SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2023 Supreme(Online)(Mad) 104118

MADRAS HIGH COURT
, J
Ramasubbu Ginning Factory v. Superintending Engineer Tamil Nadu Electricity Board Virudhunagar
Writ Petition | W.P(MD).No.840 of 2010



Advocates:
For the Appellants/Petitioners: [Counsel Name]
For the Respondents: [Standing Counsel Name]

The enforcement of procedural regulations is essential before imposing penalties for electricity theft, relying on expert findings and proper cause establishment.

Headnote:This judgement analyzes the applicability of sections of the Tamil Nadu Electricity Supply Code regarding theft of electricity and failure to conduct a proper investigation into the burning of a meter. It is found that the respondents did not adhere to the mandatory procedural requirements before concluding theft. The Court remits the matter for proper consideration. The main issues revolve around the proper testing of the meter and procedural compliance. The Court concludes that the allegations of theft remain a presumption without proper substantiation, and thus, orders for the matter to return to the second respondent for adherence to regulations. The impugned order is set aside and the matter is remitted back, ordering compliance with the specific regulations before any final assessment.

Table of Content
1. challenge to final assessment order under electricity act. (Para 1 , 2)
2. arguments about meter inspection and procedural compliance. (Para 3 , 5 , 6 , 7 , 8 , 9 , 10)
3. court's observations on procedural necessity and presumptions. (Para 11 , 12 , 13 , 14 , 15 , 16)
4. judgment concludes with remitting the matter for regulatory compliance. (Para 17 , 18)

1. The present writ petition has been filed challenging an order of the second respondent in issuing a final assessment order arising under S.135 of the Electricity Act, 2003.

2. According to the petitioner, they are having a LT service connection in Survey No.171 and they are running a ginning factory. On 12.01.2010, the electricity meter got burnt and immediately, on the same day, the petitioner has informed the same to the second respondent herein. The second respondent had conducted an inspection on 17.01.2010. After inspection, the second respondent had suspected theft of energy and they initiated proceedings under the Electricity Act. An Observation Mahazer was issued to the writ petitioner on 17.01.2010. As per the said Observation Mahazer, the seal in the meter terminal cover was intact. The company seal and seal by the MRT wing on the outer cover of the meter was also intact. However, the seal covering over the box in which the meter was kept had been damaged and the bottom portion had burnt. The said burning could not have happened either due to leakage of electricity or due to short circuit.
The Observation Mahazer further pointed out that the said burning of the meter would have happened only by some external interference and hence, there is theft of energy.

3. Based upon the above said Observation Mahazer, a provisional assessment order was issued to the writ petitioner demanding a sum of Rs.12,17,688/-. The petitioner had challenged the said provisional assessment order in W.P(MD).No.840 of 2010. The said writ petition was allowed on 02.01.2014 directing the respondents to pass orders after affording due opportunity to the writ petitioner. Thereafter, the petitioner has submitted his explanation on 06.03.2014. In the said explanation, the petitioner has contended that the meter should be sent for inspection to a lab in order to find out the reason for burning of the said meter. The petitioner has also undertaken to bear the expenses for the same. In the said explanation, the petitioner has agreed to accept the said inspection report and proceed further.

4. According to the petitioner, the second respondent herein has passed the present impugned order on 01.04.2014. In the impugned order, the second respondent herein in Paragraph No.8 has relied upon the inspection report as well the opinion expressed by the Enforcement Department. The second respondent has arrived at a finding that only in order to screen the theft of energy, the petitioner has created such burning of meter and hence, there is theft of energy. Based upon the said finding, the impugned final assessment order has been passed for a sum of Rs.10,17,688/-. This order is under challenge in the present writ petition.

5. The learned counsel for the petitioner had contended that burning of the meter was immediately reported by the petitioner mill on 10.12.2010 and they have requested for a fresh meter to be installed so that they could restart the factory. The petitioner mill has also paid the charges for the new meter. Thereafter, the respondents have issued a notice for conducting an inspection on 17.01.2010. When the respondents had issued the Observation Mahazer on 17.01.2010, immediately the petitioner has objected to the said Observation Mahazer and has also recorded the same in the Observation Mahazer. Thereafter, on the same day namely 17.01.2010, the petitioner has addressed a letter to the respondents that the meter is in intact and nothing was found to be tampered till date, and there is no possibility for tampering the seal.

6. The learned counsel for the petitioner had further sub
















Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top