SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Online)(MP) 4439

HIGH COURT OF MADHYA PRADESH
DEEPAK KHOT, J
M/S SWADESH DEVELOPERS AND BUILDERS – Appellant
Versus
INDIA LAND DEVELOPMENT PVT. LTD. – Respondent
MISC. APPEAL No. 4356 of 2025



Advocates:
For the Appellants/Petitioners: Shri Manoj Sharma, Shri Kabeer Paul
For the Respondents: Shri Sankalp Kochar

Court ruled that a temporary injunction requires proof of a prima facie case, irreparable loss, and balance of convenience; failing which, the injunction is unjustified.

Headnote:(A) Specific Relief Act, 1963 - Sections 41(e) and 41(ha) - Temporary injunction - Respondent sought injunction to halt construction by the appellant on claimed grounds of landslide risk - Court found no concluded contract existing and ruled the lower court overstepped its jurisdiction in granting relief - The respondent failed to prove prima facie case, irreparable loss, and balance of convenience. (Paras 5, 13, 14)

(B) Injunctions - A party seeking an injunction must demonstrate a prima facie case, irreversible loss, and balance of convenience in their favor - Without such demonstration, the court cannot grant the requested relief. (Paras 11, 12)

Facts of the case:
The appellant was restrained from construction on his land based on a claim that an agreement existed regarding a retaining wall for the safety of the respondent's land. The appellant argued there was no actionable contract.

Findings of Court:
The Court determined that the respondent lacked a prima facie case for the temporary injunction and that the lower court's actions were beyond its jurisdiction.

Issues: Whether a prima facie case was established by the respondent for granting a temporary injunction; whether there was a concluded contract.

Ratio Decidendi: The Court reiterated the necessity for a prima facie case to be presented and that bald pleadings do not satisfy necessary legal standards for injunctions. Injunctions require a clear justification and proving of damage to be admissible.

Result: Impugned order set aside; however, the appellant is directed not to raise construction on the respondent's land until the suit's resolution.

Table of Content
1. arguments presented by both parties regarding the validity of the contract. (Para 5)

ORDER

The case is listed today for admission and hearing on other interlocutory applications including I.A.No.10647/2025, application for vacating stay.

By the consent of counsel for the parties, the matter is heard finally.

Present appeal has been filed being aggrieved by the impugned order dated 07.02.2025 (Annexure P/1) passed in RCS No.812-A/2024 by VII Additional Sessions Judge, Bhopal; whereby application filed by respondent/plaintiff under Order 39 Rule 1 & 2 CPC has been allowed injuncting the appellant/defendant from raising construction/development over his land.

Signature Not Verified Signed by: ANAND KRISHNA

2. The respondent/plaintiff had filed a suit for specific performance, declaration and permanent injunction.

3. In reply to the application for temporary injunction, the defendant submitted that the defendant sent an offer letter dated 25.03.2022 to the plaintiff proposing construction of retaining wall, however, plaintiff in his reply dated 02.04.2022 did not accept the offer but instead merely inquired about the cost sharing aspect which does not constitute an agreement. It was also averred that mere anticipation of the plaintiff of landslide or some untoward incident over his land, the defendant cannot be restrained from construction/development of his own land and prayed for rejection of the application.

4. On the basis of the rival pleadings and documents, the learned Court below allowed the application under Order 39 Rule 1 & 2 CPC by granting temporary injunction in favour of respondent/plaintiff thereby restraining the appellant/defendant from raising construction/development over his land. Being aggrieved, the appellant/defendant has filed the instant appeal.

5. It has been submitted by learned Senior Counsel for the appellant that such impugned order dated 07.02.2025 is illegal, perverse to the material available on record and the Court below has exceeded in jurisdiction in granting temporary injunction in favour of the respondent/plaintiff. It is further submitted that there was no concluded contract to ascertain any obligation to be performed by the appellant/defendant and the same was mere communication between two parties. It is also submitted that even if such a contract is assumed Signature Not Verified Signed by: ANAND KRISHNA to exist, then also such a contract is not executable as per Section 41 (e) and (ha) of the Specific Relief Act. It is submitted that until permission was not given by the authorities for construction of retaining wall, there was no reason to believe that the appellant/defendant was under any obligation to construct the said retaining wall and therefore, prayed that the order impugned be set-

aside.

6. Refuting the submissions made by learned Senior counsel for the appellant, it is submitted by counsel for the respondent that the suit is filed by the respondent/plaintiff for specific performance, declaration and permanent injunction on the basis of an offer letter dated 25.03.2022 which was issued by appellant/defendant and accepted vide letter dated 02.04.2022 by the respondent/plaintiff with condition to bear 50% cost of retaining wall and as such it has been averred that the communication has turned into a concluded contract and the appellant cannot shirk its liability arising out of the said contract. It is further submitted that the appellant/plaintiff had started excavating the slope of the hill and cut it to the angle of 90 degree and vide letter dated 28.02.2024 has denied to erect the retaining wall. Some part of the land of the respondent/plaintiff is falling in the area where the excavation has been done at 90 degrees and there are chances of accident, land slide or mass destruction. It is also submitted that the appellant/defendant has started constructing multi-storey building and by way of letter dated 28.02.2024 has denied the concluded contract which may cause any

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top