IN THE HIGH COURT OF MADHYA PRADESH AT JABALPUR
HON'BLE SHRI JUSTICE VIVEK JAIN
Smt Kamala Jaiswal – Appellant
Versus
Shri Ram Chandra Jaiswal – Respondent
MP 2930/2025
Warija Ghildiyal,Advocate General
##PAGE1##
IN THE HIGH COURT OF MADHYA PRADESH AT JABALPUR BEFORE HON'BLE SHRI JUSTICE VIVEK JAIN
ON THE 9 OF APRIL, 2026 MISC. PETITION No. 2930 of 2025 SMT KAMALA JAISWAL Versus SHRI RAM CHANDRA JAISWAL AND OTHERS Appearance:
Shri Kapil Sharma - Advocate for the petitioner.
Shri K.K. Gautam Panel Lawyer for the respondent-State.
Shri Premendra Singh- Advocate for the respondents no. 1 to 3.
ORDER The present petition has been filed challenging the orders Annexure P/1 and P/2 dated 20.11.2024 and 16.04.2025 passed by the SDO and by the Additional Collector respectively, under Section 129(5) and in revision. 2. The necessary facts for the purpose of disposal of the present petition are that demarcation proceedings were conducted on 22/04/2018 and against the said demarcation proceedings, objections/challenge under Section 129(5) of MPLR Code was filed by the present respondents on 18/08/2020, which was with a delay of more than 5 years. The limitation period from the date of demarcation dated 22/04/2018 is 45 days to make challenge. The SDO by the composite order dated 20/11/2024 allowed the application under Section 5 Limitation Act and condoned the delay and by the same order passed the order on merits remanded the matter back to the Tehsildar to carry out fresh demarcation by holding that the demarcation proceedings do not seem to be proper.
##PAGE2##3. Against the said order, the petitioner had filed revision before the Additional Collector, but the said revision has been said to be not maintainable and has been dismissed as not maintainable because no further remedy against the final adjudication of SDO on an application under Section 129(5) has been provided under the MPLR Code. The aforesaid legal position that the revision against the order passed by the SDO is not maintainable could not be disputed by the counsel for the petitioner, but he submitted that since he has made a challenge to the order Annexure P/1 passed by the SDO also. Therefore, though the revision against the order of SDO order was rejected as being not maintainable, this court should take up the legality of the order passed by the SDO.
4. While taking up the challenge to the order Annexure P/1 dated
20.11.2024, it is seen that the application before the SDO was filed on 18/02/2023, which was a delay of more than 5 years from the date of order of Tehsildar. Demarcation took place on 22/02/2018 which was confirmed by the Tahsildar on 08/05/2018. The entire order of SDO revolves on merits of the case and so far as the question of delay is concerned, the delay has been condoned in only one single line mentioning only one single line of consideration which is as under:-
"धारा 5 प(cid:5)रसीमा अिधिनयम अतं गत(cid:16) उभय प(cid:19)(cid:20) के तक(cid:16) (cid:23)वण कर (cid:26)कया जाकर (cid:28)वलंब सदभा(cid:28)वक होने से (cid:34)वीकार "
(cid:26)कया गया। (cid:36)करण म(cid:37) उभय प(cid:19)(cid:20) के अिंतम तक(cid:16) का (cid:23)वण (cid:26)कया गया।.
5. This is the entire consideration on the application under Section 5 Limitation Act by the SDO. The limitation is admittedly 45 days and the SDO was required to apply its mind as to whether any sufficient cause has been shown by the applicant before him for condonation of delay. However, the SDO has simply written that delay seems to be bonafide without even recording arguments of the applicant before him in the matter of condonation of delay and condoned the delay.
##PAGE3##6. The aforesaid manner of condonation of delay of a long period of
5 years is totally alien and unknown to law. The SDO could not have acted in this manner and condoned the delay without writing a single word as to why he finds any sufficient cause for condonation of delay. In fact, he has simply written that the delay seems to be bonafide without even writing the argument of the applicant before him in the matter of condonation of the delay.
7. The matter would now go back to the SDO who would now first take up the application for condonation of delay