2023 Supreme(Online)(NCLT) 1035

NATIONAL COMPANY LAW TRIBUNAL
SAI WARDHA POWER GENERATION LIMITED – Appellant
Versus
PUNJAB & SIND BANK – Respondent


Advocates:
For the Petitioner:MARRIPATI MAHARSHI VISWARAJ

ORDER

1. This is an application filed under Section 60(5) of IBC, 2016 read with Rule 11 of the NCLT Rules, 2016 seeking directions to the Respondent No.1 to issue No-Objection Certificate (“NOC”) for charge satisfaction forthwith (Charge Id 10329502 & 10324285) and enable the Applicant to file the charge satisfaction with ROC/Respondent No.2 and seeking directions to the Respondent No.1 to do all such things that are pre requisite for satisfaction of charges created against the Applicant.

2. Averments made in the Application:

2.1 It is averred that this Tribunal vide its order dated 9th November, 2018 in C.P. (IB) No. 275/7/HBD/2018 admitted the Petition filed by the Original Petitioners i.e., India Opportunities PTE Limited and Vistra ITCL (India) Limited and initiated CIRP of the Applicant/Corporate Debtor and imposed moratorium in accordance with Section 14 of the Code. It is stated that Mr.V.Venkatachalam, was initially appointed as the Interim Resolution Professional ("IRP") and later confirmed by the Committee of Creditors ("CoC) as Resolution Professional ("RP"), for the CIRP.

2.2 It is stated that pursuant to the advertisement of Expression of Interest, consortium of M/s. KCR

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top