IN THE HIGH COURT OF MANIPUR: AT IMPHAL
MC(W.P.(C)) No. 38 of 2021
(Ref.: W.P.(C) No. 26 of 2021)
Seryyo Hungyo, aged about (62) years S/o (L) China Hungyo,
Special Class Contractor, a resident of Bungba Village, Ukhrul
District, Manipur, presently residing at mantripukhri Marcy Land,
P.O. Mantripukhri & P.S. Heingang, Imphal East, Manipur-
795002.
… Applicant
-Versus-
1. Shri Murphy Thumrah, aged about 53 years old, presently
working as Special Class Contractor, S/o L. Daniel Thumrah,
a resident of Lunghar Village, Ukhrul District, P.O.& P.S.
Manipur-795142.
… Respondent / Petitioner
2. The State of Manipur, represented by the Chief Secretary,
Govt. of Manipur, having its office at Old Secretariat, South
Block, P.O. & P.S. Imphal, Imphal West District, Manipur-
95001.
3. The Principal Secretary (RD & PR), Govt. of Manipur, having
its office at Old Secretariat, South Block, P.O. & P.S. Imphal,
Imphal West District, Manipur -95001.
4. The Chief Engineer, Rural Engineering Department (RED),
Manipur
State
Rural
Roads
Development
Agency
(MSRRDA), Govt. of Manipur, 4th Floor Secure its Office
Complex, At Line North AOC, Imphal, Manipur-795001.
... Performa Respondent
B E F O R E
HON’BLE MR. JUSTICE KH. NOBIN SINGH
For the applicant
:: Ms. Ayangleima, Adv.
For the respondents
:: Mr. N. Jotendro, Sr. Adv.
Mr. Niranjan Sanasam, GA
Date of Hearing
:: 11.03.2021
Date of Judgment & order
:: 22.03.2021
MAYAN
GLAMBA
M
CHANU
NANDINI
Digitally signed
by
MAYANGLAMB
AM CHANU
NANDINI
Date:
2021.03.22
16:58:06 +05'30'
MC(W.P.(C)) No. 38 of 2021
Page 2
O R D E R
[1]
Heard Ms. Ayangleima, learned Advocate appearing for
the applicant/ respondent No.4 while Shri N. Jotendro, learned
Senior Advocate for the respondent No.1/petitioner and Shri Niranjan
Sanasam, learned GA appears for the State respondents.
[2]
This is an application filed by the applicant/ respondent No.
4 praying for dismissal of the writ petition being WP(C) No.26 of
2021 on the inter-alia grounds that the said writ petition is not
maintainable and that the respondent No.1/ petitioner does not have
any locus standi to file it.
[3.1]
The writ petition being WP(C) No.26 of 2021 has been filed
by the respondent No.1/ petitioner questioning the validity and
correctness of the resolution dated 19-08-2019 of the Tender
Committee and work order dated 30-12-2020 issued by the Chief
Engineer (RED), MSRRDA, Government of Manipur in respect of the
Package No. MN09108 of PMGSY Phase-IX for construction of road
from LO26- Meiling to Ngaprum under Phungyar block of the Ukhrul
District, Manipur.
[3.2]
A NIT dated 28-11-2018 was issued by the Chief Engineer
(RED), MSRRDA, Manipur inviting tenders from the eligible
candidates in respect of various packages including the said
package. The respondent No.1/ petitioner along with the applicant/
respondent No.4 and others applied for the said package and all of
MC(W.P.(C)) No. 38 of 2021
Page 3
them were qualified in the Technical Bid. In the Financial Bid, both
the applicant/ respondent No.4 and the respondent/petitioner were
qualified as L2.
[3.3]
The applicant/ respondent No.4 filed a writ petition being
WP(C) No.627 of 2019 praying for cancelling all the bids of the
respondent Nos.4 & 5 therein, out of which the respondent No.1/
petitioner was the respondent No.4 and while the said writ petition
was pending, a decision was taken on 19-08-2019 by the Tender
Committee rejecting the bids submitted by 3(three) bidders in order
to re-float the tender. Since the NIT having been rejected, this Court
disposed of the said writ petition with the direction that the applicant/
respondent No.4 should submit a representation and in the event of
the same being submitted by him, the State respondents should
consider it and dispose of. In the said ord