IN THE HIGH COURT OF JUDICATURE AT MADRAS
M. Dhandapani, J
M/s.Nataraja Construction – Appellant
Versus
The State of Tamilnadu – Respondent
WP No. 43849 of 2025
| Table of Content |
|---|
| 1. the requirement for a site visit certificate for tender submissions. (Para 1 , 2) |
| 2. the petitioner's assertion of rights concerning certificate issuance. (Para 4) |
| 3. court's direction to issue certificates based on procedural obligations. (Para 5 , 6 , 7) |
ORDER
The writ petition has been filed seeking a directions to the fourth respondent to issue a site visit certificate to the Petitioner in respect of the e- Tender Notice No.43/CE/DO2025-26/ Dated 28.10.2025 in so far as S.No.4 work is concerned for construction of four multi-purpose halls in government college of Engineering at Erode District and consequently direct the third respondent to accept the Petitioners Tender Application and to evaluate the same in E-Tender Notice No.43/CE/DO2025-26/ Dated 28.10.2025 in so far as S.No.4 work is concerned.
2. It is the case of the petitioner that the petitioner, a State level first class contractor under Highways Department. The first respondent issued tender notification dated 28.10.2025 regarding construction of four multi-purposes halls, Government College of Engineering, Erode. The tender required bidders to personally inspect the work site and obtain the Work Site inspection certificate and the working condition of plants & Machineries certificate from the third respondent, which were mandatory pre qualification documents. Applications for issuance of these certificate were to be submitted through online on or before 13.11.2025 at 3.00 P.M. And the same will be opened on
14.11.2025 at 3.30 P.M.
3. It is the further case of the petitioner that the petitioner approached the
4th respondent on 04.11.2025 requesting to issue work site inspection certificates and working condition of the plant and machineries certificates to the them and the same has not been considered. Hence, the petitioner has filed the above said writ petitions.
4. The learned counsel for the petitioner submitted that the 4th respondent being a public authority, who is duty-bound to process the request made by the petitioner within the prescribed time-lines. The last date for submitting the application is 13.11.2025. Therefore, this Court may direct the 4th respondent to issue work site inspection certificate and working condition of the plants and machineries certificate to the petitioner by today itself.
5. The learned Special Government Pleader submitted that the certificates will be issued to the petitioner by today itself during office hours.
6. Heard the leaned counsel for the petitioner and the learned Special Government Pleader for the respondents and perused the materials available on record.
7. Considering the fact and circumstances of the case and in view of the limited request sought for by the petitioner, this Court directs the 4th respondent to issue work site inspection certificate and working condition of the plants and machineries certificates to the petitioner in both the cases by today itself before
5.00 P.M. The petitioner shall collect the same during office hours.
8. With the above directions, the writ petitions are disposed. No costs.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.