2026 Supreme(Online)(Mad) 50856
Prayer in O.A.No.542 of 2026:- Judge’s Summon under Order XIV Rule 8 of O.S. Rules read with Section 9(1)(d) of Arbitration and Conciliation Act, 1996, to grant an interim injunction restraining the Respondent No.1 from invoking the Bank Guarantees mentioned in the schedule to the Judges Summons, issued by Respondents No.2-5 herein, aggregating to Rs.310 Crores, pending adjudication of disputes between the Parties.
Prayer in Arb.Appln.No.1072 of 2026:- Judge’s Summons under Order XIV Rule 8 of O.S. Rules read with Section 9(1)(e) of Arbitration and Conciliation Act, 1996, to stay the operation of the impugned notice of part termination dated 30.05.2026 issued by the respondent No.1 to the applicant herein, pending adjudication of disputes between the parties.
A.No.2465 of 2026
EKK Infrastructure Limited
Represented by its Managing Director
Mr.Sanju Muhammed
Having its Office at
Building No.20/21, 2nd Floor,
Razack Garden Main Road,
Arumbakkam, Chennai – 600 106
..Applicant /Proposed 6th respondent
vs.
1.BNR Infrastructure Projects Private Limited
Represented by its Director
Mr.Charan Prasad B,
No.923, 17th Main Road,
Anna Nagar, Chennai – 600 040.
2.Yuzhan Technology (India) Private Limited
Represented by its Director,
Mr.Chia Wei Chen, Principal Office at B-04,
ESR Oil Park, Oragadam,
Walajabad Road, Varanavasi,
Sriperumbudur, Kanchirpuram 631 604.
3.Kotak Mahindra Bank,
Represented by its Senior Manager,
Mr.Arun S.
Anna Salai Branch,
Prestige Polygon
12th Floor, 471, Anna Salai,
Nandanam, Chennai 600035.
4.ICICI Bank Ltd,
Represented by its Authorised Signatory,
Mount Road Branch,
CSI Arulmanai Building,
Ground Floor, Anna Salai, Chennai – 600002.
5.HDFC Bank Limited,
Represented by its Manager, Ms.Deena S,
Koyambedu Branch,
No.18/77, Ayyappa Nagar,
1st Main Road, Opp to Marthoma School,
Chinmaya Nagar, Chennai – 600 092.
6.Indian Bank,
Represented by its Senior Manager,
Mr.Ankit Saha
MID Corporate Branch, Anna Salai
No.42, 1st Floor, GEE GEE Complex,
Anna Salai, Chennai – 600 002.
Prayer: Judges Summons filed under Order XIV Rule 8 of Madras High Court Original Side Rules read with Order I Rule 10(2) and Section 151 of the Code of Civil Procedure, 1908, to implead the Applicant herein as the 6th respondent in Arb.Application No.1072 of 2026.
Important Points
Subject
Arbitration - Interim Measures
Act Referred
Code of Civil Procedure, 1908: S.151, O.XIV R.8, O.I R.10(2)
Headnote
Facts of the case:
The applicant, a contractor, sought an interim injunction to restrain the respondent from invoking Bank Guarantees and to stay a partial termination notice issued on 30.05.2026. The respondent contended that the applicant breached contractual terms regarding project timelines, justifying termination and the right to retain materials and continue works through third parties.
Findings of Court:
The Court held that the contractual right of the respondent to continue work under Clause 18.1.7 is subject to the compliance period of 30 days granted to the contractor under Clause 18.1.3. As the deadline for compliance (29.06.2026) had not elapsed, the respondent could not prematurely utilize or dismantle the contractor's materials or equipment.
Issues: Whether the employer (respondent) is entitled to immediately take over the work and utilize the contractor's materials following a termination notice, despite the 30-day compliance period provided for post-termination obligations.
