Authorities must consider applications for shifting of electricity poles after affording opportunity to affected parties.
Headnote:First Paragraph: Statute Analysis (Article 226 of the Constitution of India) - Facts of the Case: Petitioner owns housing plot properties in S.F.Nos.161 and 162 at Narasothipatti Village, Salem City, with pre-existing electricity poles and lines laid across the property without consent obstructing construction. Petitioner paid Rs.1,58,160/- as shifting charges on 09.04.2025 after representation, but work could not be undertaken due to objection by 6th respondent regarding public pathway in S.F.No.149.
Findings of Court:
Court directs the 3rd respondent to consider the petitioner’s case after affording an opportunity to the 6th respondent. Second Paragraph: Issues - Whether the electricity authorities should shift the electric poles and lines from petitioner’s property in accordance with law? Ratio Decidendi - Court observed that electricity authorities have the responsibility to consider such applications for shifting after affording opportunity to third parties who may be affected, in accordance with law and within reasonable time. Last Paragraph: Result - Writ petition is disposed of with direction to the 3rd respondent to take appropriate action within six weeks from the date of receipt of copy of this order. No costs.
| Table of Content |
|---|
| 1. petitioner's property ownership and payment of shifting charges (Para 1 , 2) |
| 2. submissions regarding opportunity to third party (Para 3 , 4) |
| 3. direction to consider case within timeline (Para 5) |
Writ Petition filed under Article 226 of the Constitution of India for issuance of a Writ of Mandamus directing the respondents 3 and 4 to forthwith shift the electricity lines from the existing electric poles situated in the petitioner’s property comprised in S.F.Nos.161 (Old No.16/2-P) and 162 (Old No.16/1B-P) at Narasothipatti Village, Salem City, to the newly erected poles with the aid of the 5th respondent and complete the said work within a time frame fixed by this Hon'ble Court.
For Petitioner(s): Mr.R.Nalliyappan For Respondent(s): Mr.I.Syed Sibghatulla for R1 to R4 Mr.V.Meghanathan Government Advocate (Crl. Side)
for R5
ORDER
This writ petition has been filed to direct the respondents 3 and 4 to forthwith shift the electricity lines from the existing electric poles situated in the petitioner’s property comprised in S.F.Nos.161 (Old No.16/2-P) and 162 (Old No.16/1B-P) at Narasothipatti Village, Salem City, to the newly erected poles with the aid of the 5th respondent and complete the said work within a time frame.
2.The petitioner states that he is the absolute owner of the housing plot properties comprised in S.F.Nos.161 (Old No.16/2-P) and 162 (Old No.16/ 1B-P) at Narasothipatti Village, Salem City. The petitioner is intended to put up construction in the said property. Originally, electric poles and electricity lines were laid across the middle of the petitioner’s property without his consent. Since it causes serious obstruction for construction and effective usage of the property, the petitioner made a representation before the electricity authorities for shifting of electric poles and accordingly, the authorities inspected the property and directed the petitioner to remit a sum of Rs.1,58,160/- towards shifting charges, which was duly paid by the petitioner on 09.04.2025. However, the 6th respondent has been causing obstruction for shifting of electric poles on the ground that the electricity lines would pass the public pathway in S.F.No.149. However, it is the contention of the petitioner that the 6th respondent has already been granted pathway rights by the petitioner by a registered document dated 10.03.2004 and that the 6th respondent had agreed for erection of electric poles. However, based on the said objection of the 6th respondent, the respondent authorities could not undertake the work on 07.04.2026. Hence, the petitioner has come forward with the present writ petition.
3.Learned counsel for the petitioner would submit that, despite payment of requisite charges, the respondent electricity authorities are not proceeding with the work of shifting of electric poles only based on the objection of the 6th respondent and therefore, prays for appropriate orders.
4.Mr.I.Syed Sibghatulla, learned counsel who takes notice for the respondents 1 to 4 (TANGEDCO), would submit that the 3rd respondent will consider the petitioner’s case and take appropriate action within a period of six weeks, after affording an opportunity to the 6th respondent. Mr.V.Meghanathan, learned Government Advocate (Crl. Side) takes notice for the 5th respondent.
5.In view of the submissions made by the learned counsel on either side, this Court directs the 3rd respondent to consider the petitioner’s case, after affording an opportunity to the 6th respondent, in accordance with law, and take appropriate action, within a period of six weeks from the date of receipt of a copy of this order. Since no adverse orders are passed, notice to the 6th respondent is dispensed with.