SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(MP) 472

IN THE HIGH COURT OF MADHYA PRADESH AT JABALPUR
Sanjeev Sachdeva, C.J., Vinay Saraf, J.
Sahakar Global Ltd – Petitioner
Versus
The State Of Madhya Pradesh And Others – Respondents
Writ Petition No. 48901 of 2025, Writ Petition No. 1880 of 2026
Decided On : 18-03-2026

Advocates Appeared:
For the Petitioner:Shri Nalin Kohli, Senior Counsel (through VC) and Shri Naman Nagrath, Senior Counsel with Shri Shoeb Hasan Khan, Shri Rachit Kumar Soni, Shri Shanky Agrawal, Shri Siddharth Shukla and Shri Harsh Shukla, Advocates for petitioner.
For the Respondent:Shri Prashant Singh, Advocate General with Shri Swapnil Ganguly, Deputy Advocate General, Shri Nilesh Yadav, Additional Advocate General (through VC )

A tender inviting authority may validly nullify a tender process or reject the highest bid to prevent loss to the public exchequer and protect public interest, as the highest bidder possesses no vested right to the contract until it is formally concluded.

Headnote:(A) Sand Mining Rules - Right to nullify tender process - Bidders who previously held contracts for specific mine blocks and subsequently surrendered them participated in a fresh auction for the same blocks, quoting significantly lower rates than in the previous tender - Such action, leading to substantial potential loss to the public exchequer, constitutes a valid ground for the tender inviting authority to nullify the process in the larger public interest (Paras 7, 11 and 15).

(B) Tender Law - Rights of highest bidder - The highest bidder has no vested right to have the auction concluded in their favour - The government or its authority validly retains the power to accept or reject the highest bid in the interest of public revenue (Para 19).

(C) Contract Law - Right to reject/nullify - Where the Notice Inviting Tender specifically reserves the right to nullify the process or reject bids without assigning reasons, such a provision is valid, provided the decision taken is reasonable and not arbitrary (Paras 16, 17 and 18).

Facts of the case:
Petitioners were the highest bidders in a tender process for sand mine blocks. It was observed that the petitioners had been successful bidders for the same blocks in a previous round but had surrendered the contracts. In the current tender, they quoted rates substantially lower than their own previous bids, which would have resulted in a significant financial loss to the public exchequer. Consequently, the board of the tender inviting authority took a conscious decision to nullify the tender process to protect public interest and await the notification of amended rules concerning the surrender of mines.

Findings of Court:
The court found that the tender inviting authority took a conscious and documented decision based on calculations of potential financial loss to the state. The decision was deemed reasonable, as the authority acted to prevent the exploitation of gaps in the existing rules regarding the surrender of mines.

Issues: Whether the tender inviting authority could legally nullify the entire tender process after the identification of highest bidders on the grounds of potential loss to the public exchequer.

Ratio Decidendi: A tender inviting authority is not bound to accept the highest bid and can nullify the process if valid reasons exist, particularly to prevent loss to the public exchequer and protect the larger public interest. In the absence of a concluded contract, a bidder has no right other than the right to equality and fair treatment. A decision to nullify based on financial prudence and public interest is a reasonable view that does not warrant judicial interference.

Result: The Petitions are accordingly dismissed.

Legal Category Hierarchy

  • administrative law
    • government contracts
      • tender process
        • nullification of tender (Para 14, 15, 16, 17, 18, 21)
        • rights of bidders (Para 19, 20)
    • judicial review
      • reasonableness of administrative action (Para 14, 15, 21)
  • practice and procedure
    • writ petitions
      • maintainability (Para 5)
  • natural resources law
    • mining
      • sand mining rules (Para 6, 11)

Table of Contents

1. Challenge to nullification of tender process for sand mines due to alleged loss to public exchequer. (Para 1 , 2 , 5 , 6 , 7 , 8 , 9 , 10 , 11 )

2. Petitioners argued arbitrary cancellation; respondents justified cancellation to prevent loss to exchequer. (Para 3 , 4 , 12 , 13 )

3. Petitions dismissed; petitioners may participate in fresh tender if eligible. (Para 22 , 23 , 24 )

4. Can a tender inviting authority nullify the tender process after bids are opened?

Yes, if valid reasons exist and the authority acted in public interest, provided the tender conditions reserve such right. (Para 14 , 15 , 16 , 17 , 18 , 21 )

