NATIONAL COMPANY LAW APPELLATE TRIBUNAL
Ashok Bhushan, J
Atul Paper Pvt. Ltd. – Appellant
Versus
Rakesh Kumar Jain, Liquidator for RG Infra Build Pvt. Ltd. – Respondent
Company Appeal (AT) (Insolvency) Nos.1100 & 1101 of 2024 | Comp. App. (AT) (Ins) No. 1311 of 2024 | Comp. App. (AT) (Ins) No. 2137 of 2024
| Table of Content |
|---|
| 1. overview of appeals filed (Para 1 , 2) |
| 2. court’s considerations on the matter (Para 3 , 8 , 9 , 10 , 13 , 15 , 16) |
| 3. arguments presented by parties (Para 5 , 6 , 7) |
| 4. court's reasoning on rights and claims (Para 12 , 14 , 18) |
| 5. final decision and directions (Para 20) |
JUDGMENT
Ashok Bhushan, J.
These three Appeal(s) have been filed challenging the same order dated 06.05.2024 passed by National Company Law Tribunal, New Delhi Bench (Court – II) in IA No.355 of 2021 and CA No.26/2023 in CP (IB)- 917(ND) 2019. Company Appeal (AT) (Ins.) Nos.1100 & 1101 of 2024 have been filed by M/s Atul Paper Pvt. Ltd., who is in possession of B-101, First Floor at RG City Centre and has filed claim before the Liquidator of the Corporate Debtor (“CD”) – M/s RG Infra Build Pvt. Ltd. Company Appeal (AT) (Ins.) Nos.1311 of 2024 has been filed by the Liquidator of the CD, challenging the part of direction issued by Adjudicating Authority in IA No.355 of 2021, whereas Company Appeal (AT) (Ins.) Nos.2137 of 2024 has been filed by Punjab National Bank, a Financial Creditor of the CD, challenging part of the order passed in IA No.355 of 2021.
2. Brief facts of the case necessary to be noticed for deciding the Appeal are:
(i) The Appellant entered into an Agreement to Sell dated 24.04.2018 with the CD – RG Infra Build Pvt. Ltd. for sale of commercial unit B-101, First Floor at RG City Centre, admeasuring built up area of 301.75 meters, for a total sale consideration of Rs.2.70 crores. Atul Paper Pvt. Ltd. paid an amount of Rs.2.01 crores towards sale consideration and possession of the unit was also handed over to the Atul Paper Pvt. Ltd. on 25.04.2018. However, no Sale Deed could be executed in favour of Atul Paper Pvt. Ltd.
(ii) The Corporate Insolvency Resolution Process (“CIRP”) against the CD commenced on 25.09.2019 on an Application filed by M/s Ved Contracts Pvt. Ltd. The Respondent – Rakesh Kumar Jain was appointed as the Resolution Professional (“RP”).
(iii) Atul Paper Pvt. Ltd. along with its two Directors filed a claim of Rs.2.51 crores before the RP. The claim of the Appellant was rejected by the RP on 27.08.2021.
(iv) The RP after coming to know that Atul Paper Pvt. Ltd. is in possession of the commercial unit owned by the CD, filed an IA No.355 of 2021 seeking a direction to Atul Paper Pvt. Ltd. to vacate the premises.
(v) On 16.03.2023, an order was passed by the Adjudicating Authority, directing initiation of liquidation proceedings against the CD.
(vi) On 27.04.2023, Atul Paper Pvt. Ltd. filed a claim of Rs.2.51 crores before the Liquidator, which claim was rejected by the Liquidator on 30.04.2023 on account of claim having been filed with delay. Atul Paper Pvt. Ltd. filed an Appeal under Section 42 of the Insolvency and Bankruptcy Code, 2016 (hereinafter referred to as the “IBC”) being CA No.26 of 2023.
(vii) The Adjudicating Authority permitted the Liquidator to pursue the IA, which was filed by the RP being IA No.355 of 2021. The Adjudicating Authority heard the Liquidator and Atul Paper Pvt. Ltd. along with two Directors, i.e. Atul Kumar Garg and Sachin Kumar Garg and by the impugned order, disposed of IA No.355 of 2021, directing the Atul Paper Pvt. Ltd. to vacate the commercial unit. The Adjudicating Authority also while issuing the said direction, directed the Liquidator to pay an amount of Rs.2.01 crores to the Atul Paper Pvt. Ltd., in event of sale of the above unit by the Liquidator. CA No.26 of 2023, which was an Appeal filed by Atul Paper Pvt. Ltd. challenging the rejection of its claim, was disposed of as having become infructuous.
(viii) Aggrieved by the order passed in IA No.355 of 2021 and CA No.26 of 2023, Company Appeal (AT) (Ins.) Nos.1100 & 1101 of 2024 have been filed by Atul Paper Pvt. Ltd.; Company Appeal (AT) (Ins.) Nos.1311 of 2024 has been filed by the Liquidator, challenging the impugned order insofar as it directed the Liquidator to pay an amount of Rs.2.01 crores. Punjab National Bank – Financial Cred
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.