2026 Supreme(Online)(NCLT) 8034

IN THE NATIONAL COMPANY LAW TRIBUNAL COURT-V NEW DELHI BENCH


IN Company Petition IB NO. 309/(ND)/2022


An Application under Section 9 of the Insolvency and Bankruptcy Code, 2016 read with Rule 6 of the Insolvency and Bankruptcy (Application to Adjudicating Authority) Rules, 2016.


IN THE MATTER OF:

M/s Redpro Construction Pvt. Ltd.

8233, Rani Jhansi Road, Near Filmistan Cinema, Delhi – 110006 …Applicant /Operational Creditor

Versus

M/s Skyline Infratech Pvt. Ltd.

Sh. Anil Kumar Vaswani (Director), A-14, Basement, Kailash Colony, New Delhi-110048 …Respondent/Corporate Debtor


Order Delivered on: 01.10.2026


CORAM:SHRI MANNI SANKARIAH SHANMUGA SUNDARAM,

HON’BLE MEMBER (JUDICIAL)

MS. REENA SINHA PURI,

HON'BLE MEMBER (TECHNICAL)


APPEARANCES:

For the Applicant : Ms. Kanika Singhal, Ms. Deepshikha, Advs.

For the Respondent: Adv. Lokesh Garg


In the light of the above facts and circumstances, CP (IB) No. 309/ND/2022 is dismissed.


Sd/- Sd/-


(REENA SINHA PURI) (MANNI SANKARIAH SHANMUGA SUNDARAM)

MEMBER (TECHNICAL) MEMBER (JUDICIAL)

ORDER

1. This Application is filed, by M/s Redpro Construction Pvt Ltd (Applicant/RPC)against M/s Skyline Infratech Pvt Ltd (Respondent/SIPL), seeking initiation of CIRP, Corporate Insolvency Resolution Process. under Section 9 of the IBC, The Insolvency and Bankruptcy Code, 2016.. The Applicant claims Rs. 1,40,96,295 as outstanding operational debt, together with interest at 18% per annum.

2. The Applicant is engaged in the business of construction and civil works. It states that three separate word orders dated 25.08.2017 were issued by the Respondent/SIPL for execution of civil & structural works, internal electrical works and plumbing & firefighting works on a back-to-back basis corresponding to works awarded SIPL by M/s Jaiprakash Associates Limited (JAL). Reference is made to three separate agreements dated 17.07.2017 entered into between SIPL with JAL for execution of the aforesaid works at JAL’s Kensington Boulevard Project, Noida, in respect of Towers Nos. 7, 12, 14, 19, 20, 21 and 22. The terms specified are:

“1. (RPC) shall execute all works as per the BOQ signed between 'SIPL' and 'JAL'.

2. (RPC) shall raise/submit all bills to 'JAL' on behalf of 'SIPL

3. (RPC) shall be responsible for all works at site.

4. (RPC) shall adhere to all the terms and conditions and guidelines.”

3. The said work orders, issued by SIPL under the signature of its Managing Director, Mr Anil Vaswani, also contain a hand written stipulation that the works would be transferred to a new company, in which 50 % of the shareholding would be held equally by Mr Rajan Gupta, Director of RPC, the Applicant Company, and Mr Anil Vaswani, Managing Director of SIPL, the Respondent Company.3Annexure 4 of the Application, pages 80-82

4. It is submitted that the Applicant/ RPC executed the works, raised bills after approval by JAL and maintained a running and recurring account in the name of the Respondent/ SIPL. Payments received were adjusted against earlier unpaid invoices. The last payment amounting to Rs. 9,16,000 is stated to have been received from SIPL on 15.10.2019.

5. According to the Applicant, the Respondent committed default in payment of invoices from the financial year 2017-18. Despite repeated requests for reconciliation and payment, the Respondent failed to do so. Consequently, a demand notice dated 16.09.2021 was issued under Section 8 of the IBC. Thereafter, since the Respondent did not reply or dispute the Demand Notice, transmitted through email dated 27.09.2021, and also failed to pay the outstanding amount, the Applicant filed the present Petition under section 9 of the IBC on 21.02.2022.

6. By order dated 16.10.2023, this Tribunal dismissed the petition on the ground that the claim included invoice RA-E-06 dated 10.05.2020, which was hit by Section 10A. However, in Company Appeal (AT) (Insolvency) No.1630 of 2023, the Hon'ble NCLAT, by judgment dated 21.11.2025, set aside that order and restored CP (IB) No.309/ND/2022 for decision in accordance with law.Following restoration, the parties were heard.

7. It is the plea of the Applicant that the invoices, bank statements and ledger establish debt and default. It is submitted that it made repeated follow-ups with the Respondent through emails, WhatsApp messages, physical meetings and telephonic conversations during 2017-2020. It is further alleged that the Respondent acknowledged the outstanding liability, both orally and in writing, but failed to make payment on one pretext or another. After adjusting all amounts received from the Respondent against the past dues in the running account, a sum of Rs. 1,40,96,295 is stated to be outstanding as on 16.09.2021, which is the subject-matter of the present Application.

8. The Respondent/SIPL disputes this liability. It is submitted that the said work orders communications dated 25.08.2017, issued under the signature of its Managing Director, Mr Anil Vaswani, also contained a hand written sentence stating that the works would be transferred