2026 Supreme(Online)(Mad) 24078

IN THE HIGH COURT OF JUDICATURE AT MADRAS
KRISHNAN RAMASAMY, J
M/s.Serene Estates Pvt Ltd Rep. by its Authorised Signatory (Previously Known as Zillion Estate Pvt Ltd., and Nuziveedu Seeds Ltd) – Appellant
Versus
Government of Tamil Nadu, Rep. by its Secretary (Energy Department,) – Respondent
WMP NO. 1255 OF 2020



Advocates:
For the Appellants/Petitioners: Mr.JP.Karunakaran
For the Respondents: Mr.C.Gowthamaraja, GA for R1 & 4, Mr.D.R.Arunkumar, St.counsel, for R2 & 3

The court mandated reassessment of property compensation to comply with existing statutory provisions following the completion of construction.

Headnote:This Writ Petition has been filed under Article 226 of the Constitution of India, seeking a Writ of Mandamus to direct the respondents to assess the property for compensation under the Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013. The petitioner's request for compensation was initially rejected, but the court indicated that it should now be considered afresh following the completion of necessary works. The court directed a reassessment of the compensation, adhering to prior judicial determinations. Resultantly, the petitions were disposed of with a directive for timely compensation assessment.

Table of Content
1. assessment of compensation under statutory frameworks. (Para 1 , 5 , 6)
2. petitioner's request for compensation consideration. (Para 2 , 3 , 4)
3. court directives for timely compensation resolution. (Para 8)

COMMON ORDER

These writ petitions have been filed to direct the respondents to assess the extent of Schedule Property, which cannot be used for any construction and calculate and pay the compensation to the petitioner as per section 30(2) and First Schedule of Fair Compensation and Transparency in Land Acquisition, Rehabiliation and Resettlement Act, 2013.

2. The learned counsel for the petitioner would submit that in this case, initially, the respondent had intend to utilise the petitioner's subject land for the purpose of erecting the Electrical High Transmission Lines, due to which, he had faced great hardship and inconvenience. In this regard, a representation dated 13.01.2018 was filed by the petitioner, requesting the respondents to determine the compensation for the subject land. Subsequently, the said representation was rejected by virtue of order dated 15.03.2018 by stating that the compensation would be paid to the tower leg occupied area and line corridor after the completion of erection of towers in the subject land.

3. Further, he would contend that now, the erection of tower was completed by the respondent and hence, in terms of the aforesaid rejection order dated 15.03.2018, the respondents are supposed to have determined compensation for the subject land. Hence, this petition. In support of his submissions, he referred to the order dated 05.10.2023 passed in WP(MD)No.4715 of 2020.

4. In reply, the learned counsel for the respondent had fairly admitted and confirmed the submission made by the petitioner and would submit that the petitioner's representation dated 13.01.2018 will be considered afresh by the respondent. Hence, he requests this Court to pass appropriate orders.

5. Heard the learned counsel for the petitioner and the respondents and also perused the entire materials available on record.

6. In the cases on hand, initially, prior to the erection of Electrical High Transmission Lines in the subject land, a representation dated 13.01.2018 was filed by the petitioner before the respondents for determination of compensation. The said representation was rejected by stating that the compensation will be determined, for the tower leg occupied area and line corridor, only after the completion of erection of towers in the subject land.

7. Now, it was submitted by the respondents that the installation of tower at the subject land was completed and hence, the respondents will determine compensation by considering the petitioner's representation dated 13.01.2018 afresh.

8. In view of the above, this Court directs the respondents to consider the petitioner's representation dated 13.01.2018 afresh and determine compensation by taking into consideration of the law laid down by this Court vide order dated 05.10.2023 passed in WP(MD)No.4715 of 2020 after affording sufficient opportunities to the petitioner, within a period of 12 weeks from the date of receipt of a copy of this order.

9. With the above directions, these writ petitions are disposed of. No cost.

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top