Ratio Decidendi: Contractual clauses must be read harmoniously; the right to resume work under Clause 18.1.7 does not supersede the 30-day window provided to the contractor to wind up obligations under Clause 18.1.3 or the requirement for a final settlement determination under Clause 18.1.5(d).
Result: Applications disposed of with directions to maintain status quo until the expiry of the notice period.
For the Appellants/Petitioners: P.S.Raman, Anirudh Krishnan, Adarsh Subramanian
For the Respondents: Sathish Parasaran, S.Manuraj, Srinath Sridevan, Arvind Srevatsa, S.R.Rajagopal, Akshay Pradeep
| Table of Content |
|---|
| 1. summary of existing disputes and previous status quo orders in construction arbitration. (Para 1 , 2 , 3 , 4 , 5) |
| 2. applicant's arguments regarding illegal termination and non-compliance with corrective notice clauses. (Para 6 , 7 , 8 , 9 , 10) |
| 3. respondent's counterarguments regarding contractor's delay and the employer's right to lien and resume works. (Para 11 , 12 , 13 , 14 , 15 , 16 , 17) |
| 4. analysis of post-termination obligations and the criteria for invoking lien on equipment/materials. (Para 18 , 19 , 20 , 21 , 22 , 23 , 24 , 25 , 26 , 27) |
| 5. determining that the employer's rights are contingent upon the expiry of the contractor's 30-day compliance window. (Para 28 , 29 , 30 , 31 , 32 , 33 , 34 , 35) |
COMMON ORDER
Heard the learned Senior Counsel appearing on behalf of the applicant as well as the learned Senior Counsel appearing on behalf of the respondents.
2. The contentious arguments with regard to the termination of the agreement that had been entered into between the parties had been placed on record. Arguments touching upon the merits, including allegations of delay in handing over the site and finalising the designs, were advanced on behalf of the applicant. On the other hand, the learned Senior Counsel appearing for the respondent had contested the claim and submitted that, without prejudice to the allegations that there has been a delay on the part of the respondent, there had also been delay on the side of the applicant in progressing with the works. These allegations have to be substantiated by leading in evidence.
3. Prima facie, from the materials placed on record, this Court is of the view that there had been delay in handing over the site and finalising the designs, as evidenced by the report of the M/s. Cushman and Wakefield India Private Limited, Project Co-ordinator, appointed by the respondent. It is further to be noted that whether the delays shown in the said report dated 23.05.2016, had any impact in the applicant’s delay in progressing with the contractual obligations need not be gone into in the present application.
4. In the present scenario, an Arbitrator has already been appointed on consent and has also been requested to enter upon reference and deal with the reliefs sought for by the parties. This Court, by its order dated 11.06.2026, on the understanding reached between the learned counsel appearing on either side, had appointed an Advocate Commissioner to have a joint inspection and, in the course of the same, had directed the parties to maintain status quo without prejudice to the ongoing construction activities.
5. The learned Senior Counsel appearing on either side had brought to the notice of this Court that, even though the parties have submitted themselves for arbitration to be conducted by a Sole Arbitrator, the said order has given rise to an anomalous situation in maintaining the status quo. It is the claim of the applicant that the status quo to be maintained cannot entitle the respondent or its contractors, appointed after termination of the applicant's contract, to dismantle or utilise the materials belonging to the applicant. On the other hand, it is the claim of the respondent that once the agreement had been terminated, it was imperative upon the applicant to remove its materials, and that the materials available at the site could be utilised by the respondent or its agents.
6. In that regard, Mr.P.S.Raman, learned Senior Counsel appearing for the applicant, drawing attention to the report of the M/s. Cushman and Wakefield India Private Limited, would submit that there had been admitted delays both on the part of the respondent and its design agency. In that regard, he would draw the attention of this Court to Clause 3.1.5 of the agreement, which envisages extension of time equivalent to the period of delay attributable to the employer/respondent. In that context, he had also referred to Clauses 4.1.2 and 4.4.2.
7. Referring to the aforesaid clauses, he would subm