2024 Supreme(Online)(NGT) 4326

NATIONAL GREEN TRIBUNAL NEW DELHI (PRINCIPAL BENCH)
Sudhir Agarwal, JM, Afroz Ahmad, EM
Sach Sewa Samiti Trust – Appellant
Versus
Ministry of Environment Forest and Climate Change – Respondent
Original Application No. 908/2022 | IA No. 370/2024



Advocates:
For the Appellants/Petitioners: Mr. Deepak Kohli, Mr. Mohd. Shariq, Mr. Amit Kharbanda, Mr. Abhishsek Yadav
For the Respondents: Mr. Shariq Ahmed, Mr. Ankit Verma, Mr. Ravindra Kumar, Mr. Shivam Saxena, Mr. Vipin Kumar Saxena, Mr. Pradeep Misra, Mr. Daleep Dhyani, Mr. Deepak Dhingra, Mr. Pushkar, Ms. Sneh Somani, Ms. Ritu Dhingra

Plot development cannot infringe upon designated green belt areas. Environmental clearances are mandatory for construction activities to ensure ecological protection.

Headnote:(A) National Green Tribunal Act, 2010 - Sections 14 and 15 - Allegations of environmental damage due to allotment of land from green belt for commercial use - Applicant alleged that residential development on green belt area damages ecology and violates sustainable development principles. Respondents denied encroachment on green areas and confirmed compliance with environmental regulations. The Court ruled that the claims of the applicant lacked substantial evidence and directed pollution control authorities to enforce environmental laws where applicable. (Paras 1-27)

(B) Environmental Clearance - Requirement for compliance with Environment Impact Assessment Notification - The tribunal emphasized the necessity of obtaining requisite environmental clearances before undertaking development activities. Violations subject to penalty. (Paras 6, 26)

Table of Content
1. allegations of environmental damage due to land allotment (Para 1 , 2 , 3 , 4 , 5)
2. necessity of environmental compliance and permits (Para 6 , 12)
3. claims against authorities concerning illegal allotments (Para 20 , 21)
4. final observations and directives regarding environmental compliance (Para 25 , 26 , 27)

ORDER

1. Applicant, Sach Sewa Samiti Trust through President, Yatender Kumar Bhati (hereinafter referred to as ‘applicant’) had filed this original application under Section 14 and 15 of National Green Tribunal, Act 2010 (hereinafter referred to as ‘NGT Act, 2010’) alleging that Greater NOIDA Authority through Chief Executive Officer (hereinafter referred to as ‘respondent4’) has developed Knowledge Park-I, which is an educational region in Southern Western Greater Noida. Object of establishing Knowledge Park-I was to establish various universities and colleges in the vicinity. Knowledge Park-I was developed after acquiring land of village Tugalpur of Haldona, District Gautambudh Nagar, Uttar Pradesh. A layout plan of Knowledge Park-I was prepared wherein institutional areas and residential areas have been duly earmarked and notified separately. As per layout plan, which is based on Master Plan notification there was a green area/belt admeasuring 10,500 square meters falling in between Plot No. 12 and 22, left for maintaining ecology and environment. Copy of proposed Layout Plan of Knowledge Park-1 has been placed on record as Annexure A-2, page 36. Respondent 4 granted a license of 10,500 square meter green area to one Viren Singh, S/o Nawab Singh for plantation, nursery, floriculture, etc., for a period of 20 years vide license agreement dated 27.05.2003. This shows that land was actually left for making area green and license was granted to adhere to the said objective. Further, there is a High Tension wire of 1,10,000 watt passing through ‘green area’. Area under High Tension line was also to be kept vacant. One Rajendra Singh son, of Mehtab Singh i.e. respondent 7 had encroached upon a piece of land measuring 1000 square metres approximately on ‘green belt’ situated between Plot No. 12 and 22 of Knowledge Park-I, Greater NOIDA.

2. Applicant when got knowledge of this encroachment, made complaint, sent several interrogatories to Authorities to find out real fact and therefrom came to know that respondent 7 made a representation on behalf of Ms. Shwetna and Madhu Singh i.e. respondents 8 and 9 to officials of respondent 4 stating that two pieces of land i.e. Plot No. 10 and 12, area 1710 sq. mtr and 1630 sq. mtr were allotted in Village Tusiyana in lieu of acquisition of land in furtherance of allotment of 6% land to affected farmers. Respondent 7 however requested Authorities to allot land in place of Village Tusiyana to Tugalpur Haldona. Pursuant to said request, respondent 4 carved out Plot No. A-1 out of green belt from Knowledge Park-I, in active connivance with respondent 7. Vide letter dated 10.11.2024 respondents 8 and 9 were informed that respondent 4 had allotted Plot No. A-I of Village Tugalpur Haldona, area 870 sq. mtr, and for remaining area, respondent 4 would consider in future. Respondent 8 and 9 were also informed that their allotment of land at Village Tusiyana stands cancelled with immediate effect. Subsequently, vide letter dated 27.11.2024, respondent 4 informed respondents 8 and 9 that area of Plot No. A-1 has reduced from 870 sq. mtr to 691 sq. mtr which ultimately resulted in reduction in amount demanded from respondent 8 and 9. Lease deed 27.11.2024 was executed in respect of Plot No. A-I, Village Tugalpur Haldona, area 691 sq. mtr in favor of respondent 8 and 9 which shows that officials of respondent 4 and 7 have worked and functioned, hands in gloves with each other. After execution of lease deed, Building Plan was submitted for raising construction on Plot No. A-1 vide application dated 06.09.2015 but no such plan has been approved till date.

3. Grievance of applicant is t