2026 Supreme(Online)(NCLT) 7830
IN THE NATIONAL COMPANY LAW TRIBUNAL COURT-V, NEW DELHI
CP IB NO. 226/(ND)/2026
An Application under Section 7 of the Insolvency and Bankruptcy Code, 2016 read with Rule 4 of the Insolvency and Bankruptcy (Application to Adjudicating Authority) Rules, 2016.
IN THE MATTER OF:
PUNJAB AND SIND BANK
Having its Corporate Office At Samvert, 1st Floor, NBCC Building, East Kidwai Nagar, New Delhi-110003
Email: Ho.samvertical@psb.bank.in
…Applicant/Financial Creditor
Versus
AMAN HOSPITALITY PVT. LTD.
Having its Registered Office At L-4, Green Park Extension, New Delhi-110016
Email: ambience@ambiencegroup.in compliance@ambienceisland.com
...Respondent/Corporate Debtor
Order Delivered on: 01.10.2026
CORAM:
SHRI MANNI SANKARIAH SHANMUGA SUNDARAM, HON’BLE MEMBER (JUDICIAL)
MS. REENA SINHA PURI, HON’BLE MEMBER (TECHNICAL)
APPEARANCES:
For the Applicant : Mr. Karan Gandhi, Ms. Riya Jain, Advs.
For the Respondent : Mr. Sunil Fernandez, Sr. Adv., Mr. Anush Raajan, Mr.Pradyumn Yadav, Advs.
SD/- SD/-
(REENA SINHA PURI) (MANNI SANKARIAH SHANMUGA SUNDARAM)
MEMBER (TECHNICAL) MEMBER (JUDICIAL)
ORDER
1. This Application has been filed by Punjab and Sind Bank, the Financial Creditor, under Section 7 of IBC1Insolvency and Bankruptcy Code, 2016 read with Rule 4 of the Insolvency and Bankruptcy Rules2Insolvency and Bankruptcy (Application to Adjudicating Authority) Rules, 2016, seeking initiation of CIRP3Corporate Insolvency Resolution Process against Aman Hospitality Pvt.Ltd., the Corporate Debtor.
2. The Applicant has claimed an aggregate amount comprising two components.The first is a sum of Rs. 67,14,71,913.29, stated to be outstanding towards principal and interest in respect of the credit facilities extended to the Corporate Debtor as on 31.03.2026. The second is a sum of Rs. 177,40,96,104.34, claimed in relation to the amount earlier converted into equity pursuant to the SDR4Strategic Debt Restructuring Scheme.
3. The Applicant, as a member of a consortium of lenders, sanctioned a Term Loan of Rs 50 Crores to the Corporate Debtor on 28.09.2011 for construction of a five-star hotel project at Shahdara, Delhi. The loan and security documents were executed on 29.09.2011. Subsequently, a Cash Credit facility of Rs 35 Crores was sanctioned on 04.09.2012. On a request made by the Corporate Debtor on 26.12.2014, restructuring of the loan account was approved on 30.12.2014, pursuant to which the total exposure, including the FITL5Funded Interest Term Loan, stood enhanced to Rs 95.85 Crores.
4. According to the Applicant, the Corporate Debtor failed to adhere to the repayment obligations even after restructuring and its account continued to remain irregular, with defaults in servicing interest and instalments. Thereafter, pursuant to a revival request dated 30.06.2017 made by the Corporate Debtor, the consortium lenders considered restructuring under the SDR Scheme in the Joint Lenders’ Forum meetings held on 18.07.2017 and 26.07.2017. A Shareholders Subscription cum Conversion Agreement was consequently executed on 09.01.2018, pursuant to which a substantial portion of the outstanding dues was converted into equity shares of the Corporate Debtor. The lenders thereby acquired an aggregate majority shareholding of 51% in the Corporate Debtor. A Supplemental Term Loan Agreement was thereafter executed on 08.03.2018.
5. The restructuring measures, however, did not result in regularisation of the account. The account of the Corporate Debtor was ultimately classified as NPA, Non-Performing Asset on 30.06.2018 with effect from 29.07.2017. The Applicant thereafter issued a demand notice dated 18.09.2018 under Section 13(2) of the SARFAESI Act7Securitisation and Reconstruction of Financial Assets and Enforcement of Security Interest Act, 2002, calling upon the Corporate Debtor to discharge its liabilities within the statutory period of 60 days i.e., upto 17.11.2018. According to the Applicant, the amount remained unpaid.
6. The Applicant further relies upon the financial statements of the Corporate Debtor for the financial years 2019-20 and 2020-21 and various OTS, One-Time Settlement proposals submitted by the Corporate Debtor during the period 2021 to 2024 as acknowledgements of the subsisting liability. The OTS proposals were not accepted by the Applicant.
7. Recovery proceedings were also initiated by the Applicant by filing an Original Application T.A. No. 58/2022 before the Debts Recovery Tribunal (DRT). The proceedings culminated in a final order dated 07.10.2025. By the said order, the DRT crystallised the amount recoverable in respect of the loan facilities at Rs 39,11,96,578.81, together with pendente lite and future interest in terms of the order. The DRT also dealt with the claim relating to the amount converted into equity under the SDR Scheme.
8. Aggrieved by the order dated 07.10.2025, the Corporate Debtor preferred Appeal No. 2004/2025 before the Debts Recovery Appellate Tribunal (DRAT). In connection with the appeal, amounts of Rs 35,72,70,653 and Rs 15,35,77,440 were deposited by the Corporate Debtor before the D