2023 Supreme(Online)(NGT) 406

Item No.04 (Court No. 2)

BEFORE THE NATIONAL GREEN TRIBUNAL PRINCIPAL BENCH, NEW DELHI (Through Physical Hearing with Hybrid VC Option)

Miscellaneous Application No. 114/2023 In Original Application No.882/2022

1. Mr. Sanjeev Kumar, VPO Barnoh Near Sawmill Tehsil, Una, H.P.

Phone: 9805764510. (cid:133)Applicant Versus

1. Deputy Commissioner, Rupnagar, Mini Secretariat DC, Office Rupnagar, Rupnagar-140001, Punjab. Email: dc.rprpunjab.gov.in.

2. Senior Superintendent of Police, Rupnagar, Office of Senior Superintendent of Police, Government College Road, Rupnagar-140001.

Punjab Email: ssp.rpr.police@punjab.gov.in.

3. Daljit Singh, Nikku Nangal, Tehsil Nangal, District Rupnagar-140124, Punjab.

4. Bachitter Singh, Nikku Nangal, Tehsil Nangal, District Rupnagar-140124, Punjab.

5. Akash Rana, Nangran Village, Tehsil Nangal, District Rupnagar-140124, Punjab.

6. State of Punjab, Through its Chief Secretary, Punjab Civil Secretariat, Chandigarh.

Email: cs@punjab.gov.in.

7. Principal Chief Conservator of Forests (HoFF), Government of Punjab, Forest Complex, Sector 68, SAS Nagar, Mohali-160062, Punjab, Email: pccfcomplex@gmail.com.

8. District Magistrate, Rupnagar, Mini Secretariat, Near Bus Stand, Rupnagar, Punjab-140001.

Email: div.com.rpr@punjab.gov.in.

9. State of Himachal Pradesh, Through Chief Secretary, Government of Himachal Pradesh, Multi-Purpose Projects and Power, Non-Conventional Energy Sources, Chairman Himachal Pradesh, State Electricity Board Limited, Email Address: cshp@nic.in.

10. Principal Chief Conservator of Forests (H.O.F.F.)

Government of Himachal Pradesh, Talland, Milsington Estate, Chotta Shimla, Shimla, Himachal Pradesh 171002, Email Address: hp067@ifs.nic.in.

11. District Magistrate, Una, Secretariat, Una, Himachal Pradesh-174303.

Email: dc-una-hp@nic.in. (cid:133) Respondents For the Applicant:

None for the applicant. For the Respondents:

Ms. Nupur Kumar, Advocate for respondent no. 1-DC Rupnagar.

Mr. Kartik K Sood, Advocate for respondent no. 10-PCCF (Hoff), H.P. and respondent no. 11-DC, Una.

Ms. Preeti Yadav, IAS, DC, Rupnagar (through VC).

Shri Jatin Lal, IAS, DC, Una (through VC). Mr. Sushil Kumar DFO, Una (through VC).

PRESENT:

HON(cid:146)BLE MR. JUSTICE ARUN KUMAR TYAGI, JUDICIAL MEMBER HON(cid:146)BLE DR. AFROZ AHMAD, EXPERT MEMBER Judgment Reserved on:- 12.03.2024 Judgment pronounced on :- 05.07.2024 Application under provisions of the National Green Tribunal Act, 2010.

JUDGMENT

PRONOUNCED BY: HON(cid:146)BLE MR. JUSTICE ARUN KUMAR TYAGI, JM

1. The applicant filed O.A. No. 882/2022 complaining about illegal felling of trees from a small forest owned and possessed by the Himachal Pradesh Forest Department.

2. The applicant submitted in the application that land measuring about 281 Kanal Marla situated at Nangal Township is owned and possessed by the Himachal Pradesh Forest Department where number of trees were planted and with passage of time, the land became a small forest. In the Revenue record, the land is recorded as Makbooja Mehkama Timber Market. The Punjab Government Revenue Department willfully misplaced the revenue record of village Nikku Nangal. Some local persons prepared wrong revenue map and claimed the land and trees standing over the same as belonging to them. During July, 2018 30 trees, one Shisham and 29 Eucalyptus, were illegally cut by some persons in collusion with Punjab PWD and B & R Br Construction Division, Ropar. Himachal Pradesh Forest Department requested for registration of FIR against the persons involved but the Punjab Police did not register any FIR. Some local persons have illegally cut 25 trees standing on the above said land. The Himachal Pradesh Forest Department requested for registration of FIR but no FIR is registered so far. If cognizance of the matter is not taken, the entire valuable small forest will be destroyed which will also damage the river bank and increase the soil erosion and endanger the Nangal Dam stability.

3. Vide order dated 19.12.2022 notices were ordered to be issued to the respondents and this Tribunal constituted a Joint Committee with direction to verify the factual position and submit its report. The relevant part of the order reads as under:-

" 4. In view of the averments made in the application, we consider it appropriate to have response of respondents (1) Deputy Commissioner, Rupnagar, (2) Senior Superintendent of Police, Rupnagar, (3) Daljit Singh, (4) Bachitter Singh and (5) Akash Rana already impleaded in the application as respondents no. 1 to 5 as well as (6) State of Punjab through Chief Secretary, Government of Punjab; (7) the Principal Chief Conservator of Forests (HoFF), Government of Punjab and (8) District Magistrate, Rupnagar; (9) State of Himachal Pradesh through Chief Secretary, Government of Himachal Pradesh; (10) the Principal Chief Conservator of Forests (HoFF), Government of Himachal Pradesh and (11) District Magistrate, Una, who stand , impleaded as respondents No. 6 to

11. The Registry is directed to amend memo of parties to the application and issue notices to respondents No. 1 to 11.

5. In view of the averments made in the application, we also consider it appropriate that a Joint Committee be constituted to verify the factual position. Accordingly, we constitute a Joint Committee comprising of the Principal Chief Conservators of Forests, Governments of Puniab and Himachal Pradesh and Punjab State Pollution Control Boards and the Deputy Commissioners, Rupnagar and Una and direct the same, to meet within two weeks, undertake visits to the site, look into the grievances of the applicant, associate the applicant and representative of the concerned project proponent, verify the factual position and submit its Report within two months by e- mail at judicial-ngt@gov.in preferably in the form of searchable PDF/OCR Supported PDF and not in the form of Image PDF. The State PCB will be the nodal agency for coordination and compliance."

4. In compliance thereof, report of the Joint Committee was submitted vide email dated 16.03.2023. The relevant part of the report is reproduced below:-

(cid:147)X X X X

 Meeting of the Joint Committee:

In Compliance of order dated 19.12.2022 of the Hon’ble National Green Tribunal, the meeting of the Joint Committee was held on 30.12.2022 in the Shakti Sadan Guest House of Bhakhra Beas Management Board (Power -Wing) at Nangal, in the presence of the complainant Sh. Sanjeev Kumar, the officers of Pu