2026 Supreme(Online)(NCLAT) 248

NATIONAL COMPANY LAW APPELLATE TRIBUNAL
Justice Sharad Kumar Sharma (Member(Judicial)) , Hon'ble Mr. Jatindranath Swain (Member (Technical)) ,
Assistant Commissioner Pudukkottai1circle – Appellant
Versus
Mathur Sabapathy Viswanathan – Respondent
451/CN/2024 COMPANY APPEAL(AT)(INS)



NATIONAL COMPANY LAW APPELLATE TRIBUNAL AT CHENNAI (APPELLATE JU RISDICTION)

Company Appeal (AT) ( CH) (Ins) No. 451/2024 In the matter of:

The Commercial Taxes and Registration Department, Government of Tamil Nadu, Rep. by Jurisdictional Assistant Commissioner, Pudukkottai - I circle, Ground Floor, Commercial Taxes Buildings, Kattupudukkulam, Pudukkottai - 622 001. …Appellant V Thiru. Mathur Sabapathy Viswanathan, The Official Liquidator of M/s. Surya Balaji Steels Pvt. Ltd., ‘A’, Ground Floor, Alamu Apartment, Gandhipuram, Coimbatore – 641 012. ...Respondent Present :

For Appellant : Mr. B. Sandeep Harish, Advocate For Mr. Sathish, AGP For Respondent : Mr. V. Manivannan, Advocate

Order

(Hybrid Mode)

20.02.2026:

Oral Judgment: Justice Sharad Kumar Sharma, Member (Judicial)

A very short controversy requires consideration in the instant Company Appeal. The Appellant, puts a challenge to the impugned order of 11.03.2024, that was rendered by the Learned NCLT, Chennai Bench in TCP/575/IB/CB/2017, whereby the Learned Tribunal by the impugned order of 11.03.2024, while adjudicating upon the Interlocutory Applications preferred by the Appellant being IA(IBC)/1571(CHE)/2023, IA(IBC)/1572(CHE)/2023 & IA(IBC)/1573(CHE)/2023 had rejected the application IA(IBC)/1573(CHE)/2023 preferred under Section 42 of the I & B Code, on the ground that the said application has been filed with more than 600 days of delay and the application IA(IBC)/1572(CHE)/2023, preferred by the Appellant seeking condonation of delay does not contain any reasonable cause and hence the delay cannot be condoned.

2. It is the case of the Appellant herein, that a Field Audit was directed to be conducted for the purposes of an assessment of VAT Tax liability, in relation to the Corporate Debtor i.e., M/s. Surya Balaji Steels Private Limited, the Joint Commissioner (ST), the competent authority, directed the Commercial Tax Officer (Enforcement) to conduct field audits at the registered place of business of Corporate Debtor and at various other places of business of Corporate Debtor and to submit the report and the said field audit report proposal, which was received by the Office of the Joint Commissioner, Pudukkottai – 1 Assessment circle.

3. Further, a revision notice was issued to the dealer, that is, the Corporate Debtor on 03.02.2014 for the purposes of assessment years of 2009-10 to 2013-14. In response to the aforesaid Revision Notice issued by the Joint Commissioner, a reply was submitted by the dealer objecting to the Revision Notice by filing a reply to the said effect on 20.02.2014.

4. However, the Assessment Order was passed on 19.03.2014 assessing the tax liability under the VAT Act for the years 2009-10 to

2013-14, fixing the same as Rs.2,35,88,750/-.

5. The said Assessment Order of 19.03.2014 was put to challenge by the Corporate Debtor before the Hon’ble Madurai Bench of Madras High Court by preferring a Writ Petition, being Writ Petition No.5650 to 5655/14. These Writ Petitions were disposed of, remanding the matter back to Joint Commissioner (ST).

6. Further, a Surprise Inspection was initiated for the financial years

2010-11 to 2014-15 at the registered places of the business of the Corporate Debtor, and the report was submitted on 29.05.2017, based on which notices were served on various dates to the dealer (Corporate Debtor). At that point, the Appellant came to know that the company has been classified as NPA on 21.10.2013, that the bank has initiated action under SARFAESI on 02.01.2015, and that the unit was under their physical possession.

7. Meanwhile, the Corporate Debtor was placed into the CIRP, by an order of the Adjudicating Authority dated 05.10.2017, and consequently, due to the non-receipt of suitable resolution plans, it was later put to liquidation by an order of 29.05.2018. As a consequence of the Corporate Debtor being put to liquidation on 29.05.2018, a public announcement was made by the liquidator for the invitation of claims on 15.06.2018, and

1