SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Online)(Mad) 14263

IN THE HIGH COURT OF JUDICATURE AT MADRAS
N. Anand Venkatesh, J
Ms Indostar Capital Finance Limited – Appellant
Versus
Srinivasan K – Respondent



Advocates:
For the Appellants/Petitioners: Mr. M.Arunachalam

Interim injunction granted to secure loan repayments pending arbitration due to irreparable loss risk.

Headnote:This judgment concerns an application filed under the Arbitration and Conciliation Act, 1996, seeking an interim injunction against a respondent for non-payment of loan installments secured by property. The court found a prima facie case based on the respondents' default and the irreparable loss to the applicant if the property was not secured. The court ruled in favor of granting the injunction until the arbitral proceedings are concluded.

Table of Content
1. application for interim injunction due to loan defaults. (Para 1 , 2 , 3 , 4)
2. hearing of the application for interim relief. (Para 6 , 7 , 8)
3. court finds balance of convenience favors injunction. (Para 9)
4. final decision to grant injunction until arbitration conclusion. (Para 10)

ORDER

This application has been filed under Section 9 of the Arbitration and Conciliation Act, 1996, (hereinafter referred to as “the Act”) seeking an interim injunction restraining the first respondent from alienating or parting with the property more fully described in the schedule to the Judge’s Summon.

2. The case of the applicant is that the respondents approached the applicant for a loan facility for the purchase of a commercial vehicle. The first respondent is the borrower, the second respondent is the co-borrower and the third respondent stood as the guarantor. They entered into a Loan-cum- Hypothecation Agreement, dated 10.05.2023 for a sum of Rs.13,94,000/- in respect of the purchase of the vehicle. The respondents agreed to repay back the loan with interest in 48 monthly instalments commencing from 10.06.2023 and ending on 10.05.2027. The vehicle was also hypothecated in favour of the applicant and the applicant will remain the owner of the vehicle until the last instalment is paid.

3. The further case of the applicant is that the respondents committed default in repayment of the loan amount and they have paid only 27 instalments and the remaining instalments have not been paid. As the default continued, the loan facility was recalled on 15.02.2025, and the respondents were called upon to pay a sum of Rs.10,21,618/-.

4. The agreement between the parties contains an arbitration clause in Clause 37. Accordingly, arbitration proceedings were also initiated by the appointment of a sole Arbitrator, and the arbitral proceedings are pending. 5. The applicant was not in a position to file an application under Section

17 of the Act before the sole Arbitrator, as the hypothecated vehicle could not be traced. In the mean time, the applicant was able to identify one of the properties belonging to the first respondent and, in order to secure the loan amount, has approached this Court seeking interim protection by restraining the first respondent from alienating or dealing with the said property.

6. When the application came up for hearing on 10.02.2026, this Court ordered notice to the respondents.

7. Though notice has been served on the respondents and their names have also been printed in the cause list, there is no representation either in person or through counsel on their behalf.

8. Heard the learned counsel appearing for the applicant and carefully perused the materials available on record.

9. A prima facie has been made out, as the amount due and payable by the respondents has not been paid till date. Insofar as the balance of convenience and the test of irreparable loss and hardship are concerned, the vehicle that was hypothecated in favour of the applicant has not been traced till date. Therefore, the only available security is the immovable property belonging to the first respondent, which has to be kept intact till the completion of the arbitral proceedings. Hence, balance of convenience is in favour of the applicant. If the property is not secured, even if an award is passed in favour of the applicant, they will not be able to recover the amount without the security and hence, it will cause irreparable loss to the applicant.

10. In the light of the above discussion, there shall be an order in injunction as prayed for, till the conclusion of the arbitral proceedings.

11. In the result, this Original Application is allowed in the above terms.

No costs.

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top