SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Online)(NCDRC) 373

NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION
Inder Jit Singh, Presiding Member, Sudhir Kumar Jain, Member
Alok Jain – Appellant
Versus
Jaguar Infrastructures Pvt. Ltd. – Respondent
Consumer Complaint No. 2 of 2017



Advocates:
For the Appellants/Petitioners: Vibhor Garg, Sharon Jacob
For the Respondents: Manish Varma, Somya Chugh

A developer cannot enforce one-sided contractual clauses, such as capped penalty provisions, to escape liability for delayed possession or service deficiency, and shall be liable for full refund with interest where project delays are inordinate and statutory approvals have lapsed.

Headnote:(A) Consumer Protection Act, 1986 - Section 21(a)(i), 12(1)(c), 2(1)(g), 2(1)(r) - Builder Buyer Agreement - Delayed possession - Unfair trade practice - Refund of principal amount with 9% interest - Class action maintainability determined by aggregate value of claims - Force majeure claims rejected for routine economic downturns - One-sided clauses in builder-buyer agreements declared unconscionable - Litigation costs awarded. (Paras 7, 8, 9, 10, 11, 14)

Facts of the case:
A group of homebuyers filed a class action complaint against the developer for failing to deliver possession of residential units in the project “Aryan Apartment” within the promised 42-month timeframe. Complainants alleged the project was stalled, statutory approvals had expired, and the developer engaged in unfair trade practices by selling units without proper sanction. The developer defended the delay citing force majeure events like demonetization and economic recession, and accused buyers of being defaulters.

Findings of Court:
The Commission held the complaint maintainable as a class action having pecuniary jurisdiction based on the aggregate value. It rejected the force majeure defense, noting the breaches predated the cited events and that developers cannot escape liability through one-sided contract terms. The court ordered immediate refund of principal deposits with 9% interest.

Issues: 1. Maintainability of the complaint as a class action and pecuniary jurisdiction. 2. Whether the developer committed deficiency in service and unfair trade practice. 3. Validity of the 'force majeure' defense. 4. Enforceability of one-sided compensation clauses in the builder-buyer agreement.

Ratio Decidendi: Contractual clauses which are wholly one-sided, unfair, and unreasonable are unconscionable and void under the act. A developer cannot rely on such clauses to limit liability for inordinate project delays or to excuse contractual obligations via general economic difficulties.

Result: Complaint allowed; full refund ordered with 9% interest and litigation costs.

Table of Content
1. summary of facts, booking details, and allegations regarding delayed possession and unfair trade practices. (Para 1 , 2 , 3 , 4)
2. summation of parties' contentions regarding jurisdiction and liability. (Para 5)
3. establishment of maintainability and pecuniary jurisdiction for class action proceedings. (Para 6 , 7)
4. discussion on deficiency of service, rejection of force majeure, and invalidation of one-sided agreement clauses. (Para 8 , 9 , 10)
5. adjudication of the quantum of refund and directions for compensatory interest. (Para 11 , 12 , 13 , 14 , 15)

ORDER

DR. INDER JIT SINGH, PRESIDING MEMBER

1. The present Consumer Complaint (CC) has been filed under Section 21(a)(i) read with Section 12(1)(c) of the Consumer Protection Act, 1986 by the Complainants (a class of homebuyers) against the Opposite Party, inter alia praying for directions to the Opposite Party:

i. To refund the entire principal amounts deposited by each of the Complainants towards their respective units in the project "Aryan Apartment";

ii. To pay interest @24% per annum on the refunded amounts from the date of each deposit till realization;

iii. To pay compensation of Rs.3,00,000/- per complainant for mental agony, harassment and increased cost of alternative accommodation; and

iv. To pay litigation expenses of Rs.50,000/- per complainant.

2. It is averred/stated in the Complaint that:

i. The Opposite Party entered into a Collaboration Agreement dated 31.08.2012 with the original landowners for development of about 7000 sq. yards of Abadi land at Sector 73, Noida, Sarfabad, U.P. for construction of approximately 400 flats (1 BDR and 2 BDR units). Relying on the Opposite Party's aggressive marketing and promises of "speedy construction and timely delivery", the Complainants booked various residential units in the project "Aryan Apartment" between 2013 and 2014.

ii. The Complainants entered into standardized Builder Buyer Agreements (BBA) with the Opposite Party under different payment plans (Down Payment, Flexi Payment, Construction Linked, Subvention Plans). Substantial amounts were deposited, Complainant Nos. 1 & 2 deposited Rs.12,61,822/- for a 2 BHK unit (C1-416) having total consideration of Rs.33,09,189/-; Complainant Nos.3 & 4 deposited Rs.11,55,755/- for a 3 BHK unit (C1-511) of Rs.47,66,624/-.

iii. Under Clause 9.1 of the BBA, the Opposite Party committed to complete construction and hand over possession within 42 (forty-two) months from the date of the respective applications. For many Complainants, the 42-month period expired in 2016 or 2017, yet possession was not offered.

iv. The Complainants allege that the project was virtually abandoned: Tower A never commenced, Tower C1 was unilaterally split into two phases without consent, and digging for the second phase of Tower C1 had not begun even years after bookings.

v. Unfair trade practice is alleged: the Opposite Party sold 3 BHK units even though the Collaboration Agreement and sanctioned layout only permitted 1 BDR and 2 BDR units. The term "BHK" (including Hall) was used to camouflage this lack of approval.

vi. During a meeting on 13.02.2015, it was revealed that all statutory approvals, layout plans and NOCs from Zila Panchayat had expired and were not renewed by the Builder, which also prevented buyers from securing institutional financing.

vii. Several Complainants sent emails requesting cancellation and refund citing complete halt in construction for over six months, but received evasive replies. A joint Legal Notice dated 09.08.2016 demanding refund with 24% interest was also not responded to by the Opposite Party.

3. The Opposite Party in its written statement/reply stated that:

i. The complaint is not maintainable on the ground of pecuniary jurisdiction as the original four complainants had deposited only Rs.45,26,133/-, which is below the Rs.1 Crore threshold under Section 21 of the Act. It was also contended that there is no "common grievance" because e

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top