5. Does a highest bidder have a vested right to have the auction concluded in their favour?

No, until the bid is accepted, there is no concluded contract and the authority can reject the highest bid in the interest of public revenue. (Para 19 , 20 )

6. What constitutes a valid reason for nullifying a tender?

Loss to public exchequer from earlier bidders surrendering and re-bidding at lower rates can be a valid reason for cancellation. (Para 7 , 8 , 9 , 11 , 15 )

7. Can the authority nullify the tender without assigning reasons if the tender conditions permit?

Yes, if the tender conditions reserve the right to nullify without assigning any reason, the authority can do so. (Para 16 , 17 , 18 )

ORDER :

Sanjeev Sachdeva, CJ.

Petitioners have filed the subject petitions impugning communication dated 05.12.2025 whereby the tender inviting authority had decided to nullify the tender process that was initiated with the Notice Inviting Tender (NIT) dated 18.09.2025.

2. The contentions of the petitioners primarily are that petitioners were the highest bidders for the respective blocks of sand mines which were tendered in different districts and despite petitioners being the highest bidders, the tender process has been canceled without assigning any reason.

3. Learned Senior Counsel for the petitioners contend that since the petitioners were the highest bidders, there is no justification to arbitrarily nullify the tender process.

4. In W.P. No.1880 of 2026 when the petition was listed on 20th January 2026, respondents were directed to file a brief reply disclosing the reasons behind cancellation of the entire tender process along with the necessary note sheets. Reply has been filed by the respondents in W.P. No. 1880 of 2026 and same reply has been adopted in W.P. No. 48901 of 2025. Learned Advocate General appearing for the State submits that since the tender process for both the blocks was nullified by the same decision, common reply is relied upon.

5. For the purposes of expedition, reference may be had to the reply submitted in W.P. No. 1880 of 2026. Though the reply raises a preliminary objection with regard to maintainability of the petitions, we are considering primarily the reasons recorded in the reply for passing of the impugned order nullifying the tender process.

6. This relevant portion reads as under :

(PART B):- REASONS FOR PASSING OF THE IMPUGNED ORDER

i. That against the NIT floated 18.09.2022, the petitioner (M/s Dhanshri Merchandise Private Limited) has filed W.P. No. 49937/2025 who has participated for group Katni while petitioner (Sahakar Global Limited) has filed W.P. No.48901/2025 who has participated for the group Shahdol. That it is observed that earlier also the similar tender is being issued for tender quantity of 2000000 of group Katni,wherein the reserve price was 500000000, wherein the petitioner Dhanlakshmi Merchandise Private Limited has quoted the highest price and the rate quoted by him is 323.883 rupees per cubic meter and in the current tender proceedings the petitioner (Dhanlakshmi Merchandise Private Limited) has quoted a price of Rs. 540741111 @ 270.371 rupees per cubic meter. Thus, now, being an H1 bidder, he has quoted fewer prices than the previous bid. Similarly, for the group Shahdol earlier, the petitioner (Sahakar Global Limited) has quoted 391.151 rupees per cubic meter in the previous tender and in the current tender, the petitioner (Sahakar Global Limited) has coded 273.886 rupees per cubic meter. If being a HI price the petitioner (Shahkar Global in W.P. No. 48901/2025) has earlier quoted 688425999 in previous bid of the tender and in present tender he has quoted 482040000, thus eventually, from the previous tender, both the petitioners like Shahdol and Katni Group has quoted much less than the previous tender. Thus, the tendering authority, while evaluating the tender process after participation by all the bidders have observed that these successful bidders are also the successful bidders of the previous round, and they have quoted much higher price being a HI bidder in earlier tender.

ii. That after declaring the H1 bidder or the successful bidder in the previous tender, these petitioners have surrendered their group, which resulted into fresh auction /present NIT dated 18.09.2025 and now the same persons have quoted less amount thus being a H1 bidder of previous tender. Thus by surrendering the tender / contract now they become again the HI bidder with much less amount. In these circumstances, the loss to the public exchequer cannot be ruled out.

iii. That the board of the Mining Corporation on 19.11.2025 has evaluated these aspects of awarding the contract and when such an aspect i

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

AI

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top