SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Mad) 1466

IN THE HIGH COURT OF JUDICATURE AT MADRAS
M. DHANDAPANI, J.
Megha Engineering & Infrastructures Ltd. - Petitioner
Versus 
Government of Tamil Nadu Rep. By its Secretary Ministry of Municipal Administration, Urban & Water Supply Secretariat – Respondent 
W.P. NO. 10759 OF 2026, W.M.P. NOS. 11682 & 11683 OF 2026
Decided On : 30-04-2026

Advocates Appeared:
For the Petitioner: Mr. V.Vijay Narayan, SC, for M/s.Vignesh K
For the Respondent: Mr. Neeraj Kumar,Mr. Krishna Ravindran Dr. T.Sreenivasan, Spl. GP

Absence of authorisation in experience certificate does not constitute fraudulent practice unless knowingly misrepresented to mislead; courts exercise limited review in tenders, deferring to authority absent arbitrariness.

Headnote:(A) Constitution of India - Article 226 - Tender process - Judicial review - Fraudulent practice under tender conditions - Submission of experience certificate not issued by authorised person - Held, mere absence of authorisation does not constitute fraudulent practice unless knowingly or recklessly misrepresented to mislead for obtaining benefit - Tender authority rightly ignored disputed certificate and qualified bid on basis of other valid sub-contractor credentials - No perversity, arbitrariness or mala fides in evaluation process. (Paras 37-50)

(B) Tender evaluation - Scope of interference - Courts must exercise restraint and not act as appellate authority - Interference warranted only if decision is arbitrary, irrational, unreasonable, biased or mala fide - Greater latitude to tender authority in interpreting documents unless malicious misuse of power - Principles of commercial prudence govern evaluation. (Paras 31-35)

Facts of the case:
Petitioner, an unsuccessful bidder, challenged acceptance of rival bid for urban water supply project, alleging reliance on fabricated experience certificate from sub-contractor purportedly issued by third party, which was disowned for lack of authorisation. Tender authority qualified bid disregarding disputed certificate and relying on other sub-contractor's valid credentials.

Findings of Court:
No fraudulent practice established as disownment limited to lack of authorisation, not fabrication or falsity of work experience; no evidence of bidder's knowledge of irregularity; tender authority applied mind and correctly evaluated bids.

Issues: Whether submission of unauthorised certificate constitutes fraudulent practice mandating bid rejection; scope of judicial review in tender evaluation.

Ratio Decidendi: Fraudulent practice requires knowing or reckless misrepresentation to mislead for benefit; internal authorisation issues do not vitiate bid if other eligibility criteria met through valid documents; courts defer to expert evaluation absent perversity.

Result: Writ petition dismissed.

Table of Content
1. factual background of tender dispute and fabricated certificate (Para 1 , 2 , 3 , 4 , 6)
2. petitioner's argument: fraudulent practice mandates bid rejection (Para 5 , 7 , 8 , 9 , 10 , 11 , 12)
3. 3rd respondent's defense: no reliance on disputed certificate (Para 13 , 14 , 15 , 16 , 17 , 18)
4. 4th respondent's defense: limited judicial review, no fraud (Para 19 , 20 , 21 , 22 , 23 , 24 , 25 , 26 , 27 , 28 , 29)
5. judicial review principles in tender matters (Para 30 , 31 , 32 , 33 , 34 , 35)
6. analysis of fraudulent practice clause and jwil letter (Para 36 , 37 , 38 , 39 , 40 , 41 , 42 , 43 , 44 , 45 , 46 , 47)
7. no arbitrariness; tender authority's interpretation upheld (Para 48 , 49 , 50)
8. writ petition dismissed (Para 51)

ORDER :

M. DHANDAPANI, J.

1.Aggrieved by the order in and by which the bid submitted by the 4th respondent has been accepted by the 3rd respondent in rela floated for the purpose of undertaking the project ‘Chennai Ring Main Project’, the present petition has been filed by the petitioner.

2. It is the case of the petitioner that pursuant to the tender notification issued, in which the 2nd respondent was to serve as the execu 3rd respondent was to function as the implementing agency, the petitioner, along with four other entities participated in the tender process. The petitioner, in joint venture with JWIL Infra Ltd. (for short ‘JWIL’), the 4th respondent, in joint venture with respondents 5 and 6, Larsen & Toubro Ltd., Nagarjuna Construction Company Ltd. ad Eco Protection Engineers Pvt. Ltd., participated in the bid process.

3. It is the further case of the petitioner that the 4th respondent submitted its bid showing the 7th respondent as their sub-contractor to qualify for one of the technical eligibility for the purpose of construction of pipe carrying bridges of a particular length in a single contract for water supply project in urban area. To establish the said qualification, the 4th respondent had furnished the certificate of the 7th respondent, viz., its sub contractor dated 31.01.2026, which was alleged to have been issued by JWIL. By letter dated 10.2.2026, when the 3rd respondent called upon the petitioner to clarify the contents of the performance certificate issued by JWIL to the 7th respondent, JWIL, vide its letter dated 12.02.2026, denied having issued the said certificate; rather disowned the said certificate by stating that it was not issued by an authorised person of their company and further requested the 3rd respondent not to place any reliance on the said certificate.

4. Further, JWIL also issued show cause notice to the 7th respondent calling upon it to desist from using the said certificate and to immediately withdraw the same and to the said letter dated 12.02.2026, the 7th respondent, vide its reply dated 13.02.2026, had admitted that its staff, without the knowledge and approval of the Management had created and submitted the fabricated certificate and further admitted that it has not obtained any certificate pertaining to pipe carrying bridges from any authorised representative of JWIL. On receipt of the said communication from the 7th respondent, JWIL addressed a detailed representation to the 3rd respondent bringing to its notice Clause 3 of the Instructions to Bidders (for short ‘ITB’) which clearly defines ‘fraudulent practice’ committed by the 4th respondent and further submitted that such conduct constitutes an integrity violation and, therefore, called upon the 3rd respondent to take action against the 4th respondent and its joint venture by rejecting its bid.

5. Inspite of the categorical admission made by the 7th respondent that the certificate produced by the 4th respondent, was fabricated and not issued by JWIL, the 3rd respondent did not take effective steps to reject the bid and instead the 3rd respondent issued the BOQ summary. It is the further averment of the petitioner that the 3rd respondent ought to have disqualified the 4th respondent from further

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top