HIGH COURT OF JUDICATURE AT MADRAS
T.VIJAYALAKSHMI PANDIT – Appellant
Versus
G.PANEERSELVAM – Respondent
SA 208/2004
['M/S S KARTHIKEYAN', 'M/S R S KIRUBAKARAN', '', 'N THIAGARJAN', 'FOR RESPT']
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED : 16.04.2012
CORAM
THE HONOURABLE MR.JUSTICE V.PERIYA KARUPPIAH
S.A.No.208 of 2004
and C.M.P.No.1086 of 2004
1.T.Vijayalakshmi Pandit
2.A.Jayakumar
... Appellants / Plaintiffs
vs.
G.Paneerselvam
... Respondent / Defendant
Appeal filed under Section 100 of C.P.C. against the
judgment and decree dated 24.02.2003 made in O.S.No.433/92 on
the file of the Principal District Munsif Court, Vellore,
confirmed by the Judgment and Decree dated 24.07.2003 made in
A.S.No.30/2003 on the file of the Principal District Judge,
Vellore.
For Appellants : Mr.Rajendra Kumar
for Mr.S.Karthikeyan
For Respondents : Mr.AR.L.Sundaresan, Sr.Counsel
for Mr.R.S.Kirubakaran
J U D G M E N T
This appeal is directed against the judgment and decree
passed by the 1st appellate court in A.S.No.30 of 2003 dated
24.07.2003 in confirming the judgment and decree passed by the
trial court made in O.S.No.433 of 1992 dated 24.02.2003 in
dismissing the suit filed by the plaintiff.
2. The appellants were the plaintiffs and the respondent
was the defendant before the trial court.
https://hcservices.ecourts.gov.in/hcservices/
3. The case of the plaintiffs as stated in the plaint would
be as follows:-
The 1st plaintiff is the wife of the second plaintiff. She
purchased A- schedule property under the registered sale deed
dated 24.04.1987 for a valid consideration from its previous
owner one Govindammal. It forms a part of 0.58 acres of land in
S.No.99/1A. The plaintiffs are in possession and enjoyment of
the suit property. "A" schedule property was purchased as vacant
site for the purpose of putting up a house and immediately after
purchase the plaintiffs prepared a plan and got it approved by
the panchayat also.The licence granted by the panchayat dated
2.11.87 and the approved plan are also filed. As per the recital
of the sale deed dated 24.04.1987, on the northern and eastern
side of "A" schedule property there are roads i.e. 20 feet road
on the northern side and 15 feet road on eastern side. Before
the purchase of "A" schedule property the first plaintiff
entered into an agreement with the vendor Govindammal under an
agreement dated 25.01.1987, only after satisfying that there
are roads on northern and eastern side. On the western side of
"A" schedule property there is a school building. As the 'A'
schedule site is a east-west length wise plot the plaintiffs can
have entrance only from the eastern side, having access from 15
feet road. As the north to south measurement is only 30 feet and
as the vendor Govindammal has left a 15 feet road on the eastern
side the first plaintiff purchased the site. The plaintiff
would not have purchased the property if there is no road on the
eastern side and if there is no access from the east. But long
after purchase of "A" schedule site by the first plaintiff and
long after the approval of the plan by the Panchayat the
defendant seems to have purchased the remining area from the
vendor Govindammal some time in 1988. The defendant instead of
leaving the 15 feet road shown as ABCD in the plaint plan and
described in the 'B' Schedule hereunder seems to have included
in his sale deed. The defendant could not have purchased the B
schedule road as the common vendor Govindammal has already left
B schedule portion as road to have access for the 'A 'schedule
site. However, strangely the defendant included in his sale deed
and now claims to be the owner of the "B" schedule property. Now
he is claiming to be the owner of ABCD portion described in 'B'
schedule hereunder is now trying to put up construction over
and along ABCD line. If the defendant succeeds in putting up
construction of compound wall along ABC line the plaintiff
cannot have access to their plot. After approval of the plan by
panchayat the first plaintiff has availed loan from the
Government and