SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Online)(Mad) 31598

IN THE HIGH COURT OF JUDICATURE AT MADRAS
N.SATHISH KUMAR, M.JOTHIRAMAN, JJ
V.Best Engineers Represented by Its Managing Partner, Vignesh – Appellant
Versus
The Chief Engineer, Public Works Department, Trichy Region – Respondent
W.A.(MD)No.271 of 2026 | C.M.P.(MD)No.2823 of 2026 | W.P.(MD)No.87 of 2026



Advocates:
For the Appellants/Petitioners: Mr.H.Mohammed Imran
For the Respondents:Mr.Veera Kathiravan, Addl. Advocate General II Assisted by Mr.A.Kannan Addl. Govt. Pleader for R1 to R3

Tender rejection valid if bidder unregistered at evaluation due to unverifiable certificates.

Headnote:The tender notice invited bids for LED Street Light arrangement on Thuraiyur Bypass Road. Bidder's technical bid rejected due to missing solvency and encumbrance certificates required for PWD registration, unworkable rate quote, and absent technical acceptance letter. Single Judge upheld rejection as bidder not registered contractor at evaluation due to unverifiable certificates from new partner's encumbered property. Issues framed on validity of rejection grounds and registration status. Court observed delay in certificate verification post new partner induction prevented registration update before bid evaluation. Ratio: Unregistered contractor's bid ineligible; subsequent registration efforts irrelevant to evaluation date. Writ appeal dismissed, confirming single judge order and tender rejection.

Table of Content
1. tender bid rejected on solvency, rate, acceptance grounds (Para 2)
2. single judge upheld rejection due to registration failure (Para 3)
3. respondents confirm non-registration at evaluation (Para 4 , 5)
4. rejection justified by delayed verification (Para 6)
5. appeal dismissed without costs (Para 7)

(Judgment of the Court was delivered by N.SATHISH KUMAR, J.)

The present Writ Appeal is filed challenging the order dated

09.02.2026 passed by the learned Single Judge in W.P.(MD) No. 87 of 2026, whereby the Writ Petition filed by the Appellant herein was dismissed, thereby confirming the impugned order dated 26.12.2025, by which the technical bid of the Appellant came to be rejected.

2. According to the Writ Petitioner, the respondents issued a tender notice inviting applications for providing LED Street Light arrangement to Thuraiyur Bypass (Phase II) Road at Thuraiyur Taluk in Trichy District. The Writ Petitioner has submitted his tender on 11.12.2025 and e-tender was opened on 3.30 p.m., onwards on 12.12.2025. The evaluation process was continued up to 26.12.2025, and the minutes of the Evaluation Committee were uploaded on the same day, i.e., 26.12.2025, wherein the bid submitted by the Writ Petitioner Company was rejected on three grounds. The first ground is that the copy of the Solvency Certificate and Encumbrance Certificate as furnished to the registration authority at the time of registration in his or her/their name as contractor in PWD is not enclosed. The second ground is that the tenderer has quoted (-) 33% of value against the value put to tender which is non workable rate and hence, the quality of work will be questionable and the last ground is that the acceptance letter of the technical person concerned did not enclose. Challenging the said rejection order, the Writ Petitioner has filed the Writ Petition.

3. The Learned single Judge after analyzing the entire fact found that the last two grounds assigned by the Tender Evaluating Authority for rejecting the technical bid are not sustainable in the eye of law. With regard to the first ground, the learned single Judge has clearly noted that the registration of the petitioner firm as registered contractor could not be updated due to the fact that the properties offered as security by newly inducted partner viz., Thenmozhi were already encumbered one month prior to the date of Solvency Certificate. Even assuming that the solvency certificate is not required, the alternative certificates were uploaded by the Writ Petitioner only on 04.12.2025, seven days prior to the last date for submission of the bid. The last date for submission of tender is 11.12.2025 Therefore, the learned Single Judge has held that in between 04.12.2025 and 11.12.2025 the genuineness of the certificate enclosed by the petitioner firm could not be ascertained by the authorities. Hence, on the date of evaluation of technical bid, the petitioner firm's registration has not been updated at all. Since the petitioner firm is not a registered contractor, the question of evaluating the technical bid does not arise. Hence, accepting the reasons assigned by the Respondents for rejecting the tender, the learned Single Judge dismissed the Writ Petition. Though the Petitioner had placed considerable emphasis on the fact that, pursuant to the order of this Hon’ble Court, the Petitioner was directed to be registered as a Registered Contractor, the same had not been uploaded/updated in the official portal.

4. The learned Additional Advocate General appearing for Respondents 1 to 3 brought to the notice of this Hon’ble Court that, even in the subsequent Writ Petition filed by the Petitioner in W.P.(MD) No. 5359 of 2026, by order dated 26.02.2026, the Petitioner had sought for a relief to register it as a Registered Contractor. Hence, according to the learned Additional Advocate General, as on the date of evaluation of the technical bid, the Petitioner firm was not a Registered Contractor. He would fu

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top