SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Online)(Mad) 31538

IN THE HIGH COURT OF JUDICATURE AT MADRAS
KRISHNAN RAMASAMY, J
M/s.Maharani Paints Private Limited – Appellant
Versus
The State Industries Promotion Corporation of Tamil Nadu Ltd. – Respondent
WMP Nos. 6567 & 6571 of 2022 | W.P.No.6480 of 2022 | W.P.No.6485 of 2022



Advocates:
For the Appellants/Petitioners: Mr.C.Prasanth Gopal for Mr.K.K.Sivakumar
For the Respondents: Mr. M.P.Rajavelayutham

Failure to commence production within stipulated time or seek extension justifies plot allotment cancellation after prolonged delay.

Headnote:First Paragraph: The case involves challenge to orders cancelling allotment of industrial plot under terms requiring commercial production within 30 months from possession handover, citing lack of water supply and delayed pollution clearance. Court found petitioner failed to commence production or seek extension despite 12-year lapse, justifying cancellation. Findings upheld respondents' actions as reasonable after prolonged inaction. Second Paragraph: Key issue framed as non-compliance with allotment conditions despite extensions not sought. Ratio decidendi emphasizes strict adherence to timelines for industrial commencement; undue delay forfeits rights, protecting subsequent allottees' interests. Last Paragraph: Writ petitions disposed without interference; refund of payments directed proportionately.

Table of Content
1. petitioner allotted plot but failed to start production due to delays. (Para 2)
2. no extension sought despite 12-year non-compliance. (Para 3)
3. court upholds cancellation for timeline violation. (Para 4 , 5)
4. petitions dismissed; refund ordered proportionately. (Para 6)

Common Order

These writ petitions have been filed challenging the order dated

19.02.2020 passed by the 1st respondent cancelling the allotment and also the impugned order dated 09.08.2021 passed by the 2nd respondent evicting the petitioner from the Plot No.S-11 measuring 2.00 acres, SIPCOT Industrial Complex, Ranipet Phase-III.

2. The learned counsel appearing for the petitioner would submit that initially the plot was allotted in favour of the petitioner on 20.03.2008 thereafter, the same was handed over possession on 06.08.2008. Due to the various reasons, the petitioner was not able to commence commercial production therefore, the 1st respondent passed the impugned order dated 19.02.2020 cancelling the allotment made in favour of the petitioner and subsequently, the 2nd respondent passed an order dated 09.08.2021 evicting the petitioner from the said premises. He would submit that as per the terms and conditions of the allotment, the petitioner supposed to have commenced commercial production within 30 months from the date of handing over the plot however, the same was not complied due to the reasons that there was no water supply and there was a delay in getting the Pollution Control Board permission. He would further submit that the Pollution Control Board permission was obtained only in the year 2020 therefore, now they are ready to commence industrial activities. Challenging the said impugned orders, the petitioner filed these writ petitions.

3. The learned counsel appearing for the respondents would submit that though the plot was allotted on 20.03.2008 and handed over possession on 06.08.2008, for a period of twelve years i.e., till the date of cancellation of the allotment on 19.02.2020, the petitioner has not complied the terms and conditions of the allotment, particularly, commencement of industrial activities within 30 months and even after 30 months period, no application was made by the petitioner for the purpose of extension of time relaxing the 30 months period. He would further submit that even though the petitioner had failed to file application for extension of time and commenced the commercial production within the prescribed time limit, the respondents all along waited for twelve years and without any other option, cancelled the allotment made in favour of the petitioner and allotted the said plot to the third parties on 15.02.2022. It is stated that the third parties constructed factory in the said premises and commenced production therefore, in the event, if this Court is interfering with orders impugned, the third parties interest will affect.

4. Heard the learned counsel appearing for the petitioner as well as the respondents and perused the material available on record.

5. I find some force in the submission in the learned counsel appearing for the respondents. As per the terms and conditions of the allotment, the petitioner supposed to have commenced production within a period 30 months from the date of handing over of possession i.e., 06.08.2008, which is atleast on or before February, 2011. Admittedly, no such production was commenced on the part of the petitioner and if there is no production, the petitioner supposed to have made an application for extension of time for commencing production. Admittedly, no such application was also made by the petitioner. Under these circumstances, even after expiry of the time limit prescribed in the allotment, the respondents waited for more than 10 years and passed an order for cancellation. It is also undisputed that the third party allotment was made and the third parties constructed factory and commenced production.

6. Under these circumstances, this Court is not inclined t

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top