Date of Pronouncement:
28/05/2024
Allowed
Page 1 of 8
AFR / NAFR
CHHATTISGARH STATE
CONSUMER DISPUTES REDRESSAL COMMISSION
PANDRI, RAIPUR
Date of Institution: 04/09/2023
Date of Final Hearing: 30/04/2024
Date of Pronouncement: 28/05/2024
APPEAL No.- FA/23/143
IN THE MATTER OF :
Branch Manager, Indusind Bank Limited,
Ambedkar Chowk, Ambikapur,
Dist. SURGUJA (C.G.)
… Appellant
Through: Smt. Nupur Pal, Advocate
Vs.
1. Firoz Kumar Beck
S/o. Shri Telesphore Beck,
R/o. House No.137, Ward No.07, Sarabkombo, Tah. Bagicha,
Dist. JASHPUR (CG)
… Respondent No.1.
Through: Shri Sharad Karke, Advocate
2. Manager, Tiwari Motors,
Dealer: Mahindra Ltd. Truck & Bus Division,
M.G. Road, Ambikapur,
Dist. SURGUJA (C.G.)
… Respondent No.2.
Through: Proceeded ex-parte.
CORAM: -
HON’BLE SHRI JUSTICE GAUTAM CHOURDIYA, PRESIDENT
HON’BLE SHRI PRAMOD KUMAR VARMA, MEMBER
PRESENT: -
Smt. Nupur Pal, Advocate for the appellant.
Shri Sharad Karke, Advocate for the respondent No.1.
The matter was proceeded ex-parte against the respondent No.2.
ORDER
PER: - JUSTICE GAUTAM CHOURDIYA, PRESIDENT This appeal, filed under Section 41 of the Consumer Protection Act 2019 (hereinafter called “the Act” for short) is directed against order dated 28.07.2023 passed by District Consumer Disputes Redressal Commission, Ambikapur (hereinafter called “District Commission” for short) in complaint case No.CC/2019/144 whereby the complaint filed by the respondent No.1 herein was partly allowed and the opposite party No.2 / appellant herein was directed to pay to the complainant / respondent No.1 the amount of wrongful loss suffered by him of Rs.6,40,850/- (Six Lacs Forty Thousand Eight Hundred and Fifty) with interest @ 6% p.a.
from the date of complaint 24.12.2019 till the actual date of payment. The Date of Pronouncement:
28/05/2024 Allowed Page 2 of 8 opposite party No.2/ appellant was also directed to issue NoC pertaining to the loan contract of vehicle of the complainant/ respondent No.1 and to reflect his CIBIL as debt free. Compensation for mental agony Rs.25,000/-
2. In nutshell the facts of the case are that the complainant/ respondent No.1 on 29.03.2018 purchased as Mahindra Cosmo bus bearing registration No.CG-15-AB-0799 from the opposite party No.1/ respondent No.2 for Rs.16,56,400/- under hire purchase agreement with the opposite party No.2/ appellant. Rs.3,50,000/- were deposited as down payment and loan of Rs.14,00,000/- was obtained from the opposite party No.2/ appellant which was to be repaid in equal monthly installments of Rs.41,550/-. As per story narrated by the complainant/ respondent No.1 three installments were paid in time on 05.05.2018, 05.06.2018 and 05.07.2018 respectively. The fourth and fifth installments were paid with overdue charges on 27.09.2018, sixth installment with overdue charges on 05.01.2019. Due to breakdown of the bus of the complainant/ respondent No.1 in the month of October he could not pay further installments of the loan. On 05.01.2019 without giving intimation to the complainant/ respondent No.1 the bus was seized by the opposite party No.2/ appellant due to non-payment of installments. Vide letter dated 12.02.2019 the complainant/ respondent No.1 was asked by the opposite party No.2/ Date of Pronouncement:
28/05/2024 Allowed Page 3 of 8 appellant to deposit Rs.16,15,081/-, on which he went to deposit the entire amount of Rs.16,15,081/-, but they refused to accept the same. On 05.04.2019 the complainant / respondent No.1 again visited the opposite party No.2/ appellant with the entire amount for depositing the same, where he was informed that his bus had been sold in auction. Alleging the action of the opposite party No.2/ appellant as deficiency in service complaint was filed seeking direction for the opposite party No.2/ appellant to return his bus bearing registration No.CG-15-AB-0799, to pay compensation of Rs.1,00,000/- and cost of litigation.
3. The opposite party No.1 / respondent No.2 did not file written version, affidavit and documents before the District Commission and the matter was proceeded ex-parte against them vide order 12.06.2023.
4. The opposite party No.2/ appellant in its written version took preliminary objection regarding jurisdiction of the District Commission on the ground that in the loan agreement it was agreed by the parties that the courts at Mum
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.