2026 Supreme(Online)(Mad) 7734
IN THE HIGH COURT OF JUDICATURE AT MADRAS
HONOURABLE MR. JUSTICE KRISHNAN RAMASAMY
M.K.Kungumaraj – Appellant
Versus
The Director of Geology and – Respondent
BEFORE THE MADURAI BENGH OF MADRAS HIGH COURT DATED: 21.01.2026 CORAM THE HONOURABLE MR. JUSTICE KRISHNAN RAMASAMY W.P.(MD)No.13990 of 2025 and W.M.P.(MD)Nos.10146 & 19548 of 2025 M.K.Kungumaraj ... Petitioner wVs
1. The Director of Geology and Mining, Chennai.
2. The District Collector, Dindigul District, Dindigul.
3. The Assistant Director of Mines and Geology, Dindigul, Dindigul District.
4. The Superintending Engineer (Non- Conventional Energy) Tamilnadu Electricity Board, No 144, Anna Salai, Chennai.
5. The Tahsildar, Gujiliyamparai Taluk, Gujiliyamparai, Dindigul District.
6. JSP Green Wind 1 Private Limited, 6th Floor, DLF Tower, Najapkar Road, Modi Nagar, New Delhi - 110 015.
Rep by its Authorised Person Mr.A.Venkatesan. ... Respondents Prayer: Writ Petition filed under Article 226 of the Constitution of India praying to issue a Writ of Mandamus, forbearing the respondents 1 to 5 from allowing the 6th respondent for erecting the windmill within 300 meter from quarry site in S.No.188/2 morefully in S.No.l88 situated at Thirukuranam Village, Gujiliyamparai Village, Dindigul District within time stipulated by this Court.
For Petitioner : Mr.Srisaran, Senior Counsel for Mr.C.Jeganathan For Respondents : Mrs.K.Malathi, Addl. Govt. Pleader for R1 to R3 & R5 Mr.S.Deenadhayalan, Standing counsel for R4 Mr.Isaac Mohanlal, Senior Counsel, for M/s.Isaac Chambers for R6
O R D E R
This Writ Petition has been filed to forebear the respondents 1 to 5 from allowing the 6th respondent to erect the windmill within 300 meters from quarry site in S.No.188/2 morefully in S.No.l88 situated at Thirukuranam Village, Gujiliyamparai Village, Dindigul District.
2. When this matter came up for hearing on 07.01.2026, the learned Additional Government Pleader appearing for the respondents 1 to 3 and 5 submitted that in the event, subject windmill is erected 300 meters away from the quarry, no approval is required and sought for an accommodation to verify as to whether the place where the windmill is to be erected is 300 meters away from the quarry site or not. Subsequently, when the matter was listed on 09.01.2026, the Tahsildar, Gujiliyamparai, filed a report to the effect that 'Nkwg; b fyF; thup mikeJ; ss; ,ljj; pypUe;J 300 kPll; u; njhiytpy; fhw;whiy epWTk; gzp eilngwW; tUfpwJ'. The above report did not disclose whether the windmill is situated within 300 meters or 300 meters away from the quarry site.
3. Today, when the matter is taken up for hearing, the learned Additional Government Pleader appearing for the respondents 1 to 3 and 5 would submit that the windmill is going to be erected 300 meters away from the quarry site and therefore, no approval is required in the present case. This submission is recorded.
4. The learned senior counsel appearing for the petitioner would also submit that in the event if the windmill is going to be erected 300 meters away from the quarry site, requirement of obtaining approval is not necessary.
5. Upon hearing either sides, it is clear that the sixth respondent is going to erect the windmill 300 meters away from the quarry site and hence, no approval is required for erection of windmill as per Rule
36(1-A)(c) of the Tamil Nadu Mining Mineral Concession Rules, 1959.
6. Recording the above, this Writ Petition is disposed of. No costs.
Consequently, connected Miscellaneous Petitions are closed.
21.01.2026 Index : Yes/No Speaking / Non-speaking order Neutral Citation: Yes/No mbi To
1. The Director of Geology And Mining, Chennai.
2. The District Collector, Dindigul District, Dindigul.
3. The Assistant Director of Mines and Geology, Dindigul, Dindigul District.
4. The Superintending Engineer (Non- Conventional Energy) Tamilnadu Electricity Board, No 144, Anna Salai, Chennai.
5. The Tahsildar, Gujiliyamparai Taluk, Gujiliyamparai, Dindigul District.
KRISHNAN RAMASAMY, J.
mbi W.P.(MD)No.13990 of 2025