2026 Supreme(Online)(MP) 124982
IN THE HIGH COURT OF MADHYA PRADESH AT INDORE
BEFORE HON'BLE SHRI JUSTICE VINAY SARAF
ARBITRATION CASE No. 6 of 2026
CNR No.: MPHC020010732026
SAM INDUSTRIES LTD THROUGH AUTHORIZED REPRESENTATIVE MR. RAJENDRA KUMAR PASARI Versus MAHESH AND OTHERS
Appearance:
Shri Vijay Kumar Assudani - Advocate for the applicant.
Shri Ramesh Kumar Chandrawade - Advocate for the respondent No.1.
Shri Lokesh Kumar Bhatnagar - Advocate for the respondent No.2.
Shri Dattatray Kale - Advocate for the respondent No.3.
Heard on: 01.10.2026
Pronounced on: 23.10.2026.
(VINAY SARAF)
JUDGE
VM
ORDER
1. This Arbitration Application has been filed u/S. 11 (6) of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as "1996 Act") for appointment of Arbitrator by the applicant.
2. The facts suffice for disposal of this application in nutshell are that the non applicants are the real brothers and joint owners of the undivided land admeasuring 5.67 hectares of Survey No. 242/2 of village Tillor Bujurg, Tehsil Bicholi Hapsi, District Indore (hereinafter referred to as "subject land"). The applicant and non applicant no. 1 Mahesh entered into an agreement dated 4.2.2025 for development of the part of the subject land admeasuring 2.358 hectare. Though the name of non-applicant no. 2 Brijlal has also been mentioned in the agreement as one of the executants, however, his signatures are not available on the agreement. It was recorded in the agreement itself that in respect of the balance land, a separate development agreement will be entered into between the parties. Clause 14 of the Development Agreements provides for resolution of dispute in accordance with the provisions of the 1996 Act.
3. The applicant after entering into the development agreement, issued a notice to the non applicant No. 1 for carrying out the demarcation, partition and measurement of the subject land to ascertain the part of the land, in respect of which, the development agreement was executed. The allegation of the applicant is that despite entering into the agreement, the non applicant No. 1 neglected to fulfill his part of the contract and, therefore, the notice was issued and later on the arbitration Clause was invoked by issuance of subsequent notice. The applicant further pleaded that during this period non applicant No. 2 executed a registered relinquishment deed in favour of non applicant No. 1 and 3 on 20.5.2025 and relinquished his rights in the subject land equally in favour of non applicant No. 1 and non applicant No. 3 and as a result of execution of the relinquishment deed by non applicant No. 2, the non applicant No. 1 and non applicant No. 3 have acquired 1/2 - 1/2 share in the subject land and the Development Agreement was also executed by non applicant No. 1 for 1/2 of the total subject land i.e. 2.358 hectare.
4. The applicant suggested the name of proposed Arbitrator, but in reply the non applicant denied the execution of development agreement and levelled the allegation of forgery and fraud upon the applicant and did not extend his consent on any of the proposed name. The applicant filed an application u/s 9 of the 1996 Act, before the Commercial Court, Indore seeking temporary injunction against the non applicants on the ground that a public notice dated 22.9.2025 has been published in daily newspaper 'Agniban' and the non applicants are trying to alienate the subject land. The application was ultimately allowed and the Commercial Court has restrained the non applicants from alienating, incumbering or transferring the subject land in favour of any third party by order dated 5.3.2026, which is the subject matter of arbitration appeal pending before the division bench.
5. During the pendency of this application, the non applicant No. 3 Mukesh Dangi filed a Civil Suit RCS No. 1372-A/2025 in the Court of XXXth District Judge, Indore for declaration and permanent injunction on the allegation that the alleged Development Agreement is not binding on the non applicant No. 3 and same has been prepared by committing fraud and forgery by the applicant. In the said Civil Suit the applicant moved an application under Order 7 Rule 11 of the CPC read with Sec. 8 of the 1996 Act for rejection of the plaint and referring the parties for arbitration on the ground that the subject development agreement contains an arbitration clause. The application has been dismissed by the trial court vide order dated 5.3.2026 and that order is the subject matter of Arbitration Appeal No. 86/2026, which has been heard analogously with this arbitration