SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

1964 Supreme(Online)(MP) 2

MADHYA PRADESH HIGH COURT
, J
Municipal Committee, Harda – Appellant
Versus
Harda Electric Supply Company (Private) Limited – Respondent
First Appeal



Advocates:
For the Appellants/Petitioners: Shri Dabir
For the Respondents: Shri Khirwadkar

The court affirmed that damages for breach of contract must be substantiated with reasonable certainty, allowing for presumptive calculations in cases of difficulty in exact quantification.

Headnote:(A) Arbitration Act - Sections 3, 17, and 32 - Electricity (Supply) Act, 1948 - Breach of contract - The Municipality breached its agreement with the Company by utilizing lower water heads for pumping than specified (130 feet), resulting in damages. The claim for surcharge was limited to three years preceding the suit under Art. 52 of the Limitation Act. (Paras 4, 6, 18, 24)

(B) Contracts - Statutory Requirements - Failure to comply with mandated signing procedures under municipal legislation rendered the supplementary agreement unenforceable. (Paras 20-21)

(C) Damages - The assessment of damages must prove loss with reasonable certainty despite difficulties in quantification, with the court acknowledging that damages must be substantiated yet allowing room for presumptions depending on the situation. (Paras 30-32)

(D) Result - The appeal is partly allowed, modifying the decree to Rs. 6,911/- with proportionate costs allowed to both parties.

Result: Appeal partly allowed.

Table of Content
1. initial case and agreement details (Para 1 , 2)
2. arguments regarding breach and contract interpretation (Para 3 , 5 , 6)
3. court's findings on breach of agreement (Para 4 , 7 , 9)
4. details of water supply mechanics and head calculation (Para 10 , 11)
5. importance of tappings and head impact on service (Para 12 , 14)
6. discussions on contract validity and nature of electricity (Para 18 , 20 , 21)
7. legal status and characteristics of electricity (Para 22 , 23)
8. impact of statutory obligations on the supplementary agreement (Para 27 , 28)
9. damages assessment principles and reasoning (Para 29 , 30)
10. final damage calculations and claims reevaluation (Para 32 , 33 , 34)
11. final conclusions and decree outcome (Para 35 , 41)

1. This first appeal arises from a suit instituted by the Harda Electric Supply Company (Private) Limited (hereinafter called the Company) against the Municipal Committee, Harda (hereinafter called the Municipality) for recovery of Rs. 50,000/- as damages and for other alternative reliefs. The suit was resisted by the Municipality. The Additional District Judge, Hoshangabad, passed a decree for Rs. 40,000/-. The Municipality has filed this appeal; the Company has filed cross - objections.

2. The plaintiff's case was that by an agreement dated July 31, 1936, the Electro Mechanics Ltd., Bombay, agreed to supply the Municipality with electric energy for the purpose of pumping approximately 3 lac gallons of water daily. The agreement was to operate for 25 years. Of the terms and conditions contained in it one was that the water pumped per unit would not be below 1000 gallons on an average "at the specified head of 130 feet''. By another clause, it was agreed between the contracting parties that the Municipality would pay to the Company two annas per unit of energy consumed. On November 29, 1939, the said Electro Mechanics Ltd., assigned all their right, title and interest in the aforesaid agreement to the plaintiff - Company by virtue of a deed.
In or about the year 1944 the Municipality, by surreptitiously making or opening new tappings and by directly pumping water through them, lowered the pumping head so that the discharge of water per unit increased and the Company was consequently put to loss of income. When the Company became aware of the resultant breach of the agreement, on the part of the Municipality, it protested. After some correspondence, the Municipality, by its resolution No. 4 dated October 15, 1951, agreed to pay to the Company 20 per cent surcharge on the total units consumed every month. This was accepted by the Company. Later on the Municipality resiled from this subsequent agreement for additional payment (hereinafter called the supplementary agreement).
Calling it a concluded contract, the plaintiff - Company claimed a decree for Rs. 12,206/5/3 for the period between 1-4-1950 and 31-3-1953 and Rs. 20,667/8/9 for the period between 1-4-1953 and 30-9-1956, total Rs. 32,873/14/-. Alternatively, it claimed a sum of Rs. 40,000/- on the basis of the right to enhance rates under the Electricity (Supply) Act, 1948 . As a second alternative, the plaintiff claimed a decree for Rs. 48,707/1/3 as damages for loss of income caused by pumping larger quantities of water for fewer number of units. This claim was for the period between 1-4-1950 and 30-9-1956. In addition to this, the plaintiff claimed damages for injury to the machinery and plant doe to overloading : Rs. 2,650/1/9 actually expended on repairs and Rs. 9,349/14/3 as compensation for the shortening of life of the pumping sets by wear and tear, total Rs. 12,000/-.


3. The appellant resisted the suit, inter alia, on the ground that no new tappings were made by the Municipality. By the existence and working of the tappings the water head was not appreciably lowered, that is, to 80 or 85 feet, as alleged by the plaintiff. Even if there was any such lowering of the water head, it did not in any way offend against the terms of the a











































































































Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top