1 and
2.
(b) The defendants 1 and 2 represented by the said Power of
Attorney, the third defendant, entered into a Development
Agreement with the plaintiff at Chennai on 10.09.2003 to develop
the said four plots. Pursuant to the said suit agreement, the
defendants put the plaintiff in possession of the suit schedule
properties as per Clause 19 of the suit agreement. As per Clause
Page No.2/28
https://hcservices.ecourts.gov.in/hcservices/
1 of the suit agreement, the plaintiff agreed to put up
construction in the plaint schedule property(ies) exclusively at
his own costs - a multi-storied complex as per building plan, as
may be permitted by the authorities concerned. Under Clause 3 of
the suit agreement, the plaintiff agreed to commence the
construction of the buildin