2026 Supreme(Online)(Mad) 47636
IN THE HIGH COURT OF JUDICATURE AT MADRAS
P. Velmurugan, K. Govindarajan Thilakavadi, JJ
Union of India – Appellant
Versus
Pundarikakshudu Sons – Respondent
CMA No. 1312 of 2023 | CMP No.13120 of 2023
Important Points
Subject
Arbitration Law - Challenge to Arbitral Award
Act Referred
Headnote
(B) Arbitration - Scope of authority - An arbitrator acting upon a dispute already settled through a final, satisfied award, acts without jurisdiction - Such proceedings and the resulting award are void as they conflict with the principles of res judicata and are opposed to public policy. (Paras 4.3, 11 and 14)
Facts of the case:
A contract was executed for construction work. Disputes arose and were settled through an initial arbitration, which reached finality after reaching the apex court. Following the satisfaction of the initial award, the contractor requested the appointment of a second arbitrator, who then passed a new award including claims for interest and additional losses. The employer challenged this second award, arguing that the contract was terminated and the arbitration agreement was spent upon the satisfaction of the initial decree. The trial court dismissed the challenge, leading to the current appeal.
Findings of Court:
The court found that although the appellant had participated in the second arbitration, the claim for additional interest on matters already adjudicated was impermissible. While the second arbitrator acted within authority regarding a new claim (bank guarantees), the re-adjudication of settled claims constituted a patent illegality. Therefore, the court partially set aside the award to preserve the integrity of final judgments.
Issues: Whether the appointment of a second arbitrator is valid after the initial award has attained finality and been satisfied, and whether an arbitrator can re-examine claims and interest requirements that were already subject to a final, executed award.
Ratio Decidendi: Once an arbitral award attains finality and the decretal amount is settled, the arbitration agreement is effectively discharged. Re-opening settled disputes or awarding further interest on satisfied claims is legally unsustainable, as it violates the principle of finality and res judicata, constituting patent illegality.
Result: Appeal partly allowed. The second arbitral award is set aside except for the portion concerning loss due to bank guarantees.
For the Appellants/Petitioners: AR.L. Sundaresan, C.Kulanthaivel
For the Respondents: V.Pushpa
| Table of Content |
|---|
| 1. factual history of initial arbitration and current dispute. (Para 1 , 2 , 7) |
| 2. appellant challenges second arbitration on grounds of limitation and res judicata. (Para 4 , 5) |
| 3. appointment of second arbitrator is valid if unchallenged and claims are distinct. (Para 8 , 9 , 10) |
| 4. court may partially set aside awards suffering from patent illegality. (Para 11 , 12 , 13 , 14 , 15 , 16) |
JUDGMENT
(Judgment of the Court was delivered by P.Velmurugan J.)
1.This Civil Miscellaneous Appeal has been filed against the order passed in A.O.P.No. 32 of 2008 on the file of the District Judge, Udhagamandalam dated 16.12.2019 confirming the order passed in CA.No.CESZ/WEL/10 of /77-78 on the file of the Arbitrator/ 2nd respondent herein dated 28.03.2008.
2. The case of the appellant/Union of India (herein after UOI) is that the 1st respondent which is a Partnership Firm/Contractor had entered into a contract with the appellant/UOI. The contract for construction of provision of married accommodation for 69 officers of D.S.S.C. Wellington was entered on 17.05.1977 between the appellant and the 1st respondent. The work commenced on 01.07.1977 and completed on 30.06.1979. The 1st respondent/Contractor raised a dispute and an Arbitrator was appointed to adjudicate the dispute between the appellant and the 1st respondent. Brig. B.V. Ahuja was appointed as Sole Arbitrator and the Arbitrator passed an award on 25.11.1985 for Rs.15,24,550.31 in favour of the 1st respondent/Contractor and Rs.1,22,803.78/- in favour of the appellant/UOI. The said award was challenged by the 1st respondent before the District Court, Udhagamandalam, in O.P.No.20/1986 and the learned District Judge, set aside the award in favour of UOI and confirmed the award passed in favour of the 1st respondent/Contractor by the decree and judgment dated 02.01.1994. The appellant took up the matter on appeal before this Court in CMA Nos.364, 366 and 367 of 1995, but all the three appeals were dismissed on 06.01.1997, upholding the decree passed by the District Judge. Thereafter, the appellant preferred Civil Appeal Nos.8337 to 8339 of 1997 before the Hon’ble Supreme Court of India and all the three appeals were dismissed and the decree and judgment of the District Judge, Udhagamandalam, were confirmed by the order dated 09.09.2003. Subsequently, in compliance of the decree, the appellant/UOI, deposited a sum of Rs.46,82,627/- being the decree amount together with interest into the Court and the 1st respondent had also withdrawn the same. However, after disposal of the matter by the Hon’ble Supreme Court on 09.09.2003, the 1st respondent/Contractor under his letter dated 03.03.2005 again requested for appointment of Arbitrator for adjudication of further disputes in respect of following claims and the same were denied and objected by the appellants UOI vide letter dated 18.10.2005.
(a) Claim No.1: Loss due to unwarranted extension of Bank Guarantees upto 1996 Rs.20,62,715/-.
(b) Claim No.2: Losses on account of non-release of FDR.
(c) Claim No.3: Interest payment till actual payment.
(d) Claim No.4: Cost of Arbitration.
2.1 However, considering the request of the 1st respondent/Contractor, the Appointing Authority mentioned in the contract agreement, appointed another Arbitrator/2nd Arbitrator/2nd respondent herein as a Sole Arbitrator. The appellant/UOI had made only one claim for the cost of arbitration of Rs.50,000/-.
2.2 The sole Arbitrator passed the award in favour of the 1st respondent on 28.03.2008 as detailed hereunder:
Award on Claim No.1: Keeping above in view I award an interest of 16% against 24% for the claim as per statement A and B. The claim No.1 is modified to that extent. The amount of award is Rs.8,86,564.00. The details are attached as Appendices C and D. Award on Claim No2: The claim was withdrawn by the builder during the hearing and hence Nil amount awarded against Claim No.2.
Award on Claim No.3: On a perusal of the documents submitted by both the parties, I