IN THE HIGH COURT OF MADHYA PRADESH AT INDORE


NEUTRAL CITATION NO. 2026:MPHC-IND:28553


WRIT PETITION No. 954 of 2026

CNR No.: MPHC020010852026


PRIYANSHU JAIN Versus UNION OF INDIA AND OTHERS


Shri Lavesh Saraswat – Advocate with Shri Shivendra Singh Parihar – Advocate for the petitioner.

Shri Abhinav Dhanodkar – Advocate for the Intervenor.

Shri Pradyumna Kibe – G.A. for respondent Nos.2, 3, 4, 8 and 9/State.

Shri Amol Shrivastava – Advocate for the respondent No.6- M.P. Metro Rail Corporation Limited.

Ms. Kamakshi Singh – Advocate for the respondent No.7/IMC.


HON'BLE SHRI JUSTICE SUBODH ABHYANKAR & HON'BLE SHRI JUSTICE JAI KUMAR PILLAI


Reserved on : 08.10.2026

Pronounced on : 22.10.2026


(SUBODH ABHYANKAR)


JUDGE


(JAI KUMAR PILLAI)


JUDGE


Pankaj

Legal Category Hierarchy

  • administrative law
    • public interest litigation (Para 2, 12, 15)
    • judicial review (Para 15, 17)
  • infrastructure and transport
    • metro rail projects (Para 3, 9, 11, 12)
  • environmental law
    • wildlife protection (Para 5, 10, 20)
    • forestry and tree conservation (Para 13, 20)
  • practice and procedure
    • stare decisis (Para 17, 19)

Advocates:
Abhay Saraswat,Deputy Solicitor General[R-1]

Table of Contents

1. Public Interest Litigation seeking to restrain tree felling and protect bird habitats at a site designated for the construction of an underground urban mass rapid transit project. (Para 2 , 3 )

2. Petitioners allege destruction of wildlife habitat violating statutory protections, while respondents argue the project is technically fixed, approved, and immune to challenge based on prior judicial findings. (Para 5 , 6 , 7 , 8 , 9 , 10 , 11 , 12 , 13 , 14 )

3. The court observed that the project alignment and technical feasibility were settled in earlier proceedings, precluding interference under the principle of stare decisis and the finality of prior orders. (Para 15 , 16 , 17 , 18 , 19 )

4. Judicial review of technical planning decisions, such as metro route alignments previously upheld, cannot be circumvented through subsequent public interest petitions by challenging the project's incidental consequences. (Para 16 , 17 )

5. The petition was dismissed with specific directions to ensure construction-related tree clearing is conducted in a phased manner under expert supervision with mandatory compensatory plantation obligations. (Para 20 , 21 , 22 , 23 )

6. Can a public interest litigation be entertained to challenge an approved infrastructure project alignment previously affirmed by a court?

No, once a project's alignment has been judicially scrutinized and confirmed, the principle of stare decisis prevents the court from reopening the issue, as matters settled by a coordinate bench attain finality. (Para 15 , 16 , 17 )

7. Does a statutory administrative approval for a public works project override independent challenges to its environmental impact?

Yes, where a project has received requisite governmental approvals and prior judicial concurrence, the court will not substitute expert findings on alignment, but may issue supplementary directions to mitigate specific environmental harm. (Para 11 , 15 , 19 , 20 )

8. What is the court's role in mitigating environmental impact when the core infrastructure project is permitted?

While the court may decline to interfere with the project itself, it exercises its inherent power to issue conditional directions such as mandatory expert supervision of tree felling and specific compensatory plantation schedules to minimize ecological distress. (Para 20 , 21 , 22 )

This petition having been heard and reserved for orders, coming on for pronouncement this day, the Court passed the following:

O R D E R

Per: Justice Subodh Abhyankar:-

1] Heard.

2] The present writ petition has been filed by the petitioner under Article 226 of the Constitution of India, is in the nature of Public Interest Litigation (PIL), seeking the following reliefs :-

“i. Issue any appropriate writ to direct the Respondent No.1 to 9 to not cut any trees from the said land.

ii. Issue any appropriate writ to direct the Respondents to pass a prohibitory order against the Respondent No. 6, at once to prevent cutting of the trees and destroying the nests and habitat of the birds from the Rani Sarai Land (S.P. Office Premises Indore) and further direct the respondent no. 6 to obey and implement provisions of The Wildlife (Protection) Act 1972 in the interest of justice.

iii. Direct the Respondents to frame policy and guidelines with regard to the Transplantation Policy of Trees.

iv. Direct the Respondents to maintain the trees in the city instead of attempting to make them fall or engage in deforestation.

v. Pass any other suitable writ, order or direction as this Hon’ble Court may deem fit and proper in the interest of Justice.”

3] Although, the petitioner is aggrieved of the proposed construction of the underground Metro Station at Rani Sarai land (S.P. Office Premises Indore), which would require the felling of more than 150 trees on which nests of 1000 birds would be destroyed, which is their only habitat left in the city of Indore, where they come to roost, would be destroyed. The petitioner is also joined by the intervener in his cause by the intervener, the Nature Volunteers’ Society, through its president Padmshri Shri Bhalchandra Mondhe, by filing an application for intervention I.A.No.10209/2026.

4] Before hearing this petition finally, on 29.09.2026, we have also visited the site along with the parties and their respective counsel, in order to ascertain the claim of the petitioner. And we also directed the counsel for the respondent No.6 to come up with alternative plans, and today, a report has also been filed by the respondent No.6 giving details of the alternative plans in respect of the other adjacent lands, which, according to the petitioners and the intervener can be acquired for the purposes of construction of underground metro station.

5] Counsel for the petitioner has submitted that cutting of the trees on which thousands of birds, including parrots or parakeets, which are protected under the Wild Life (Protection) Act, 1972 (hereinafter referred to as “the Act of 1972’) come to roost, would certainly amount to an offence under the Act of 1972.

6] It is also submitted by the counsel for the petitioner as also the intervenor that if the trees are allowed to be cut, it would cause irreparable damage to the city of Indore, and this rich legacy would be lost forever. The details of the trees which are proposed to be cut are also given in the representation submitted by the petitioners. Counsel have also submitted that there are alternative lands available around the Rani Sarai, also including that of Regal Talkies, Gandhi Hall, and Pritamlal dua Sabhagrah, and thus, it is submitted that the lands available in and about the said areas can be used for construction of underground metro stations.

7] It is also submitted that even though there are hundreds of other trees already available in the vicinity, but still, those trees are of no use to the birds, as the majority of the birds come to the Rani Sarai premises only to roost, and thus, it is not merely a question of cutting of trees, but a question of saving the life of thousands birds who would lose their natural habitat because of Metro project.

8] Counsel for the petitioner has also submitted that a perusal of the metro route from Palasia to Railway Station would also reveal that it is curved, and it is not known as to what was the reason to not to directl

1