IN THE HIGH COURT OF JUDICATURE AT MADRAS
Honourable Ms. Justice P.T. ASHA
K.MAARIMUTHU – Appellant
Versus
The Secretary to Government – Respondent



IN THE HIGH COURT OF JUDICATURE AT MADRAS DATED: 10-02-2026 CORAM THE HON'BLE MS. JUSTICE P.T. ASHA K.Maarimuthu ..Petitioner(s)

Vs

1. The Secretary to Government Public Works Department, Water Resources Organization Irrigation, Government of Tamil Nadu, Fort St. George, Chennai-600 009.

2. The Chief Engineer Public Works Department, Water Resources Organization, Chepauk, Chennai-600 005.

3. The District Collector office of the Collectorate, Dharmapuri District.

4. The Executive Engineer Public Works Department, Water Resources Organisation, Mel Pennaiyaru Basin Division, Dharmapuri ..Respondent(s)

Prayer:- Writ petition filed under Article 226 of the Constitution of India praying for issuance of a writ of Mandamus, directing the 3rd and 4th respondent to construct a concrete wall on the western side of petitioners property at the end of the check dam proposed to be constructed across Nagavathi river for the purpose of preventing excess waterflow in the agricultural land belongs to the petitioner by disposing of the petitioners representation dated 15.12.2025 and the same within a time to be stipulated by this Honourable Court.

For Petitioner(s): Mr.S.Velmurugan For Respondent(s): Mr.Yogesh Kannadasan, SGP

ORDER

This Writ Petition has been filed for the following reliefs:-

“directing the 3rd and 4th respondent to construct a concrete wall on the western side of petitioners property at the end of the check dam proposed to be constructed across Nagavathi river for the purpose of preventing excess waterflow in the agricultural land belongs to the petitioner by disposing of the petitioners representation dated 15.12.2025 and the same within a time to be stipulated by this Honourable Court.”

2. A report has been submitted by the Assistant Engineer, WRD, Irrigation Section, Pennagaram which is signed on 02.02.2026, stating that as per the approved design, the petitioner’s land will not be prone to backwater effect or flooding. However, as a precautionary measure, earthen bunds will be provided on either side of the check dam, which, according to the Engineer, will safeguard the petitioner’s land.

3. The said report is taken on file and the Writ Petition is disposed of in terms of the said report. It is needless to state that if any damage is caused despite the measures taken, the State shall ensure adequate compensation to the petitioner. No costs.

10-02-2026 Index: Yes/No Speaking/Non-speaking order Neutral Citation: Yes/No SHR To

1. The Secretary to Government Public Works Department, Water Resources Organization Irrigation, Government of Tamil Nadu, Fort St. George, Chennai-600 009.

2. The Chief Engineer Public Works Department, Water Resources Organization, Chepauk, Chennai-600 005.

3. The District Collector office of the Collectorate, Dharmapuri District.

4. The Executive Engineer Public Works Department, Water Resources Organisation, Mel Pennaiyaru Basin Division, Dharmapuri P.T.ASHA, J.

SHR

10-02-2026

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top