Court mandates inquiry into unauthorized construction affecting public infrastructure with a timeline for action.

Subject

Public Law - Administrative Law

Act Referred

Headnote

This order arises from a petition seeking a writ of Mandamus concerning unauthorized construction that allegedly damages public infrastructure. The court mandates an inquiry into construction violations impacting roads and drainage systems, requiring appropriate actions within a three-month timeframe. The relevant statutes to be observed include Article 226 of the Constitution, ensuring compliance with legal building permissions. The court urges due diligence to safeguard public pathways and infrastructure.

Advocates:
For the Appellants/Petitioners: Mr.P. Arun Jayatram
For the Respondents: ----

Table of Content
1. allegations of unauthorized construction harming public infrastructure. (Para 1)
2. court orders inquiry into alleged construction violations. (Para 2)
3. writ petition disposed of with no cost. (Para 3)

O R D E R

[Order of the Court was made by The Hon'ble CHIEF JUSTICE]

The petitioner has made a representation dated 26.09.2025 to the official respondents alleging that by violating the building permission, while raising construction, the fourth respondent is damaging the cement road, the common lane and the drainage water pipe.

2. The allegation, if not already enquired, is required to be duly enquiried by the third respondent, by conducting a spot inspection/survey. If it is found that the alleged illegallity in construction by the fourth respondent is affecting the public pathway, road or public drainage system, appropriate action is required to be taken. The enquiry shall be concluded within a period of three months from the date of receipt of a copy of this order and after giving an opportunity of hearing to the fourth respondent.

3. Writ Petition is, accordingly, disposed of. There shall be no order as to costs. Consequently, connected interim applications are closed.