2026 Supreme(Online)(Mad) 52608
IN THE HIGH COURT OF JUDICATURE AT MADRAS
M. Dhandapani, J
Shyam Trading Corporation – Appellant
Versus
State Industries Promotion Corporation of Tamil Nadu Ltd – Respondent
W.P. No.4801/2020 | W.M.P. No.5678/2020
Important Points
Subject
Civil - Contract Law
Act Referred
Headnote
(B) Estoppel - Doctrine of - Allottee having agreed in the lease deed to obtain building plan approvals from competent authority on its own, cannot turn around and claim that non-provision of layout approval by the respondent caused the failure to construct. (Paras 16-17, 30-33)
Facts of the case:
Petitioner firm was allotted a standalone industrial plot in 2007 for setting up a hotel and multi-purpose hall. Despite obtaining possession in 2009 and multiple extensions of time, the petitioner failed to commence commercial production or complete construction within the period stipulated in the lease agreement. The respondent issued notice for cancellation of allotment and directed the execution of a surrender deed. The petitioner challenged this on the ground that the respondent failed to provide a sanctioned layout necessary for seeking planning permission.
Findings of Court:
The court observed that the petitioner was under a contractual obligation per the lease deed to obtain all necessary statutory clearances and building plan approvals independently. The plot was a standalone site, not part of a larger approved layout. The court held that the petitioner, having failed to adhere to the timeline for over a decade despite multiple extensions, could not shift the blame to the respondent. The impugned order of cancellation was found to be in accordance with the terms of the lease deed.
Issues: Whether the 1st respondent's cancellation of the allotment and demand for a surrender deed due to the petitioner's failure to complete construction and commence production was arbitrary or illegal.
Ratio Decidendi: The petitioner is bound by the specific terms of the lease deed which mandated that the allottee must obtain independent building plan approvals for a standalone plot; therefore, failure to comply with the construction and production timelines constitutes a valid breach of contract justifying the cancellation of the allotment.
Result: Writ Petition dismissed.
For the Appellants/Petitioners: Mr. M.Vaidhiyanathan
For the Respondents: Mr. Abishek Murthy for R-1, Mr. M.Sivavarathanan, Govt. Counsel for R-2
| Table of Content |
|---|
| 1. summary of facts regarding allotment disputes and show-cause proceedings. (Para 1 , 2 , 3 , 4 , 5 , 6) |
| 2. arguments concerning contractual duties and responsibilities for building approvals. (Para 7 , 8 , 9 , 10 , 11 , 12 , 13 , 14 , 15 , 16 , 17 , 18 , 19 , 20) |
| 3. court's reasoning on breach of lease terms and failure to fulfill obligations. (Para 21 , 22 , 23 , 24 , 25 , 26 , 27 , 28 , 29 , 30 , 31 , 32 , 33 , 34) |
Writ Petition filed under Article 226 of the Constitution of India praying this Court to issue a writ of certiorari calling for the records of the 1st respondent culminating with its order bearing P-II/SIP/SPR/94/Shyam Trading/2014 dated 6.2.2020 and quash the same.
For Petitioner : Mr. M.Vaidhiyanathan
For Respondents : Mr. Abishek Murthy for R-1
Mr. M.Sivavarathanan,
Govt. Counsel for R-2
ORDER
Challenging the impugned communication dated 6.2.2020 in and by which the 1st respondent had directed the petitioner to execute a surrender deed within a particular time frame and the consequences that would follow on non-compliance, the present petition has been filed before this Court.
2. It is the case of the petitioner that it is a partnership firm, which applied for allotment of land in SIPCOT Industrial Park, Sriperumbudur for the purpose of putting up a hotel with a restaurant and a multi-purpose hall and based on the said request, the land to an extent of 2 acres in Plot No.C-1 (Phase III) comprised in S. Nos.1542 Part and 1543 Part of Sriperumbudur ‘V’ Village was allotted on payment of plot cost of Rs.89,85,000/-, which was paid by the petitioner on 27.12.2007. Inspite of the said allotment made, in view of certain disputes between the 1st respondent and the land owner, the lease deed was registered only on 29.12.2008 whereinafter possession of the land was taken by the petitioner.
3. It is the further averment of the petitioner that Clause 19 of the lease deed obligated the petitioner to commence construction within six months and complete the construction within 24 months from the date of allotment. On 9.6.2011, the 1st respondent issued a show cause notice to the petitioner alleging violation of non-compliance of Clause 19 of the lease deed and calling upon to show cause as to why the allotment should not be cancelled and possession of the plot taken under the Tamil Nadu Public Premises and Establishments Act to which reply was sent by the petitioner on 22.6.2011 requesting the 1st respondent to withdraw the show cause notice. In response to the further notice dated 6.2.2012, explanation was submitted by the petitioner on 20.2.2012 seeking six more months time for completing the project. Further notice was issued by the 1st respondent on 1.8.2012 to which reply dated 3.10.2012 was issued showing the progress in construction. The petitioner, on 27.11.2012, submitted its plan of construction to the 2nd respondent for approval along with the requisite fee. Once again, by letter dated 18.12.2019, the petitioner sought for extension of further six months time to complete the construction, which was granted by the 1st respondent and the 1st respondent also issued a No Objection letter permitting the petitioner to mortgage the plot for raising funds from the bank by withdrawing the show cause notice dated 1.8.2012.
4. By letter dated 11.1.2013, on the basis of the petitioner’s application for plan approval, the 2nd respondent directed the petitioner to produce a copy of the sanctioned layout which had been issued in favour of SIPCOT. Inspite of the petitioner requesting the 1st respondent to provide the copy of the sanctioned layout, while the same was not give, it was orally informed that no such sanction was necessary. On 29.1.2014, the petitioner was informed by the 1st respondent that action would be taken to cancel the allotment if the petitioner did not fulfil its obligations. On 12.2.2014, the petitioner sent its reply to the 1st respondent that its plan had been rejected by the 2nd respondent