SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Online)(NCDRC) 352

NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION
J. Rajendra, Presiding Member, Anoop Kumar Mendiratta, Member
Veeresh Berry – Appellant
Versus
Citi Center Developers – Respondent
FIRST APPEAL NO. 197 OF 2026



Advocates:
For the Appellants/Petitioners: Jasbir Singh Malik, Prachi Sohi

A party seeking condonation of delay under the Consumer Protection Act must provide a satisfactory explanation for each day of delay, demonstrating reasonable diligence; routine excuses regarding record collection or personal stress do not constitute 'sufficient cause' to override statutory limitations.

Headnote:(A) Consumer Protection Act - Condonation of delay - Applicant must satisfy the court with sufficient cause for every day's delay - Delay of 179 days - Reasons cited such as complexity of legal issues, collection of records, and financial stress were found to be routine and inadequate - Failure to demonstrate reasonable diligence or bona fide conduct leads to dismissal of the application for condonation of delay (Para 15).

Facts of the case:
The appellant challenged an order passed by the State Commission. Due to a delay of 179 days in filing the appeal, the appellant moved an application for condonation of delay citing complex legal issues, the requirement to collect voluminous records, and personal hardship as reasons.

Findings of Court:
The Commission found that the reasons provided were insufficient to explain the day-to-day delay and stated that the appellant failed to act with reasonable diligence as required under the law.

Issues: Whether the appellant has provided sufficient cause to condone the 179-day delay in filing the appeal.

Ratio Decidendi: The principle that the law of limitation must be applied with rigour; 'sufficient cause' requires the party to show they were prevented from prosecuting the case diligently and not merely suffering from routine inconvenience.

Result: Application for condonation of delay disallowed and appeal dismissed.

Table of Content
1. summary of delay and the appellant's justification. (Para 1 , 2 , 3 , 4)
2. quantification of the delay period requiring explanation. (Para 5 , 14)
3. judicial precedents on 'sufficient cause' and limitation. (Para 6 , 7 , 8 , 9 , 10 , 11 , 12 , 13)
4. conclusion of the court on insufficiency of reasons. (Para 15 , 16 , 17)

ORDER

1. As per the record of the Registry, there is a delay of 179 days in filing this First Appeal. Accordingly IA/3400/2026 has been filed by the Appellant seeking Condonation of delay.

2. In the said Application, the appellant has stated that after the order was pronounced, the certified copy was applied for and was made available after some time. The Appellant is a senior citizen aged about 68 years and a retired officer from Indian Oil Corporation, who had taken voluntary retirement to start an independent business which unfortunately could not be commenced due to non-delivery of possession of the commercial units in question. He was under mental stress and financial strain owing to prolonged litigation, continued non-delivery of lawful possession, and partial denial of contractual reliefs despite favourable findings recorded by the State Commission.

3. The Appellant averred that immediately upon receipt of the certified copy of the order, the Appellant approached his counsel for legal advice. Since the matter involved complex issues relating to contractual penalty @2% per month compounded quarterly, unilateral alteration of layout plan, reduction of undivided land share, GST demands and interpretation of statutory provisions under RERA and the Consumer Protection Act, detailed consultations and examination of voluminous record were required. The Appellant was also required to collect complete records including agreements, brochure, correspondence, email communications and other annexures forming part of the record before the State Commission, which consumed considerable time. In the intervening period also witnessed pendency of connected proceedings filed by the Respondents and related developments which required legal evaluation before finalising the present Appeal.

4. The learned counsel for Appellant argued that on 26.08.2025, the impugned order pronounced by the State Commission and in early September 2025, certified copy applied for. The copy was made available in Mid-September 2025, upon receipt of the certified copy, the Appellant, being a senior citizen aged 68 years and suffering continuous financial hardship due to non-delivery of possession since 2016, required time to understand the financial and legal implications of the partial relief granted. Late September 2025 to October 2025, the Appellant was simultaneously required to defend the First Appeal No. 628/2025 filed by the Respondents before this Commission, wherein substantial issues relating to possession, compensation and GST demand were involved. The Appellant had to priorities defending his awarded relief before challenging the denied portion. He argued that in Oct-Nov 2025, detailed consultations were held with counsel at Delhi. The matter involved complex contractual clauses (2% per month compounded quarterly penalty), reduction of undivided land share, unilateral structural alterations under Section 14 of RERA, and reciprocal penalty jurisprudence. The Appellant stated that he had to retrieve agreements-2014, brochure copies, layout plans, modified sanction plans, email correspondence dated 22.06.2018, clarification letters dated 03.07.2018, photographs, and pleadings filed before the State Commission. The record was voluminous. He argued that in November-December 2025, drafting of the appeal required detailed financial recalculation of contractual penalty @ 2% compounded quarterly on Rs.1.60 Crores from 17.10.2016 onward, which itself required tabulation and legal structuring. He further argued that the Appellant, being dependent on post-retirement savings and without possession of his commercial u

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top