2026 Supreme(Online)(Mad) 53472
IN THE HIGH COURT OF JUDICATURE AT MADRAS
Hemant Chandangoudar, J
Shamsullutha – Appellant
Versus
Director of Town and Country Planning – Respondent
W.P(MD)No.10221 of 2026
Important Points
Subject
Civil - Town Planning and Land Acquisition
Act Referred
Headnote
For the Appellants/Petitioners: SMA. Jinnah
For the Respondents: M.Mahaboob Athiff
| Table of Content |
|---|
| 1. challenge to land reservation lapse under the town and country planning act. (Para 1 , 2 , 3) |
| 2. application of statutory deeming provision for release of land after three years of inaction. (Para 4) |
| 3. declaration of reservation lapse and directions for record correction and building regularisation. (Para 5 , 6 , 7) |
Prayer: Writ Petition filed under Article 226 of the Constitution of India, praying this Court to issue a Writ of Declaration to declare the proposed reservation made in respect of petitioner's land situated in Survey No.25/1B measuring with an extent of 2 acres 36 cents, Palayamkottai Taluk, Melappalayam Village, Tirunelveli District as lapsed in light of section 38 of Tamil Nadu Town and Country Planning Act, 1971 (TN Act 35 of 1974) and consequently forbear the respondents herein from treating the development proposed in the said land as unauthorized development/construction.
For Petitioner : Mr.SMA. Jinnah
For Respondents : Mr.M.Mahaboob Athiff
Govt. Advocate for R1 and R2
No appearance for R3
ORDER
The petitioner has approached this Court seeking issuance of a Writ of Declaration declaring that the reservation of the petitioner’s land comprised in Survey No.25/1B, measuring an extent of 2 acres and 36 cents, situated in Melappalayam Village, Palayamkottai Taluk, Tirunelveli District, has lapsed by operation of Section 38 of the Tamil Nadu Town and Country Planning Act, 1971 (Tamil Nadu Act 35 of 1974), and consequently to forbear the respondents from treating any development or construction undertaken in the said land as unauthorized.
2.Heard the learned counsel appearing for the petitioner and the learned Government Advocate appearing for the respondents. The materials placed on record have also been perused.
3.The subject property was reserved for the formation of a scheme road under Detailed Development Plan No.6, which was published in the year 2000. For better appreciation, Section 38 of the Tamil Nadu Town and Country Planning Act, 1971, is extracted hereunder:
“38. Release of land.—If within three years from the date of publication of the notice in the Tamil Nadu Government Gazette under Section 26 or Section 27—
(a) no declaration as provided in sub-section (2) of Section 37 is published in respect of any land reserved, allotted or designated for any purpose specified in a regional plan, master plan, detailed development plan or new town development plan covered by such notice; or
(b) such land is not acquired by agreement, such land shall be deemed to be released from such reservation, allotment or designation.”
4.In the present case, it is not in dispute that although the subject land was reserved for the formation of a scheme road under the Detailed Development Plan, no steps were taken by the respondents to acquire the land within the period prescribed under Section 38 of the Act. Consequently, by virtue of the statutory deeming provision contained in Section 38(b) of the Tamil Nadu Town and Country Planning Act, 1971, the reservation in respect of the petitioner’s land stands lapsed and the land shall be deemed to have been released from such reservation.
5.In view of the above, the relief sought by the petitioner is liable to be granted. Accordingly, it is declared that the reservation made in respect of the petitioner’s land comprised in Survey No. 25/1B, measuring an extent of 2 acres and 36 cents, situated in Melappalayam Village, Palayamkottai Taluk, Tirunelveli District, has lapsed under Section 38 of the Tamil Nadu Town and Country Planning Act, 1971. The respondents are directed to carry out the necessary corrections in the relevant revenue and planning records so as to reflect the release of the subject land from reservation. The petitioner shall be entitled to enjoy and deal with the property in accordance with law.
6.However, insofar as the construction put up in the subject property is concerned, it is open to the petitioner to approach t